Chapter 7, Problem 9P
Metters Cabinets, Inc., needs to choose a production method for its new office shelf, the Maxistand. To help accomplish this, the firm has gathered the following production cost data:
Metters Cabinets projects an annual demand of 24,000 units for the Maxistand. The Maxistand will sell for $120 per unit. a) Which process type will maximize the annual profit from producing the Maxistand?
b) What is the value of this annual profit?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Metters Cabinets, Inc., needs to choose a production method for its new office shelf, the Maxistand. To help accomplish this, the firm has gathered the following production cost data: Metters Cabinets projects an annual demand of 24,000 units for the Maxistand. The Maxistand will sell for $120 per unit.a) Which process type will maximize the annual profit from producing the Maxistand?b) What is the value of this annual profit?
The design capacity, effective capacity and efficiency for a car licensing operation are shown in the following table:
Process
Design capacity
Effective capacity
Efficiency
Document checking
145,000
128,000
0.95
License production
1,250,000
900,000
0.15
Distribution
165,000
160,000
0.75
What are the expected output levels for each process?
What are the utilization rates for each process?
Tribal Systems, Inc., is opening a new plant and has yet todecide on the type of process to employ. A labor-intensiveprocess would cost $10,000 for tools and equipment and$14 for labor and materials per item produced. A more automated process costs $50,000 in plant and equipment buthas a labor/material cost of $8 per item produced. A fullyautomated process costs $300,000 for plant and equipmentand $2 per item produced. If process selection were basedsolely on lowest cost, for what range of production wouldeach process be chosen?
Chapter 7 Solutions
OPERATIONS MANAGEMENT CUSTOM 12E >C<
Ch. 7.S - Prob. 1DQCh. 7.S - Prob. 2DQCh. 7.S - Prob. 3DQCh. 7.S - Prob. 4DQCh. 7.S - Prob. 5DQCh. 7.S - Distinguish between bottleneck time and throughput...Ch. 7.S - Prob. 7DQCh. 7.S - Prob. 8DQCh. 7.S - Prob. 9DQCh. 7.S - Prob. 10DQ
Ch. 7.S - Prob. 11DQCh. 7.S - Prob. 12DQCh. 7.S - What are the techniques available to operations...Ch. 7.S - Amy Xias plant was designed to produce 7,000...Ch. 7.S - For the post month, the plant in Problem S7.1,...Ch. 7.S - Prob. 3PCh. 7.S - Prob. 4PCh. 7.S - Prob. 5PCh. 7.S - The effective capacity and efficiency for the next...Ch. 7.S - Southeastern Oklahoma State Universitys business...Ch. 7.S - Prob. 8PCh. 7.S - Prob. 9PCh. 7.S - Prob. 10PCh. 7.S - The three-station work cell illustrated in Figure...Ch. 7.S - The three-station work cell at Pullman Mfg., Inc....Ch. 7.S - The Pullman Mfg., Inc., three-station work cell...Ch. 7.S - Prob. 14PCh. 7.S - 10 minutes per unit. Part 2 is simultaneously...Ch. 7.S - Prob. 16PCh. 7.S - Prob. 17PCh. 7.S - Using the data in Problem S7.17: a) What is the...Ch. 7.S - Prob. 19PCh. 7.S - Prob. 20PCh. 7.S - Prob. 21PCh. 7.S - Prob. 22PCh. 7.S - Prob. 23PCh. 7.S - Prob. 24PCh. 7.S - Prob. 25PCh. 7.S - Prob. 26PCh. 7.S - Prob. 27PCh. 7.S - Prob. 32PCh. 7.S - Prob. 33PCh. 7.S - Prob. 34PCh. 7.S - Prob. 35PCh. 7.S - Prob. 36PCh. 7.S - Prob. 37PCh. 7.S - Prob. 38PCh. 7.S - Prob. 39PCh. 7.S - Prob. 1VCCh. 7.S - a capacity expansion plan and a new 11-story...Ch. 7.S - a capacity expansion plan and a new 11-story...Ch. 7 - Ethical Dilemma For the sake of efficiency and...Ch. 7 - Prob. 1DQCh. 7 - Prob. 2DQCh. 7 - Prob. 3DQCh. 7 - Prob. 4DQCh. 7 - Prob. 5DQCh. 7 - Prob. 6DQCh. 7 - Prob. 7DQCh. 7 - Prob. 8DQCh. 7 - Prob. 9DQCh. 7 - Prob. 10DQCh. 7 - Prob. 11DQCh. 7 - Prob. 12DQCh. 7 - Prob. 13DQCh. 7 - Prob. 14DQCh. 7 - Prob. 15DQCh. 7 - Prob. 16DQCh. 7 - Prob. 17DQCh. 7 - Prob. 18DQCh. 7 - Prob. 19DQCh. 7 - Prob. 1PCh. 7 - Usingthedatain Problem 7.1, determinethemost...Ch. 7 - Prob. 3PCh. 7 - Refer to Problem 7.1. If a contract for the second...Ch. 7 - Stan Fawcetts company is considering producing a...Ch. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Metters Cabinets, Inc., needs to choose a...Ch. 7 - Prob. 10PCh. 7 - Nagle Electric. Inc., of Lincoln, Nebraska, must...Ch. 7 - Stapleton Manufacturing intends to increase...Ch. 7 - Prepare a flowchart for one of the following: a)...Ch. 7 - Prepare a process chart for one of the activities...Ch. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 1CSCh. 7 - Prob. 2CSCh. 7 - Prob. 3CSCh. 7 - Process Strategy at Wheeled Coach Wheeled Coach,...Ch. 7 - Prob. 1.2VCCh. 7 - Prob. 1.3VCCh. 7 - Prob. 1.4VCCh. 7 - Alaska Airlines: 20-Minute Baggage...Ch. 7 - Prob. 2.2VCCh. 7 - Prob. 2.3VCCh. 7 - Prob. 2.4VCCh. 7 - Prob. 2.5VCCh. 7 - Prob. 3.1VCCh. 7 - Prob. 3.2VCCh. 7 - Prob. 3.3VCCh. 7 - Prob. 3.4VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Tribal Systems, Inc., is opening a new plant and has yet todecide on the type of process to employ. A labor-intensiveprocess would cost $10,000 for tools and equipment and $14 for labor and materials per item produced. A more au-tomated process costs $50,000 in plant and equipment but has a labor/material cost of $8 per item produced. A fullyautomated process costs $300,000 for plant and equipmentand $2 per item produced. If process selection were basedsolely on lowest cost, for what range of production wouldeach process be chosen?arrow_forwardSamoset Fans, Inc. manufacturers its fan blades in-house. The owner, Betty Dice, doesn't outsource any fan parts except fan motors — all other fans parts are made in-house. Their current process and its equipment are getting old. Maintenance and repair costs are increasing at seven percent per year. She and her company team are evaluating two new processes. The first process has an annual fixed cost of $730,000 and a variable cost of $12 per fan blade. The second process is more automated and requires an annual fixed cost of $1,050,000 and a variable cost of $10 per fan blade. The internal transfer cost of a fan blade is $22, and this helps the firm determine the total manufactured cost of a completed fan. Use the Excel template Break-Even in MindTap to answer the following questions: What is the break-even quantity between these two processes? Round your answer to the nearest whole number. fan blades If predicted demand for next year is 110,000 blades, what process do you…arrow_forwardSamoset Fans, Inc. manufacturers its fan blades in-house. The owner, Betty Dice, doesn't outsource any fan parts except fan motors — all other fans parts are made in-house. Their current process and its equipment are getting old. Maintenance and repair costs are increasing at eleven percent per year. She and her company team are evaluating two new processes. The first process has an annual fixed cost of $760,000 and a variable cost of $19 per fan blade. The second process is more automated and requires an annual fixed cost of $1,100,000 and a variable cost of $11 per fan blade. The internal transfer cost of a fan blade is $24, and this helps the firm determine the total manufactured cost of a completed fan. Use the Excel template Break-Even in MindTap to answer the following questions: What is the break-even quantity between these two processes? Round your answer to the nearest whole number. fan blades If predicted demand for next year is 160,000 blades, what process do you…arrow_forward
- An organization is considering three process configuration options. There are two different intermittent processes, as well as a repetitive focus. The smaller intermittent process has fixed costsof $30000 per month, and variable costs of $9 per unit. The larger intermittent process has fixed costs of $11000 per month and variable costs of $2 per unit. A repetitive focus plant has fixed costs of $48000 and variable costs of $1 per unit.a. If the company produced 22000 units, what would be its cost under each of the threechoices?b. Which process offers the lowest cost to produce 39000 units? What is that cost?arrow_forwardThe Andrews family is in the process of hiring a five-star chef who can cook a variety of food to meet customers’ tastes and wants (top quality). In addition, the restaurant is designed to provide complete privacy to customers. Therefore, tables ought to be separated by no less than 5 feet. Using Chapter 2 and the assigned videos as your theoretical foundations, please answer the following question. What production process should the restaurant choose? Explain your answer. In contrast to the Andrews family restaurant, the Sweet family restaurant sells burgers, burritos, and hotdogs. The restaurant relies on high school students to cook food, and customers cannot customize their food choices. The Sweet family restaurant sells 2000 burgers per restaurant each day. The average costs of burgers, burritos, and hot dogs are $2, $3, and $0.50, respectively. Using Chapters 1 and 2 as your theoretical foundations, please answer the following question: What are the Sweet family…arrow_forwardSpartan Castings must implement a manufacturing process that reduces the amount of particulates emitted into the atmosphere. Two processes have been identified that provide the same level of particulate reduction. The first process is expected to incur $350,000 of fixed cost and add $50 of variable cost to each casting Spartan produces. The second process has fixed costs of $150,000 and adds $90 of variable cost per casting.a. What is the break-even quantity beyond which the first process is more attractive?b. What is the difference in total cost if the quantity produced is 10,000?arrow_forward
- Explain the two conditions that are required in process flexibility ?arrow_forwardExplain and state the five process typess and indicate the kinds of situations in which each would be used ?arrow_forwardTwo manufacturing processes are being considered for making a new product. Process A is less capital intensive, with fixed costs of $60,000 per year and variable costs of $700 per unit. Process B has fixed costs of $400,000 annually, with variable costs of $300 per unit. What is the break-even quantity for the two processes? If annual sales are expected to be 700 units, which process should be selected? Operations and Engineering have found a way to reduce the cost of Process B, such that the fixed costs for this process decrease from $400,000 to $300,000 annually. All other costs remain the same. Does this change the process selection for the annual sales volume of 700 units?arrow_forward
- As a manager what strategy, style, or action plan in Scope for Reducing Costs in terms of Process Optimization. Please explain.arrow_forwardConstruct a process flowchart of a process with which youare familiar. Identify bottlenecks, potential failure points,and opportunities for improvement.arrow_forwardby matching process capabilities with product requirements, we get the most efficient process possible? Explain?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Process selection and facility layout; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=wjxS79880MM;License: Standard YouTube License, CC-BY