Question
Chapter 7, Problem 15P
To determine
The average vehicle delay for the approach.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
An approach to a pretimed signal has 25 seconds of effective green. The approach volume is 500 veh/h and the saturation flow rate is 1400 veh/h. If the average vehicle delay is 20 seconds assuming D/D/1 queuing, determine the cycle length (in seconds)_____.
Traffic arrives at an approach of a signalized intersection at a flow rate of 360 veh/h. The approach receives 30 seconds effective green time in a 60 second cycle. The departure rate during effective green is 900 veh/h. Assume D/D/1 queuing at this approach, analyze traffic operation at this approach and provide statistics to quantify traffic operation
Compute the average approach delay per cycle, given the saturation flow rate of 2400 veh/h and is allocated 24 seconds of effective green in an 80-second signal cycle. Flow at the approach is 500 veh/h. Assume the traffic flow accounts for the peak 15-min period and that there is no initial queue at the start of the analysis period.
Chapter 7 Solutions
Principles of Highway Engineering and Traffic Analysi (NEW!!)
Ch. 7 - Prob. 1PCh. 7 - Prob. 2PCh. 7 - Prob. 3PCh. 7 - Prob. 4PCh. 7 - Prob. 5PCh. 7 - Prob. 6PCh. 7 - Prob. 7PCh. 7 - Prob. 8PCh. 7 - Prob. 9PCh. 7 - Prob. 10P
Ch. 7 - Prob. 11PCh. 7 - Prob. 12PCh. 7 - Prob. 13PCh. 7 - Prob. 14PCh. 7 - Prob. 15PCh. 7 - Prob. 16PCh. 7 - Prob. 17PCh. 7 - Prob. 18PCh. 7 - Prob. 19PCh. 7 - Prob. 20PCh. 7 - Prob. 21PCh. 7 - Prob. 22PCh. 7 - Prob. 23PCh. 7 - Prob. 24PCh. 7 - Prob. 25PCh. 7 - Prob. 26PCh. 7 - Prob. 27PCh. 7 - Prob. 28PCh. 7 - Prob. 29PCh. 7 - Prob. 30PCh. 7 - Prob. 31PCh. 7 - Prob. 32PCh. 7 - Prob. 33PCh. 7 - Prob. 34PCh. 7 - Prob. 35PCh. 7 - Prob. 36PCh. 7 - Prob. 37PCh. 7 - Prob. 38PCh. 7 - Prob. 39PCh. 7 - Prob. 40PCh. 7 - Prob. 41PCh. 7 - Prob. 42PCh. 7 - Prob. 43PCh. 7 - Prob. 44PCh. 7 - Prob. 45PCh. 7 - Prob. 46PCh. 7 - Prob. 47PCh. 7 - Prob. 48PCh. 7 - Prob. 49PCh. 7 - Prob. 50PCh. 7 - Prob. 51PCh. 7 - Prob. 52PCh. 7 - Prob. 53PCh. 7 - Prob. 54PCh. 7 - Prob. 55PCh. 7 - Prob. 56PCh. 7 - Prob. 57PCh. 7 - Prob. 58PCh. 7 - Prob. 59PCh. 7 - Prob. 60PCh. 7 - Prob. 61PCh. 7 - Prob. 62P
Knowledge Booster
Similar questions
- TRANSPORTATION ENGINEERING-TRAFFIC SIGNALS" Recent analysis at an approach to pre-time signalized intersection indicate that the volume-to-capacity ratio (v/c) is 0.8, htat saturation flow rate (s) is 1600 vehicles/hour, and the effective green time is 50 seconds. If the average delay, assuming D/D/1 is 11.25 seconds per vehicle, determine the arrival flow rate (vehicles/hour) and the cycle length.arrow_forwardAn approach to a signalized intersection has a saturation flow rate of 1800 veh/h. At the beginning of an effective red, there are six vehicles in the queue and vehicles arrive at 900 veh/h. The signal has a 60- second cycle with 25 seconds of effective red. What is the total vehicle delay after one cycle (assume D/D/1 queuing)?arrow_forwardAn intersection approach has a saturation flow rate of 1500 veh/h, and vehicles arrive at the approach at the rate of 800 veh/h. The approach is controlled by a pretimed signal with a cycle length of 60 seconds and D/D/1 queuing holds. Local standards dictate that signals should be set such that all approach queues dissipate 10 seconds before the end of the effective green portion of the cycle. Assuming that approach capacity exceeds arrivals, determine the maximum length of effective red that will satisfy the local standards.arrow_forward
- An approach to a pretimed signal has 32 seconds of effective green, a saturation flow rate of 1800 veh/h, and a volume-to-capacity ratio less than 1. If the cycle length is 115 seconds and the overall delay formula (Eq. 7.27) estimates an average delay that is 38 seconds greater than that estimated by using just the uniform delay formula, determine the vehicle arrival rate in veh/h. (Assume the signal is isolated and d_3 = 0.arrow_forwardAn approach to a pre-timed signal has 40 sec of effective green in a 75-second cycle.The approach volume is 700 veh/h and the saturation flow rate is 1600 veh/h.Calculate the time to queue clearance after the start of the effective green, themaximum number of vehicles in the queue, the total vehicle delay per cycle andthe average delay per vehicle assuming D/D/1 queuing.arrow_forwardVehicles arrive at an intersection approach at 550 veh/h at the beginning of an effective red and 15 vehicles are left in the queue from the previous cycle (end of the effective green). Due to peak hour congestion, the arrival rate increases 50 veh/h/min. Therefore after 1 minute, the arrival rate will be 600 veh/h, after 2 minutes it is 650 veh/h. The saturation flow rate of the approach is 1800 veh/h, the cycle length is 65 seconds, and the effective green time is 30 seconds. Determine the total vehicle delay until complete queue clearance. (Assume D/D/1 queuing).arrow_forward
- An approach to a pretimed signal has 30 seconds of effective red, and D/D/1 queuing holds. The total delay at the approach is 83.33 veh-s/cycle and the saturation flow rate is 1000 veh/h. If the capacity of the approach equals the number of arrivals per cycle, determine the approach flow rate and cycle length.arrow_forwardFor a given one-lane approach of a signalized intersection, the base free flow speed is 40 mph, flow rate is 450 vphpl, saturation flow rate is 1,800 vphgpl, cycle length and red interval are 90 seconds and 30 seconds. Compute the following: The total time duration from the first vehicle in queue to the last queued vehicle being discharged per cycle The longest queue length and total number of vehicles in queue per cycle; Total vehicle-hours of delay and average delay per vehicle per cycle.arrow_forwardThe southbound approach of a signalized intersection carries a flow of 1000 veh/h/ln at a velocity of 50 mi/h. The duration of the red signal indication for this approach is 15 sec. If the saturation flow is 2000 veh/h/ln with a density of 75 veh/ln, the jam density is 150 veh/mi, determine the following:a. The length of the queue at the end of the red phaseb. The maximum queue lengthc. The time it takes for the queue to dissipate after the end of the red indication. What do you understand by traffic engineering? Explain.arrow_forward
- A simple four legs intersection needs a fixed time signal and the traffic flow condition is shown as below. Determine (a) the critical flow in N-S and E-W directions. (b) Find out the saturation flow if saturation headway is 1.5s. (c) Determine the cycle length and distribution of green time (suppose the lost time per phase is 4.2 seconds)arrow_forwardThe southbound approach of a signalized intersection carries a flow of 1000 veh/h/ln at a velocity of 50 mi/h. The duration of the red signal indication for this approach is 15 sec. If the saturation flow is 2000 veh/h/ln with a density of 75 veh/ln, the jam density is 150 veh/mi, determine the following: a. The length of the queue at the end of the red phase b. The maximum queue length c. The time it takes for the queue to dissipate after the end of the red indication.arrow_forwardThe saturation flow for an intersection approach is 3600 veh/h. At the beginning of cycle no vehicles are queued. The signal is timed so that what the queue is 13 vehicles the effective green begins. If the queue dissipates 8 seconds before the end of the cycle and the cycle length is 60 seconds. What is the arrival rate assuming D/D/1 queuing?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Traffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage Learning
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning