Chapter 7, Problem 3CS
Summary Introduction
Case summary:
RM Company is looking to change its numerically controlled machines into a flexible manufacturing system. The transition will handle about 30% of RM Company’s work. There will be additional costs for startup process. The new system is likely to reduce the inventory, floor space, production time and number of labors required.
The annual labor savings is a huge sum on the implementation of the new process. The company’s return on investment states that it should be at least over 15% for a new process to be implemented and the payback period should be less than 5 years.
To determine: The case of an optimistic sales manager to move on forward with the flexible manufacturing system (FMS).
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
California Gardens, Inc., prewashes, shreds, and distributes a variety of salad mixes in 2-pound bags. Doug Voss, Operations VP, is considering a new Hi-Speed shredder to replacethe old machine, referred to in the shop as "Clunker." Hi-Speed will have a fixed cost of $85,000 per month and a variable cost of $1.25 per bag. Clunker has a fixed cost of only $44,000 per month, but a variable cost of$ 1.75. Selling price is $2.50 per bag.a) What is the crossover point in units (point of indifference) for the processes?b) What is the monthly profit or loss if the company changes to the Hi-Speed shredder and sells 60,000 bags per month? c) What is the monthly profit or loss if the company stays with Clunker and sells 60,000 bags per month?
California Gardens, Inc., prewashes, shreds, and distributes a variety of salad mixes in 2-pound bags. Doug Voss, Operations VP, is considering a new Hi-Speed shredder to replace the old machine, referred to in the shop as "Clunker." Hi-Speed will have a fixed cost of $87,000 per month and a variable cost of $1.20 per bag. Clunker has a fixed cost of only $31,000 per month, but a variable cost of $1.70. Selling price is $2.40 per bag.
Part 2
a) What is the crossover point in units (point of indifference) for the processes?
The crossover point is units. (Round your response to the nearest whole number.)
California Gardens, Inc., prewashes, shreds, and distributes a variety of salad mixes in 2-pound bags. Doug Voss, Operations VP, is considering a new Hi-Speed shredder to replace the old machine, referred to in the shop as "Clunker." Hi-Speed will have a fixed cost of $87,000 per month and a variable cost of $1.20 per bag. Clunker has a fixed cost of only $31,000 per month, but a variable cost of $1.70. Selling price is $2.40 per bag.
Part 2
a) What is the crossover point in units (point of indifference) for the processes?
The crossover point is
112000112000
units. (Round your response to the nearest whole number.)
Part 3
b) What is the monthly profit or loss if the company changes to the Hi-Speed shredder and sells
90,000
bags per month?
The monthly profit or loss if the company changes to the Hi-Speed shredder and sells
90,000
bags per month is
$enter your response here.
(Round your response to the nearest dollar and include a minus sign if necessary.)
Chapter 7 Solutions
OPERATIONS MANAGEMENT CUSTOM 12E >C<
Ch. 7.S - Prob. 1DQCh. 7.S - Prob. 2DQCh. 7.S - Prob. 3DQCh. 7.S - Prob. 4DQCh. 7.S - Prob. 5DQCh. 7.S - Distinguish between bottleneck time and throughput...Ch. 7.S - Prob. 7DQCh. 7.S - Prob. 8DQCh. 7.S - Prob. 9DQCh. 7.S - Prob. 10DQ
Ch. 7.S - Prob. 11DQCh. 7.S - Prob. 12DQCh. 7.S - What are the techniques available to operations...Ch. 7.S - Amy Xias plant was designed to produce 7,000...Ch. 7.S - For the post month, the plant in Problem S7.1,...Ch. 7.S - Prob. 3PCh. 7.S - Prob. 4PCh. 7.S - Prob. 5PCh. 7.S - The effective capacity and efficiency for the next...Ch. 7.S - Southeastern Oklahoma State Universitys business...Ch. 7.S - Prob. 8PCh. 7.S - Prob. 9PCh. 7.S - Prob. 10PCh. 7.S - The three-station work cell illustrated in Figure...Ch. 7.S - The three-station work cell at Pullman Mfg., Inc....Ch. 7.S - The Pullman Mfg., Inc., three-station work cell...Ch. 7.S - Prob. 14PCh. 7.S - 10 minutes per unit. Part 2 is simultaneously...Ch. 7.S - Prob. 16PCh. 7.S - Prob. 17PCh. 7.S - Using the data in Problem S7.17: a) What is the...Ch. 7.S - Prob. 19PCh. 7.S - Prob. 20PCh. 7.S - Prob. 21PCh. 7.S - Prob. 22PCh. 7.S - Prob. 23PCh. 7.S - Prob. 24PCh. 7.S - Prob. 25PCh. 7.S - Prob. 26PCh. 7.S - Prob. 27PCh. 7.S - Prob. 32PCh. 7.S - Prob. 33PCh. 7.S - Prob. 34PCh. 7.S - Prob. 35PCh. 7.S - Prob. 36PCh. 7.S - Prob. 37PCh. 7.S - Prob. 38PCh. 7.S - Prob. 39PCh. 7.S - Prob. 1VCCh. 7.S - a capacity expansion plan and a new 11-story...Ch. 7.S - a capacity expansion plan and a new 11-story...Ch. 7 - Ethical Dilemma For the sake of efficiency and...Ch. 7 - Prob. 1DQCh. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - Prob. 4DQCh. 7 - Prob. 5DQCh. 7 - Prob. 6DQCh. 7 - Prob. 7DQCh. 7 - Prob. 8DQCh. 7 - Prob. 9DQCh. 7 - Prob. 10DQCh. 7 - Prob. 11DQCh. 7 - Prob. 12DQCh. 7 - Prob. 13DQCh. 7 - Prob. 14DQCh. 7 - Prob. 15DQCh. 7 - Prob. 16DQCh. 7 - Prob. 17DQCh. 7 - Prob. 18DQCh. 7 - Prob. 19DQCh. 7 - Prob. 1PCh. 7 - Usingthedatain Problem 7.1, determinethemost...Ch. 7 - Prob. 3PCh. 7 - Refer to Problem 7.1. If a contract for the second...Ch. 7 - Stan Fawcetts company is considering producing a...Ch. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Metters Cabinets, Inc., needs to choose a...Ch. 7 - Prob. 10PCh. 7 - Nagle Electric. Inc., of Lincoln, Nebraska, must...Ch. 7 - Stapleton Manufacturing intends to increase...Ch. 7 - Prepare a flowchart for one of the following: a)...Ch. 7 - Prepare a process chart for one of the activities...Ch. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 1CSCh. 7 - Prob. 2CSCh. 7 - Prob. 3CSCh. 7 - Process Strategy at Wheeled Coach Wheeled Coach,...Ch. 7 - Prob. 1.2VCCh. 7 - Prob. 1.3VCCh. 7 - Prob. 1.4VCCh. 7 - Alaska Airlines: 20-Minute Baggage...Ch. 7 - Prob. 2.2VCCh. 7 - Prob. 2.3VCCh. 7 - Prob. 2.4VCCh. 7 - Prob. 2.5VCCh. 7 - Prob. 3.1VCCh. 7 - Prob. 3.2VCCh. 7 - Prob. 3.3VCCh. 7 - Prob. 3.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- California Gardens, Inc., prewashes, shreds, and dis-tributes a variety of salad mixes in 2-pound bags. Doug Voss, Operations VP, is considering a new Hi-Speed shredder to replacethe old machine, referred to in the shop as “Clunker.” Hi-Speedwill have a fixed cost of $85,000 per month and a variable costof $1.25 per bag. Clunker has a fixed cost of only $44,000 permonth, but a variable cost of $1.75. Selling price is $2.50 per bag.a) What is the crossover point in units (point of indifference) forEric Limon/ Shutterstock the processes? b) What is the monthly profit or loss if the company changes tothe Hi-Speed shredder and sells 60,000 bags per month?c ) What is the monthly profit or loss if the company stays withClunker and sells 60,000 bags per month?arrow_forwardWhat are the advantages when combining process capacities with product specifications?arrow_forwardWhat impact does the product mix have on capacity planning?arrow_forward
- Two manufacturing processes are being considered for making a new product. Process A is less capital intensive, with fixed costs of $60,000 per year and variable costs of $700 per unit. Process B has fixed costs of $400,000 annually, with variable costs of $300 per unit. What is the break-even quantity for the two processes? If annual sales are expected to be 700 units, which process should be selected? Operations and Engineering have found a way to reduce the cost of Process B, such that the fixed costs for this process decrease from $400,000 to $300,000 annually. All other costs remain the same. Does this change the process selection for the annual sales volume of 700 units?arrow_forwardWhat is the significance of using a big-picture approach to capacity planning ?arrow_forwardWhat is CAPACITY REQUIREMENTS FORECASTING?arrow_forward
- Two different manufacturing processes are being considered for maing a new product. The fir proceess is less capital-intensive, with fixed costs of only $50,000 per year and variable costs of $700 per unit. The scond proess has fixed costs of $400,000 but has variable costs of only $200 per unit. If the expected annual sales for theproduct is 800 units, which process would you choose?arrow_forwardHow important is it to align process capabilities to product requirements?arrow_forwardWhat is Quality Function Deployment and Concepts, explain with an examplesarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.