Construction Accounting And Financial Management (4th Edition)
4th Edition
ISBN: 9780135232873
Author: Steven J. Peterson MBA PE
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 7, Problem 14P
The ACWP at the end of the second week for the project in Problem 12 is $37,900. Determine the CPI for the project.
A project consists of three tasks. Task A is scheduled to begin at the start of Week 1 and finish at the end of Week 3. Task B is scheduled to begin at the start of Week 1 and finish at the end of Week 2. Task C is scheduled to begin at the start of Week 2 and end at the end of Week 3. The budgeted cost for Task A is $22,000, for Task B is $17,000, and for Task C is $15,000. At the end of the second week, Task A is 65% complete, Task B is 95% complete, and Task C is 60% complete. What is the SPI for the project at the end of the second week?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
An activity originally estimated to cost $100,000 and require 30 weeks to complete. Now the activity is on week 10 and $35,000 were spent and is 40% completed. What is the ACWP for this activity?
In a 5 months project and original budget of $1500, the 40% work are completed in 3 months at actual
cost of $900. Determine (i) Estimate at Completion (EAC), (ii) Estimate to Completion (ETC), Schedule
Performance Index (SPI), (iv) Estimate Time To Complete (ETTC).
(Note: Currently the project is running overbudgeted with CPI = 0.67).
You were told that the project actual cost of the work completed is $350,000 but budgeted cost at completion has been estimated to be $ 500,000. If earned value is $250,000, the possible EAC will be equal to
Chapter 7 Solutions
Construction Accounting And Financial Management (4th Edition)
Ch. 7 - What are the key steps in the monitoring and...Ch. 7 - What does it indicate when a superintendent has to...Ch. 7 - What is the best way to control labor costs? What...Ch. 7 - Why are equipment costs for company-owned...Ch. 7 - What is an internai change order and how is it...Ch. 7 - Why is it important to have a realistic budget for...Ch. 7 - What are some of the problems with using the CPI?Ch. 7 - Prob. 8DQCh. 7 - During the design phase, what are the steps for...Ch. 7 - Determine the estimated cost of the work performed...
Ch. 7 - Determine the estimated cost of the work performed...Ch. 7 - A project consists of three tasks. Task A is...Ch. 7 - A project consists of six tasks. Task A is...Ch. 7 - The ACWP at the end of the second week for the...Ch. 7 - A project consists of six tasks. Task A is...Ch. 7 - Determine the total estimated cost at completion...Ch. 7 - A project consists of six tasks. Task A is...Ch. 7 - Prob. 18P
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- SIS Technologies currently allocates insurance costs on the basis of direct labor hours. If the direct labor hours for departments A, B, and C are expected to be 3000, 9000, and 5000, respectively, this year, determine the allocation to each department based on an indirect cost budget of $34,000.arrow_forwardYour IT company is working on a four-month project for a local mining company. The total planned value of the project (BAC) is $600,000. You are at the end of month three. By the end of month three you scheduled to spend $500,000(PV). The actual cost through this three-month mark is $450,000 (AC). The total work completed at the end of month three is 94 percent. Calculate the earned value, EV=arrow_forwardThe master budget of Knope Inc. shows that the planned activity level for next year is expected to be 25,000 machine hours. At this level of activity, the following manufacturing overhead costs are expected: Indirect labor................................................. $720,000 Machine supplies.............................................180,000 Indirect materials.............................................210,000 Depreciation on factory building..................150,000 Total manufacturing overhead.................$1,260,000 A flexible budget for a level of activity of 30,000 machine hours would show total manufacturing overhead costs of Group of answer choices $1,260,000 $1,512,000 $1,362,000 $1,482,000arrow_forward
- Portable Power Company expects to operate at 80% of productive capacity during July. The total manufacturing costs for July for the production of 25,000 batteries are budgeted as follows:Direct materials$162,500Direct labor70,000Variable factory overhead30,000Fixed factory overhead112,500Total manufacturing costs$375,000The company has an opportunity to submit a bid for 2,500 batteries to be delivered by July 31 to a government agency. If the contract is obtained, it is anticipated that the additional activity will not interfere with normal production during July or increase the selling or administrative expenses.What is the unit cost below which Portable Power Company should not go in bidding on the government contract? Round your answer to two decimal places.$ per unitarrow_forwardPower Pack Company expects to operate at 80% of productive capacity during July. The total manufacturing costs for July for the production of 45,000 batteries are budgeted as follows: Direct materials $375,000 Direct labor 160,750 Variable factory overhead 71,750 Fixed factory overhead 261,250 Total manufacturing costs $868,750 The company has an opportunity to submit a bid for 4,500 batteries to be delivered by July 31 to a government agency. If the contract is obtained, it is anticipated that the additional activity will not interfere with normal production during July or increase the selling or administrative expenses. What is the unit cost below which Power Pack Company should not go in bidding on the government contract? Round your answer to two decimal places.arrow_forwardHere is some data for Project "ABC" Budget $ 5,270 thousand Start Workday 15 Finish Workday 117 Reporting Day 34 Earned Value $ 204 thousand Planned Value $ 314 thousand Actual Cost $ 586 thousand Using a "Do-Nothing Forecast" predict the estimated finishing Workday when you expect the project will be completed (given that the project started on time)? If the project will be completed partway through a Workday, round UP to the next integer value. The allowed error margin is + 2 Workdays, with no deduction of marks. PLEASE GIVE ME COMPLETE ANSWERarrow_forward
- Kent Corporation developed the following budgeted costs for the current year: Direct materials P120,000 Direct Labor 330,000 Factory overhead 429,000 Total P879,000 The following activity bases were also budgeted for the year: Labor hours 9,600 Machine hours 6,000 Units to be produced 12,000 Based on the current backlog, Kent expects to produce 3,500 units during the first quarter that requires 2,600 labor hours and 1,700 machine hours. For this production, Kent incurred direct materials of P38,000 and direct labor of P94,000. Required: Calculate the predetermined overhead rate and applied overhead cost using the following application base: Physical output Percentage of direct labor cost Percentage of direct materials cost Direct labor hours Machine hoursarrow_forwardKent Corporation developed the following budgeted costs for the current year: Direct materials P120,000 Direct Labor 330,000 Factory overhead 429,000 Total P879,000 The following activity bases were also budgeted for the year: Labor hours 9,600 Machine hours 6,000 Units to be produced 12,000 Based on the current backlog, Kent expects to produce 3,500 units during the first quarter that requires 2,600 labor hours and 1,700 machine hours. For this production, Kent incurred direct materials of P38,000 and direct labor of P94,000. Required: Calculate the predetermined overhead rate and applied overhead cost using the following application base: Percentage of direct materials cost Direct labor hours Machine hoursarrow_forwardA local engineering firm is bidding on a design project for a new client. The total budgeted direct-labor costs for the firm are $600,000. The total budgeted indirect costs are $800,000. It is estimated that there are 10,000 billable hours in total. a. What is the budgeted direct-labor cost rate? b. What is the budgeted indirect-cost rate assuming direct-labor cost is the allocation base? c. What should be the engineering firm bid on the project if the direct labor hours are estimated at 300 hours?arrow_forward
- Tooling for a robotic arm used in the automotive industry costs $15,000 and has an estimated salvage value of $1,000 at the end of a 3-year life. The second-year MACRS depreciation is closest to a. $5,000 b. $6,668 c. $4,667 d. $6,223 In preparing a cash budget for the last quarter of a calendar year, the opening balance for October is $95, 000. Throughout this month receipt from sales is $50,000 and total payments is $35,000. Depreciation on assets for this month is $500 and previous month’s receipt from sales is $60,000. What is November’s opening balance? a. $75,500 b. $110,000 c. $49,500 d. $169,500arrow_forwardSonic, Inc. is planning to produce 2,500 units of product in 2022. Each unit requires 3 pounds of materials at $6 per pound and a half hour of labor at $16 per hour. The overhead rate is 75% of direct labor. Compute the budgeted amounts for 2022 for direct materials to be used, direct labor, and applied overhead. Direct Materials $enter a dollar amount Direct Labor $enter a dollar amount Overhead $enter a dollar amountarrow_forwardA. Parkson Limited has produced an overhead budget for next year based on two levels of activity, 5000 units and 8,000 units. It needs to calculate budgeted figures based on an activity level of 6,800 units. The budgeted figures for activity levels of 5000 and 8,000 are shown below: Parkson Limited. Budgeted Overheads for the year ending 31 December 2015Production (Units) 5,000 8,000 Type of Cost $ $ Building rent Fixed 20,000 20,000 Building Depreciation Fixed 31,500 31,500Indirect labour Variable 25,000 40,000Indirect materials Variable 15,000 24,000Electricity Semi-variable 30,000 36,000Stock insurance Semi-variable 30,000…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegeCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College Pub
- Financial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Responsibility Accounting| Responsibility Centers and Segments| US CMA Part 1| US CMA course; Master Budget and Responsibility Accounting-Intro to Managerial Accounting- Su. 2013-Prof. Gershberg; Author: Mera Skill; Rutgers Accounting Web;https://www.youtube.com/watch?v=SYQ4u1BP24g;License: Standard YouTube License, CC-BY