Concept explainers
Table 7.5 contains information about au environmental cleanup project in the township of Hiles. Shorten the project 3 weeks by finding the minimum—cost
Want to see the full answer?
Check out a sample textbook solutionChapter 7 Solutions
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Additional Business Textbook Solutions
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Business in Action (8th Edition)
Operations and Supply Chain Management 9th edition
- 21. The following table provides the information necessary to construct a project network and project crash data: Activity (i, j) Activity Predecessor Activity Time (weeks) Normal Crash Activity Cost Normal Crash a (1,2) --- 16 8 $2000 $4400 b (1,3) --- 14 9 1000 1800 c (2,4) a 8 6 500 700 d (2,5) a 5 4 600 1300 e (3,5) b 4 2 1500 3000 f (3,6) b 6 4 800 1600 g (4,6) c 10 7 3000 4500 h (5,6) d, e 15 10 5000 8000 a. Construct the project network b. Manually crash the network to 28 weeks Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forwardWhat is the scope of the following project? (2 paragraphs please) Barbados GIS – The United Nations Food and Agriculture Organization (FAO) has collaborated with the Ministry of Maritime Affairs and the Blue Economy, and local business Adams Aquafarms, on a project to train persons in aquaponics. Aquaponics is a sustainable way of integrating land-based fish farming with plant production. Both are placed in a tank, and the set up allows for them to coexist, with the waste produced by the fish fertilizing the plants, while the plants purify the water for the fish. The training, funded by the FAO, will take place at a demonstration facility, located at Adams Aquafarms, Hopewell, St. Thomas. The FAO is currently targeting 30 entrepreneurs and 10 teachers. Minister of Maritime Affairs and the Blue Economy, Kirk Humphrey, believes the project will be “transformative”, as it has the potential to empower Barbadians. “In aquaponics, you have the opportunity to have, at the same time,…arrow_forwardJabez Contractors installs network routers. Using the CPM method and in reference to the table provided comment on the expected completion time of the projectand identify the activities that neeD to be prioritised by the project manager. (Nodiagram is required) TABLE- PROJECT INSTALLATION Activity Predecessor optimistic Most Likely Pessismistic Estimated time A - 4 7 10 7 B - 2 9 10 8 C A,B 2 5 8 5 D C 16 19 28 20 E C 6 9 24 11 F E 1 7 13 7 G C 4 10 28 12 H D,F 2 5 14 6 I G 5 8 17 9 J H,I 2 5 8 5arrow_forward
- Dave is the project manager for a construction project that is building agazebo. When the project first started, he met with the stakeholders to definethe scope. The sponsors mentioned that the gazebo is a really important partof their daughter’s wedding ceremony that was planned for 7 months fromthen. In fact, they said that if the gazebo couldn’t be completed in 7 months, itwouldn’t be worth it for them to even start the project. Dave wrote down the7-month deadline to put in his Project Scope Statement. In which section ofthe document did the deadline appear?”A. Project ConstraintsB. Project DeliverablesC. Project ObjectivesD. Project Assumptions Which of the following is a “hygiene factor” under Herzberg’s Motivation-Hygiene Theory?A. Recognition for excellent workB. Self-actualizationC. Clean clothingD. Good relations with coworkers and managersarrow_forwardYou are the project manager of the software installationproject in Table 7.12. You would like to find the minimum-costschedule for your project. There is a $1,000-per-week penaltyfor each week the project is delayed beyond week 25. In addi-tion, your project team determined that indirect project costsare $2,500 per week.a. What would be your target completion week?b. How much would you save in total project costs with yourschedule?arrow_forwardA student has been put in charge of a new garden design. The new design will involve five different activities. Per project management guideline, activities “a” and “b” start on day 0. Draw the network diagram. Calculate ES/EF/LS/LF and Slack for all activities. Activity A: Immediate Predecessprs (-) Duration days (3) Activity B: Immediate Predecessprs (-) Duration days(5) Activity C: Immediate Predecessprs (a) Duration days(3) Activity D: Immediate Predecessprs (b) Duration days(7) Activity E: Immediate Predecessprs (C,D) Duration days(3)arrow_forward
- N5 Explain some of the basic principles of cost management, such as profits, life cycle costs, tangible and intangible costs and benefits, direct and indirect costs, and reserves. Why is defining activities a process of project time management instead of project scope management?arrow_forwardThe G&E Company is preparing a bid to build the new 47,000-seat Shoreline baseball stadium. The construction must start on Jan 01 2022, and be completed in time for the finals of the 2024 season. A penalty clause of $250,000 per week of delay beyond October 1st, 2024 is written into the contract. George Earnings, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $3 million on the project. He also said if they succeed, the prospects of future projects are bright since there is a projected renaissance in building classic ballparks with modern luxury boxes. ID Activity Duration Predecessor(s) 1 Baseball Stadium 2 Clear stadium site 70 days — 3 Demolish building 30 days 2 4 Set up construction site 70 days 3 5 Drive support piling 120 days 4 6 Pour lower concrete bowl 120 days 5 7 Pour main concourse 120 days 6 8…arrow_forwardDevelopment of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table: Activity Normal Time (weeks) Crash Time (weeks) Normal Cost Total Cost with Crashing Immediate Predecessors(s) A 4 3 $2,200 $2,850 --- B 2 1 $2,100 $2,700 --- C 3 3 $750 $750 --- D 8 4 $2,500 $2,800 A E 6 3 $800 $1,250 B F 3 2 $3,200 $4,400 C G 4 2 $1,400 $1,800 D, E a) Based on the given information regarding the activities for the project, the project length = _______ weeks ? b) The total cost required for completing this project on normal time = _______ ? c) If you wish to reduce the time required to complete this project by 1 week, which activity should be crashed, and how much will this increase the total cost? The critical path with the longest length through the project is _______ ? Note:- Do not provide…arrow_forward
- CASE - CAPACITY BUILDING PROJECT AIMS TO INCREASE YOUTH INVOLVEMENT IN SUSTAINABLE DEVELOPMENT Basseterre, St. Kitts, April 29, 2021 (SKNIS): St. Kitts and Nevis Youth Ambassador Corps officially launched a new project on Wednesday (April 28, 2021) designed to increase the contributions of young people to the sustainable development of the twin-island Federation. The initiative, dubbed the Youth Capacity Building Small Grants Project on Youth in Sustainable Development, will build the capacity and practical skills of young people to design, implement, and monitor interventions relevant to the social, economic, and sustainable development of youth and their communities. The project is geared towards members of youth groups specifically. It is spearheaded by the national youth ambassador corps in collaboration with the GEF Small Grants Programme (SGP), and the Departments of Youth in St. Kitts, and Nevis. The Small Grants Project is funding the initiative to the tune of US$49,970.00. SGP…arrow_forwardCASE - CAPACITY BUILDING PROJECT AIMS TO INCREASE YOUTH INVOLVEMENT IN SUSTAINABLE DEVELOPMENT Basseterre, St. Kitts, April 29, 2021 (SKNIS): St. Kitts and Nevis Youth Ambassador Corps officially launched a new project on Wednesday (April 28, 2021) designed to increase the contributions of young people to the sustainable development of the twin-island Federation. The initiative, dubbed the Youth Capacity Building Small Grants Project on Youth in Sustainable Development, will build the capacity and practical skills of young people to design, implement, and monitor interventions relevant to the social, economic, and sustainable development of youth and their communities. The project is geared towards members of youth groups specifically. It is spearheaded by the national youth ambassador corps in collaboration with the GEF Small Grants Programme (SGP), and the Departments of Youth in St. Kitts, and Nevis. The Small Grants Project is funding the initiative to the tune of US$49,970.00. SGP…arrow_forwardCASE - CAPACITY BUILDING PROJECT AIMS TO INCREASE YOUTH INVOLVEMENT IN SUSTAINABLE DEVELOPMENT Basseterre, St. Kitts, April 29, 2021 (SKNIS): St. Kitts and Nevis Youth Ambassador Corps officially launched a new project on Wednesday (April 28, 2021) designed to increase the contributions of young people to the sustainable development of the twin-island Federation. The initiative, dubbed the Youth Capacity Building Small Grants Project on Youth in Sustainable Development, will build the capacity and practical skills of young people to design, implement, and monitor interventions relevant to the social, economic, and sustainable development of youth and their communities. The project is geared towards members of youth groups specifically. It is spearheaded by the national youth ambassador corps in collaboration with the GEF Small Grants Programme (SGP), and the Departments of Youth in St. Kitts, and Nevis. The Small Grants Project is funding the initiative to the tune of US$49,970.00. SGP…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.