OPERATIONS MANAGEMENT CUSTOM 12E >C<
OPERATIONS MANAGEMENT CUSTOM 12E >C<
18th Edition
ISBN: 9781323889503
Author: HEIZER
Publisher: PEARSON C
bartleby

Videos

Textbook Question
Book Icon
Chapter 7, Problem 1.1VC

Process Strategy at Wheeled Coach

Wheeled Coach, based in Winter Park, Florida, is the world’s largest manufacturer of ambulances. Working four 10-hour days each week, 350 employees make only custom-made ambulances; virtually every vehicle is unique. Wheeled Coach accommodates the marketplace by providing a wide variety of options and an engineering staff accustomed to innovation and custom design. Continuing growth, which now requires that more than 20 ambulances roll off the assembly line each week, makes process design a continuing challenge. Wheeled Coach’s response has been to build a focused factory: Wheeled Coach builds nothing but ambulances. Within the focused factory, Wheeled Coach established work cells for every major module feeding an assembly line, including aluminum bodies, electrical wiring harnesses, interior cabinets, windows, painting, and upholstery.

Labor standards drive the schedule so that every work cell feeds the assembly line on schedule, just-in-time for installations. The chassis, usually that of a Ford truck, moves to a station at which the aluminum body is mounted. Then the vehicle is moved to painting. Following a custom paint job, it moves to the assembly line, where it will spend 7 days. During each of these 7 workdays, each work cell delivers its respective module to the appropriate position on the assembly line. During the first day, electrical wiring is installed; on the second day, the unit moves forward to the station at which cabinetry is delivered and installed, then to a window and lighting station, on to upholstery, to fit and finish, to further customizing, and finally to inspection and road testing, The Global Company Profile featuring Wheeled Coach, which opens Chapter 14, provides further details about this process.

Discussion Questions*

1. Why do you think major auto manufacturers do not build ambulances?

2. What is an alternative process strategy to the assembly line that Wheeled Coach currently uses?

3. Why is it more efficient for the work cells to prepare “modules” and deliver them to the assembly line than it would be to produce the component (e.g., interior upholstery) on the line?

4. How does Wheeled Coach manage the tasks to be performed at each work station?

*You may wish to view the video that accompanies this case before addressing these questions.

Blurred answer
Students have asked these similar questions
Process Strategy at Wheeled Coach Wheeled Coach, based in Winter Park, Florida, is the world’s largest manufacturer of ambulances. Working four 10-hour days each week, 350 employees make only custom-made ambulances; virtually every vehicle is unique. Wheeled Coach accommodates the marketplace by providing a wide variety of options and an engineering staff accustomed to innovation and custom design. Continuing growth, which now requires that more than 20 ambulances roll off the assembly line each week, makes process design a continuing challenge. Wheeled Coach’s response has been to build a focused factory: Wheeled Coach builds nothing but ambulances. Within the focused factory, Wheeled Coach established work cells for every major module feeding an assembly line, including aluminum bodies, electrical wiring harnesses, interior cabinets, windows, painting, and upholstery. Labor standards drive the schedule so that every work cell feeds the assembly line on schedule, just-in-time for…
PROCESS STRATEGY AT WHEELED COACH     Wheeled Coach, based in Winter Park, Florida, is the world’s largest manufacturer of ambulance. Working four 10 hour days each week, 350 employees make only custom-made ambulances. Virtually every vehicle is unique. Wheeled Coach accommodates the marketplace by providing a wide variety of options and an engineering staff accustomed to innovation and custom design. Continuing growth, which now requires that more than 20 ambulances roll off the assembly line each week, makes process design a continuing challenge. Wheeled Coach’s response has been to build a focused factory. Wheeled Coach established work cells for every major module feeding an assembly line, including aluminum bodies, electrical wiring harnesses, interior cabinets, windows, painting, and upholstery.   Labor standards drive the schedule so that every work cell feed the assembly line on schedule, just-in-time for installations. The chassis, usually that of a Ford truck, moves to a…
Why is a process table needed in a timesharing system and what are the field in   a typical process table entry?

Chapter 7 Solutions

OPERATIONS MANAGEMENT CUSTOM 12E >C<

Ch. 7.S - Prob. 11DQCh. 7.S - Prob. 12DQCh. 7.S - What are the techniques available to operations...Ch. 7.S - Amy Xias plant was designed to produce 7,000...Ch. 7.S - For the post month, the plant in Problem S7.1,...Ch. 7.S - Prob. 3PCh. 7.S - Prob. 4PCh. 7.S - Prob. 5PCh. 7.S - The effective capacity and efficiency for the next...Ch. 7.S - Southeastern Oklahoma State Universitys business...Ch. 7.S - Prob. 8PCh. 7.S - Prob. 9PCh. 7.S - Prob. 10PCh. 7.S - The three-station work cell illustrated in Figure...Ch. 7.S - The three-station work cell at Pullman Mfg., Inc....Ch. 7.S - The Pullman Mfg., Inc., three-station work cell...Ch. 7.S - Prob. 14PCh. 7.S - 10 minutes per unit. Part 2 is simultaneously...Ch. 7.S - Prob. 16PCh. 7.S - Prob. 17PCh. 7.S - Using the data in Problem S7.17: a) What is the...Ch. 7.S - Prob. 19PCh. 7.S - Prob. 20PCh. 7.S - Prob. 21PCh. 7.S - Prob. 22PCh. 7.S - Prob. 23PCh. 7.S - Prob. 24PCh. 7.S - Prob. 25PCh. 7.S - Prob. 26PCh. 7.S - Prob. 27PCh. 7.S - Prob. 32PCh. 7.S - Prob. 33PCh. 7.S - Prob. 34PCh. 7.S - Prob. 35PCh. 7.S - Prob. 36PCh. 7.S - Prob. 37PCh. 7.S - Prob. 38PCh. 7.S - Prob. 39PCh. 7.S - Prob. 1VCCh. 7.S - a capacity expansion plan and a new 11-story...Ch. 7.S - a capacity expansion plan and a new 11-story...Ch. 7 - Ethical Dilemma For the sake of efficiency and...Ch. 7 - Prob. 1DQCh. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - Prob. 4DQCh. 7 - Prob. 5DQCh. 7 - Prob. 6DQCh. 7 - Prob. 7DQCh. 7 - Prob. 8DQCh. 7 - Prob. 9DQCh. 7 - Prob. 10DQCh. 7 - Prob. 11DQCh. 7 - Prob. 12DQCh. 7 - Prob. 13DQCh. 7 - Prob. 14DQCh. 7 - Prob. 15DQCh. 7 - Prob. 16DQCh. 7 - Prob. 17DQCh. 7 - Prob. 18DQCh. 7 - Prob. 19DQCh. 7 - Prob. 1PCh. 7 - Usingthedatain Problem 7.1, determinethemost...Ch. 7 - Prob. 3PCh. 7 - Refer to Problem 7.1. If a contract for the second...Ch. 7 - Stan Fawcetts company is considering producing a...Ch. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Metters Cabinets, Inc., needs to choose a...Ch. 7 - Prob. 10PCh. 7 - Nagle Electric. Inc., of Lincoln, Nebraska, must...Ch. 7 - Stapleton Manufacturing intends to increase...Ch. 7 - Prepare a flowchart for one of the following: a)...Ch. 7 - Prepare a process chart for one of the activities...Ch. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 1CSCh. 7 - Prob. 2CSCh. 7 - Prob. 3CSCh. 7 - Process Strategy at Wheeled Coach Wheeled Coach,...Ch. 7 - Prob. 1.2VCCh. 7 - Prob. 1.3VCCh. 7 - Prob. 1.4VCCh. 7 - Alaska Airlines: 20-Minute Baggage...Ch. 7 - Prob. 2.2VCCh. 7 - Prob. 2.3VCCh. 7 - Prob. 2.4VCCh. 7 - Prob. 2.5VCCh. 7 - Prob. 3.1VCCh. 7 - Prob. 3.2VCCh. 7 - Prob. 3.3VCCh. 7 - Prob. 3.4VC
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Process selection and facility layout; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=wjxS79880MM;License: Standard YouTube License, CC-BY