Textbook Question
Book Icon
Chapter 4, Problem 9P

Tuff-Rider, Inc. manufactures touring bikes and mountain bikes in a variety of frame sizes, colors, and component combinations. Identical bicycles are produced in lots of 100. The projected demand, lot size, and time standards are shown in the following table.

Chapter 4, Problem 9P, Tuff-Rider, Inc. manufactures touring bikes and mountain bikes in a variety of frame sizes, colors,

The shop currently works 8 hours a day, 5 days a week, 50 weeks a year. It operates five workstations, each producing one bicycle in the time shown in the table. The shop maintains a 15 percent capacity cushion. How many workstations will be required next year to meet expected demand without using overtime amid without decreasing the firm’s current capacity cushion?

Blurred answer
Students have asked these similar questions
Tuff-Rider, Inc., manufactures touring bikes and mountain bikes in a variety of frame​ sizes, colors, and component combinations. Identical bicycles are produced in lots of 110. The projected​ demand, lot​ size, and time standards are shown in the following​ table: Item Touring Mountain Demand forecast 4,000 ​units/year 12,000 ​units/year Lot size 100 units 110 units Standard processing time 0.25 ​hour/unit 0.50 ​hour/unit Standard setup time 2​ hours/lot 3​ hours/lot The shop currently works 8 hours a​ day, 5 days a​ week, 52 weeks a year. It operates five​ workstations, each producing one bicycle in the time shown in the table. The shop maintains a 15 percent capacity cushion. How many workstations will be required next year to meet expected demand without using overtime and without decreasing the​ firm's current capacity​ cushion? The number of workstations required next year is ?​(Enter your response rounded up to the next whole number.​)
Tuff-Rider, Inc., manufactures touring bikes and mountain bikes in a variety of frame sizes, colors, and component combinations. Identical bicycles are produced in lots of 100. The projected demand, lot size, and time standards are shown in the following table: Item Touring Mountain Demand forecast Lot size Standard processing time Standard setup time 5,000 units/year 100 units .25 hour/unit 2 hours/lot 10,000 units/year 100 units .50 hour/unit 3 hours/lot The shop currently works 8 hours a day, 5 days a week, 50 weeks a year. It operates five workstations, each producing one bicycle in the time shown in the table. The shop maintains a 15 percent capacity cushion. How many workstations will be required next year to meet expected demand without using overtime and without decreasing the firm’s current capacity cushion?
​Tuff-Rider, Inc., manufactures touring bikes and mountain bikes in a variety of frame​ sizes, colors, and component combinations. Identical bicycles are produced in lots of 90. The projected​ demand, lot​ size, and time standards are shown in the following​ table:                                                                                                                                  LOADING... Item Touring Mountain Demand forecast 4,000 ​units/year 12,000 ​units/year Lot size 110 units 90 units Standard processing time 0.30 ​hour/unit 0.75 ​hour/unit Standard setup time 2​ hours/lot 3​ hours/lot   The shop currently works 8 hours a​ day, 5 days a​ week, 50 weeks a year. It operates five​ workstations, each producing one bicycle in the time shown in the table. The shop maintains a 15 percent capacity cushion. How many workstations will be required next year to meet expected demand without using overtime and without decreasing…

Chapter 4 Solutions

Operations Management: Processes and Supply Chains, Student Value Edition Plus MyLab Operations Management with Pearson eText -- Access Card Package (12th Edition)

Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY