Construction Accounting And Financial Management (4th Edition)
Construction Accounting And Financial Management (4th Edition)
4th Edition
ISBN: 9780135232873
Author: Steven J. Peterson MBA PE
Publisher: PEARSON
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 7, Problem 16P

Determine the total estimated cost at completion and estimated cost to complete for the project in Problem 14, assuming the CPI remains the same through the remainder of the job.

The ACWP at the end of the second week for the project in Problem 12 is $37,900. Determine the CPI for the project.

A project consists of three tasks. Task A is scheduled to begin at the start of Week 1 and finish at the end of Week 3. Task B is scheduled to begin at the start of Week 1 and finish at the end of Week 2. Task C is scheduled to begin at the start of Week 2 and end at the end of Week 3. The budgeted cost for Task A is $22,000, for Task B is $17,000, and for Task C is $15,000. At the end of the second week, Task A is 65% complete, Task B is 95% complete, and Task C is 60% complete. What is the SPI for the project at the end of the second week?

Blurred answer
Students have asked these similar questions
The management of Red Star Company estimates that 60,000 machine-hours will be required to support the production planned for the year. It also estimates $300,000 of total fixed manufacturing overhead cost for the coming year and $5 of variable manufacturing overhead cost per machine-hour. What is the predetermined overhead rate?
Rundle Construction Company expects to build three new homes during a specific accounting period. The estimated direct materials and labor costs are as follows. Expected Direct labor Home 1: $63,000 Home 2: $108,000, Home 3: $181,000 Direct materials Home 1: 98,000 Home 2: 143,000 Home 3: 186,000  Assume Rundle needs to allocate two major overhead costs ($ 52,800 of employee fringe benefits and $12,,810 of indirect materials cost) among the three Jobs. required; Choose an appropriate cost driver for each of the overhead costs and determine the cost of each house ( round " allocation rate to 2 decimal places.)
Thornton Construction Company expects to build three new homes during a specific accounting period. The estimated direct materials and labor costs are as follows.  Expected Costs Home 1 Home 2 Home 3 Direct labor $ 66,000   $ 100,000   $ 178,000   Direct materials   109,000     139,000     181,000     Assume Thornton needs to allocate two major overhead costs ($51,600 of employee fringe benefits and $30,030 of indirect materials costs) among the three jobs.RequiredChoose an appropriate cost driver for each of the overhead costs and determine the total cost of each house. (Round "Allocation rate" to 2 decimal places.)
Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Text book image
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Text book image
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Text book image
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Text book image
Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning
What is variance analysis?; Author: Corporate finance institute;https://www.youtube.com/watch?v=SMTa1lZu7Qw;License: Standard YouTube License, CC-BY