Chapter 4, Problem 7QQ
Program Description Answer

A Gantt chart is not normally included in a project charter.

Hence, correct answer is option “D”.

Blurred answer
Students have asked these similar questions
Which of the following statements is false?     A work breakdown structure is a hierarchical structure that identifies the project’s resources by category and type.     Duration and effort are not synonymous terms.         A three-point estimate includes an optimistic, most likely, and pessimistic estimate.     A Gantt chart is a common tool for displaying project schedule information.
short answer a project has the following general attributes. A project has an established objective. A project has a beginning and an end. A project is unique. A project has schedule, cost, and scope constraints. A project needs resources. whats are the specifics about one of the attributes of the Getta Byte Software - New Billing System project
What is the name of the tool that can be used to allocate the project resources?
Knowledge Booster
Background pattern image
Similar questions
Recommended textbooks for you
Text book image
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning
Text book image
Management Of Information Security
Computer Science
ISBN:9781337405713
Author:WHITMAN, Michael.
Publisher:Cengage Learning,