Concept explainers
A project consists of three tasks. Task A is scheduled to begin at the start of Week 1 and finish at the end of Week 3. Task B is scheduled to begin at the start of Week 1 and finish at the end of Week 2. Task C is scheduled to begin at the start of Week 2 and end at the end of Week 3. The budgeted cost for Task A is $22,000, for Task B is $17,000, and for Task C is $15,000. At the end of the second week, Task A is 65% complete, Task B is 95% complete, and Task C is 60% complete. What is the SPI for the project at the end of the second week?
Want to see the full answer?
Check out a sample textbook solutionChapter 7 Solutions
Construction Accounting And Financial Management (4th Edition)
Additional Business Textbook Solutions
Horngren's Financial & Managerial Accounting, The Managerial Chapters (6th Edition)
PRINCIPLES OF TAXATION F/BUS.+INVEST.
Horngren's Accounting (12th Edition)
Financial Accounting (11th Edition)
Managerial Accounting (5th Edition)
- Adam Corporation manufactures computer tables and has the following budgeted indirect manufacturing cost information for the next year: If Adam uses the step-down (sequential) method, beginning with the Maintenance Department, to allocate support department costs to production departments, the total overhead (rounded to the nearest dollar) for the Machining Department to allocate to its products would be: a. 407,500. b. 422,750. c. 442,053. d. 445,000.arrow_forwardDouglas Davis, controller for Marston, Inc., prepared the following budget for manufacturing costs at two different levels of activity for 20X1: During 20X1, Marston worked a total of 80,000 direct labor hours, used 250,000 machine hours, made 32,000 moves, and performed 120 batch inspections. The following actual costs were incurred: Marston applies overhead using rates based on direct labor hours, machine hours, number of moves, and number of batches. The second level of activity (the right column in the preceding table) is the practical level of activity (the available activity for resources acquired in advance of usage) and is used to compute predetermined overhead pool rates. Required: 1. Prepare a performance report for Marstons manufacturing costs in the current year. 2. Assume that one of the products produced by Marston is budgeted to use 10,000 direct labor hours, 15,000 machine hours, and 500 moves and will be produced in five batches. A total of 10,000 units will be produced during the year. Calculate the budgeted unit manufacturing cost. 3. One of Marstons managers said the following: Budgeting at the activity level makes a lot of sense. It really helps us manage costs better. But the previous budget really needs to provide more detailed information. For example, I know that the moving materials activity involves the use of forklifts and operators, and this information is lost when only the total cost of the activity for various levels of output is reported. We have four forklifts, each capable of providing 10,000 moves per year. We lease these forklifts for five years, at 10,000 per year. Furthermore, for our two shifts, we need up to eight operators if we run all four forklifts. Each operator is paid a salary of 30,000 per year. Also, I know that fuel costs about 0.25 per move. Assuming that these are the only three items, expand the detail of the flexible budget for moving materials to reveal the cost of these three resource items for 20,000 moves and 40,000 moves, respectively. Based on these comments, explain how this additional information can help Marston better manage its costs. (Especially consider how activity-based budgeting may provide useful information for non-value-added activities.)arrow_forwardMesa Aquatics, Inc. estimated direct labor hours as 1,900 in quarter 1, 2,000 in quarter 2.2,200 in quarter 3, and 1,800 in quarter 4. a sales and administration budget using the information provided.arrow_forward
- Using the provided budgeted information for production of 10,000 and 15,000 units, prepare a flexible budget for 17,000 units.arrow_forwardUsing the following budgeted information for production of 5,000 and 12,000 units, prepare a flexible budget for 9,000 units.arrow_forwardPuyallop corporation developed the following budgeted and actual overhead costs for the current year. Budgeted (20,000 direct labor hours) Actual (at 18,000 direct labors Variable overhead 3,800,000 3,510,000 Fixed overhead 5,000,000 4,536,000 Total 8,800,000 8,046,000 Consistent with the prior year, overhead costs are is appliedbased on direct labor hours. Puayllop budgeted 20,000 direct labor hours for the current year which is the plant's normal operating capacity. Required: Calculate the following variances: a. Variable overhead spending variance b. Fixed overhead spending variance c. Idle capacity variance d. Overall factory overhead variancearrow_forward
- Puyallop corporation developed the following budgeted and actual overhead costs for the current year. Budgeted (20,000 direct labor hours) Actual (at 18,000 direct labors Variable overhead 3,800,000 3,510,000 Fixed overhead 5,000,000 4,536,000 Total 8,800,000 8,046,000 Consistent with the prior year, overhead costs are is appliedbased on direct labor hours. Puayllop budgeted 20,000 direct labor hours for the current year which is the plant's normal operating capacity. Required: Calculate the following variances: A. Overall factory overhead variancearrow_forwardAt the beginning of the period, the Grinding Department budgeted direct labor of $72,600 and property tax of $31,000 for 6,600 hours of production. The department actually completed 8,000 hours of production. Determine the budget for the department, assuming that it uses flexible budgeting.$fill in the blank 1arrow_forwardThe production supervisor of the Painting Department for Whitley Company agreed to the following monthly static budget for the upcoming year: WHITLEY COMPANYPainting DepartmentMonthly Production Budget Wages $214,000 Utilities 20,000 Depreciation 33,000 Total $267,000 The actual amount spent and the actual units produced in the first three months in the Painting Department were as follows: Amount Spent Units Produced January $252,000 56,000 February 242,000 51,000 March 232,000 46,000 The Painting Department supervisor has been very pleased with this performance, since actual expenditures have been less than the monthly budget. However, the plant manager believes that the budget should not remain fixed for every month but should "flex" or adjust to the volume of work that is produced in the Painting Department. Additional budget information for the Painting Department is as follows: Wages per hour $14.00 Utility cost per direct…arrow_forward
- Michard Corporation makes one product and it provided the following information to help prepare the master budget for the next four months of operations: a. The budgeted selling price per unit is $125. Budgeted unit sales for April, May, June, and July are 7,600, 10,500, 13,800, and 12,900 units, respectively. All sales are on credit. b. Regarding credit sales, 20% are collected in the month of the sale and 80% in the following month. c. The ending finished goods inventory equals 20% of the following month's sales. d. The ending raw materials inventory equals 30% of the following month's raw materials production needs. Each unit of finished goods requires 4 pounds of raw materials. The raw materials cost $2.00 per pound. e. Regarding raw materials purchases, 30% are paid for in the month of purchase and 70% in the following month. f. The direct labor wage rate is $25.00 per hour. Each unit of finished goods requires 3.0 direct labor-hours. g. The variable selling and administrative…arrow_forwardKent Corporation developed the following budgeted costs for the current year: Direct materials P120,000 Direct Labor 330,000 Factory overhead 429,000 Total P879,000 The following activity bases were also budgeted for the year: Labor hours 9,600 Machine hours 6,000 Units to be produced 12,000 Based on the current backlog, Kent expects to produce 3,500 units during the first quarter that requires 2,600 labor hours and 1,700 machine hours. For this production, Kent incurred direct materials of P38,000 and direct labor of P94,000. Required: Calculate the predetermined overhead rate and applied overhead cost using the following application base: Physical output Percentage of direct labor cost Percentage of direct materials cost Direct labor hours Machine hoursarrow_forwardKent Corporation developed the following budgeted costs for the current year: Direct materials P120,000 Direct Labor 330,000 Factory overhead 429,000 Total P879,000 The following activity bases were also budgeted for the year: Labor hours 9,600 Machine hours 6,000 Units to be produced 12,000 Based on the current backlog, Kent expects to produce 3,500 units during the first quarter that requires 2,600 labor hours and 1,700 machine hours. For this production, Kent incurred direct materials of P38,000 and direct labor of P94,000. Required: Calculate the predetermined overhead rate and applied overhead cost using the following application base: Percentage of direct materials cost Direct labor hours Machine hoursarrow_forward
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning