Textbook Question
Chapter 5, Problem 29E
Methods of Estimating Costs: Engineering Estimates
Custom Homebuilders (CH) designs and constructs high-end homes on large lots owned by customers. CH has developed several formulas, which it uses to quote jobs. These include costs for materials, labor, and other costs. These estimates are also dependent on the region of the country a particular customer lives. Below are the cost estimates for one region in the Midwest:
Required
A customer has expressed interest in having CH build a moderate, 3,000 square-foot home on a vacant lot, which does not have utilities. Based on the engineering estimates above, what will such a house cost to build?
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
Custom Homebuilders (CH) designs and constructs high-end homes on large lots owned by customers. CH has developed several formulas, which it uses to quote jobs. These include costs for materials, labor, and other costs. These estimates are also dependent on the region of the country a particular customer lives. The following are the cost estimates for one region in the Midwest.
Administrative costs
$
36,000
Building costs – per square foot (basic)
$
100
Building costs – per square foot (moderate)
$
180
Building costs – per square foot (luxury)
$
240
Appliances (basic)
$
31,000
Appliances (moderate)
$
41,000
Appliances (luxury)
$
61,000
Utilities costs (if required)
$
56,000
Required:
A customer has expressed interest in having CH build a moderate, 4,600 square-foot home on a vacant lot, which does not have utilities. Based on the engineering estimates above, what will such a house cost to build?
Using variable costing, service company
Henry’s Helpers provides locksmith services. One type of service call is to evaluate private residences for security concerns and make recommendations for Safety plan. Use the data below to determine the company’s total contribution margin, contribution margin per service call, and contribution margin ratio when 220 service calls are made in the month of June.
An assisted-living facility provides services in the form of residential space, meals, and other occupant assistance (OOA) to its occupants. The facility currently uses a traditional cost accounting system that charges each occupant a daily rate equal to the facility’s annual cost of providing residential space, meals, and OOA divided by total occupant days. However, an activity-based costing (ABC) analysis has revealed that occupants’ use of OOA varies substantially. This analysis determined that occupants could be grouped into three categories (low, moderate, and high usage of OOA) and that the activity driver of OOA should be nursing hours. The driver of the residential space and meals is occupant days. The following quantitative information was also provided:
OccupantCategory
AnnualOccupantDays
AnnualNursingHours
Low usage
36,000
90,000
Medium usage
18,000
90,000
High usage
6,000
120,000…
Chapter 5 Solutions
Fundamentals Of Cost Accounting (6th Edition)
Ch. 5 - What are the common methods of cost estimation?Ch. 5 - Prob. 2RQCh. 5 - Under what conditions is the engineering estimates...Ch. 5 - If one wishes simply to prepare a cost estimate...Ch. 5 - When using cost estimation methods based on past...Ch. 5 - Prob. 6RQCh. 5 - What is the difference between R2 and adjusted R2?Ch. 5 - Why are accurate cost estimates important?Ch. 5 - What are three practical implementation problems...Ch. 5 - Why is it important to incorporate learning into...
Ch. 5 - What are some complications that can arise when...Ch. 5 - The following costs are labeled fixed or variable...Ch. 5 - Prob. 13CADQCh. 5 - When preparing cost estimates for account analysis...Ch. 5 - How can one compensate for the effects of price...Ch. 5 - Prob. 16CADQCh. 5 - Prob. 17CADQCh. 5 - A decision maker is interested in obtaining a cost...Ch. 5 - Consider the Business Application item Using...Ch. 5 - A friend comes to you with the following problem....Ch. 5 - After doing an account analysis and giving the...Ch. 5 - In doing cost analysis, you realize that there...Ch. 5 - Prob. 23CADQCh. 5 - Are learning curves likely to affect materials...Ch. 5 - McDonalds, the fast-food restaurant, is known for...Ch. 5 - Prob. 26CADQCh. 5 - A manager asks you for a cost estimate to open a...Ch. 5 - Prob. 28CADQCh. 5 - Methods of Estimating Costs: Engineering Estimates...Ch. 5 - Prob. 30ECh. 5 - Methods of Estimating Costs: Engineering Estimates...Ch. 5 - Prob. 32ECh. 5 - Methods of Estimating Costs: Account Analysis The...Ch. 5 - Methods of Estimating Costs: Account Analysis...Ch. 5 - Methods of Estimating Costs: High-Low, Ethical...Ch. 5 - Methods of Estimating Costs: High-Low Adriana...Ch. 5 - Methods of Estimating Costs: High-Low
Adriana...Ch. 5 - Prob. 38ECh. 5 - Adriana Corporation manufactures football...Ch. 5 - Methods of Estimating Costs: Simple...Ch. 5 - Prob. 41ECh. 5 - Methods of Estimating Costs: High-Low Davis Stores...Ch. 5 - Methods of Estimating Costs: Scattergraph Prepare...Ch. 5 - Prob. 44ECh. 5 - Interpretation of Regression Results: Multiple...Ch. 5 - Interpretation of Regression Results Brodie...Ch. 5 - Prob. 47ECh. 5 - Interpretation of Regression Results: Simple...Ch. 5 - Learning Curves Assume that General Dynamics,...Ch. 5 - Learning Curves Assume that Whee, Cheatham, and...Ch. 5 - Prob. 51ECh. 5 - Learning Curves (Appendix B) Refer to the example...Ch. 5 - Prob. 53PCh. 5 - Prob. 54PCh. 5 - Regressions from Published Data Obtain 13 years of...Ch. 5 - Prob. 56PCh. 5 - High-Low Method, Scattcrgraph Cubicle Solutions...Ch. 5 - High-Low Method, Scattcrgraph Academy Products...Ch. 5 - High-Low, Scattergraph, Issues with Data
Wyoming...Ch. 5 - Interpretation of Regression Results: Simple...Ch. 5 - Interpretation of Regression Results: Simple...Ch. 5 - Interpretation of Regression Results: Multiple...Ch. 5 - Interpretation of Regression Results: Simple...Ch. 5 - Interpretation of Regression Results Brews 4 U is...Ch. 5 - Cost Estimation: Simple Regression The following...Ch. 5 - Prob. 68PCh. 5 - Methods of Cost Analysis: Account Analysis, Simple...Ch. 5 - Learning Curves (Appendix B) Refer to the example...Ch. 5 - Learning Curves (Appendix B) Krylon Company...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Pocket Umbrella, Inc. is considering producing a new type of umbrella. This new pocket-sized umbrella would fit into a coat pocket or purse. Classify the following costs of this new product as direct materials, direct labor, manufacturing overhead, or selling and administrative. Cost of advertising the product Fabric used to make the umbrellas Maintenance of cutting machines used to cut the umbrella fabric so it will fit the umbrella frame Wages of workers who assemble the product Presidents salary The salary of the supervisor of the people who assemble the product Wages of the product tester who stands in a shower to make sure the umbrellas do not leak Cost of market research survey Salary of the companys sales managers Depreciation of administrative office buildingarrow_forwardHicks Contracting collects and analyzes cost data in order to track the cost of installing decks on new home construction jobs. The following are some of the costs that they incur. Classify these costs as fixed or variable costs and as product or period costs. Lumber used to construct decks ($12.00 per square foot) Carpenter labor used to construct decks ($10 per hour) Construction supervisor salary ($45,000 per year) Depreciation on tools and equipment ($6,000 per year) Selling and administrative expenses ($35,000 per year) Rent on corporate office space ($34,000 per year) Nails, glue, and other materials required to construct deck (varies per job)arrow_forwardTarget costs, effect of process-design changes on service costs. Solar Energy Systems (SES) sells solar heating systems in residential areas of eastern Pennsylvania. A successful sale results in the homeowner purchasing a solar heating system and obtaining rebates, tax credits, and financing for which SES completes all the paperwork. The company has identified three major activities that drive the cost of selling heating systems: identifying new contacts (varies with the number of new contacts); traveling to and between appointments (varies with the number of miles driven); and preparing and filing rebates and tax forms (varies with the number of solar systems sold). Actual costs for each of these activities in 2016 and 2017 are:arrow_forward
- Hicks Contracting collects and analyzes cost data in order to track the cost of installing decks on new home construction jobs. The following are some of the costs that they incur. Classify these costs as fixed or variable costs and as product or period costs. A. Lumber used to construct decks ($12.00 per square foot) B. Carpenter labor used to construct decks ($10 per hour) C. Construction supervisor salary ($45,000 per year) D. Depreciation on tools and equipment ($6,000 per year) E. Selling and administrative expenses ($35,000 per year) F. Rent on corporate office space ($34,000 per year) G. Nails, glue, and other materials required to construct deck (varies per job)arrow_forwardIn which production setting is operation costing most appropriate? a) Custom automobile repair shop b) Landscaping business c) Oil refinery d) Clothing manufacturer I think it's (d) but to make sure,, i need your help..arrow_forwardThe KMP Metal Machining Company produces widgets according to customer order. The company has determined that widgets can be produced on three different machine tools: M1, M2, or M3. An analysis of widget production cost reveals the following data: Solve, a. Using a graphical approach, determine the most economical machine tool to use for all order sizes between 1 and 200 units. In other words, determine the subranges within the overall range of 1 to 200 for which each machine tool is preferred. b. Using an algebraic approach, determine the most economical machine tool to use for all order sizes between 1 and 200 units. c. For an order of size 75, which machine tool should be used to produce the order, and what is the total production cost? d. For an order of size 160, assume that the preferred (most economical) machine is unavailable. What penalty (expressed in dollars of additional production cost) must be paid if the second most economical machine is used? The third?arrow_forward
- Activity-Based Costing; Customer Group Cost Analysis Franklin Furniture Inc. (FFI) manufactures bedroom furniture in sets (a set includes a dresser, two queen-size beds, and one bedsidetable) for use in motels and hotels. FFI has three customer groups, which it calls the value, quality,and luxury groups. The value products are targeted to low-price motels that are looking for simplefurniture, while the luxury furniture is targeted to the very best hotels. The value line is attractive toa variety of hotels and motels that appreciate the combination of quality and value. Currently therehas been a small increase in the quality and value lines, and an appreciable increase in demand in theluxury line, reflecting cyclical changes in the marketplace. Luxury hotels are now in more demandfor business travel, while a few years ago, the value segment was the most popular for business travelers. FFI wants to be able to respond to the increased demand with increased production but worriesabout the…arrow_forwardClassify the following costs of this new product as direct materials, direct labor, manufacturing overhead, selling, or administrative 1. President's salary. 2. Packages used to hold the skin wipes. 3. Cleaning materials used to clean the skin wipe packages. 4. Wages of workers who package the product. 5. Cost of advertising the product. 6. The salary of the supervisor of the workers who package the product. 7. Cost accountant's salary (the accountant works in the factory). 8. Cost of a market research survey. 9. Sales commissions paid as a percent of sales. 10. Depreciation of administrative office building. Problem B Classify the costs listed in the previous problem as either product costs or period costs.arrow_forwardPatterson Lawn Co. wants to determine the cost of each lawn care maintenance job. The Company has two operating departments, one that performs lawn care services for commercial properties and one that services residential properties. Both operating departments are supported by two service departments, administrative and machine maintenance. Costs for each of these supporting departments are as follows: Administrative Machine Maintenance Total cost $576,000 $3,825,000 The following estimates that are related to the operating departments is as follows: Commercial Residential Total properties properties # of employees 68 60 128 # of customers 225 260 485 # of billable hours 23,000 22,000 45,000 Total overhead cost* $ 525,000 $ 450,000 $ 975,000 *Note that total overhead cost includes costs allocated from service departments and other overhead costs. The Company uses the…arrow_forward
- Cost Estimation; Machine Replacement; Ethics Hardison Inc. manufactures glass for officebuildings in Florida. As a result of age and wear, a critical machine in the production process hasbegun to produce quality defects. Hardison is considering replacing the old machine with a newmachine, either brand A or brand B. The manufacturer has provided Hardison with the following dataon the costs of operation of each machine brand at various levels of output:Output(square yards)Brand AEstimated Total CostsBrand BEstimated Total Costs2,000 $ 97,000 $ 120,0004,000 125,000 160,0008,000 180,000 200,00016,000 225,000 260,00032,000 280,000 300,00064,000 438,000 368,000Required1. Graph the data for the two brands of machines.2. Use the high-low method to determine the cost equation for each brand of machine and use the results tocalculate the costs of operating each machine if Hardison’s output is expected to be 25,000 square yardsarrow_forwardI need help solving the following problem. Elizabeth Flanigan and Associates is an engineering and design firm that specializes in developing plans for recycling plants for municipalities. The firm uses a job costing system to accumlate the cost associated with each design project. Flanigan employs three levels of employee: senior engineers, associate engineers, and clerical staff. The salary cost of the clerical staff is included in overhead, along with the cost of engineering supplies, automobile travel, and equipment depreciation. The cost of airline travel, motels, building permits, and fees from other consultants is charged to each project as direct materials. Overhead is applied to projects using a predetermined overhead rate based on total engineering hours. The rate for 20X0 is $5 per hour. The six different salary levels for 20X1 for the employees of Elizabeth Flanigan and Associates are listed below. The hourly rate is determined by dividing the yearly salary by 2,000…arrow_forwardMariah Enterprises makes a variety of consumer electronic products. Its camera manufacturing plant is considering choosing between two different processes, named Alpha and Beta, which can be used to make two component parts A and B. To make the correct decision, the managers would like to compare the labor and multifactor productivity of process Alpha with that of process Beta. The value of process output for component A and B are $175 and $140 per unit, respectively. The corresponding overhead costs are $6,000 and $5,000, respectively. Process Alpha Process Beta Product A B C D Output (units) 50 60 30 80 Labor ($) $1,200 $1,400 $1,000 $2,000 Material ($) $2,500 $3,000 $1,400 $3,500 a. Which process, Alpha or Beta, is more productive? b. What conclusions can you draw from your analysis?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,Managerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage Learning
- Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegeCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
How to Estimate Project Costs: A Method for Cost Estimation; Author: Online PM Courses - Mike Clayton;https://www.youtube.com/watch?v=YQ2Wi3Jh3X0;License: Standard Youtube License