Interpreting Direct Materials Price, Quantity Variances
Perfect Pet Collar Company makes custom leather pet collars. The company expects each collar to require 1.5 feet of leather and predicts leather will cost $2.50 per foot. Suppose Perfect Pet made 60 collars during February. For these 60 collars, the company actually averaged 1.75 feet of leather per collar and paid $2.00 per foot.
Required:
- Compute the standard direct materials cost per unit.
(a)
Concept introduction:
Price variance:
It is the difference between price per unit in standard and actual price of product and multiplying that with quantity purchased in actual.
Quantity variance:
It is referred to the amount which is computed by multiplying the standard price per unit with the difference between quantity in actual term and standard term of product.
Direct Material cost variance:
This amount is calculated as the difference between standard cost and actual cost of direct material. The result is favorable when price variance is more than quantity variance. The result is unfavorable when price variance is less than quantity variance.
To compute:
The standard direct materials cost per unit.
Answer to Problem 3E
The standard direct materials cost per unit is
Explanation of Solution
Perfect pet collar company produces
Standard quantity of leather is
Actual quantity of leather is
Standard quantity
Actual quantity
Calculate standard direct materials cost per unit:
(b)
Concept introduction:
Price variance:
It is the difference between price per unit in standard and actual price of product and multiplying that with quantity purchased in actual.
Quantity variance:
It is referred to the amount which is computed by multiplying the standard price per unit with the difference between quantity in actual term and standard term of product.
Direct Material cost variance:
This amount is calculated as the difference between standard cost and actual cost of direct material. The result is favorable when price variance is more than quantity variance. The result is unfavorable when price variance is less than quantity variance.
The direct materials price variance will be favorable or unfavorable.
Answer to Problem 3E
The direct materials price variance is favorable.
Explanation of Solution
The standard price of per foot is
(c)
Concept introduction:
Price variance:
It is the difference between price per unit in standard and actual price of product and multiplying that with quantity purchased in actual.
Quantity variance:
It is referred to the amount which is computed by multiplying the standard price per unit with the difference between quantity in actual term and standard term of product.
Direct Material cost variance:
This amount is calculated as the difference between standard cost and actual cost of direct material. The result is favorable when price variance is more than quantity variance. The result is unfavorable when price variance is less than quantity variance.
The direct materials quantity variance will be favorable or unfavorable.
Answer to Problem 3E
The direct materials quantity variance is unfavorable.
Explanation of Solution
The standard quantity of material is
(d)
Concept introduction:
Price variance:
It is the difference between price per unit in standard and actual price of product and multiplying that with quantity purchased in actual.
Quantity variance:
It is referred to the amount which is computed by multiplying the standard price per unit with the difference between quantity in actual term and standard term of product.
Direct Material cost variance:
This amount is calculated as the difference between standard cost and actual cost of direct material. The result is favorable when price variance is more than quantity variance. The result is unfavorable when price variance is less than quantity variance.
To explain:
The pattern of variances.
Answer to Problem 3E
The potential explanation on the pattern of variances is discussed.
Explanation of Solution
Market fluctuation is the main reason of variance in the price of material. Responsibility of material price variance is of purchasing manager of the companies. So, for P.P.C., the direct materials price variance is favorable.
(e)
Concept introduction:
Price variance:
It is the difference between price per unit in standard and actual price of product and multiplying that with quantity purchased in actual.
Quantity variance:
It is referred to the amount which is computed by multiplying the standard price per unit with the difference between quantity in actual term and standard term of product.
Direct Material cost variance:
This amount is calculated as the difference between standard cost and actual cost of direct material. The result is favorable when price variance is more than quantity variance. The result is unfavorable when price variance is less than quantity variance.
To explain:
From where it will begin to investigate the variances.
Answer to Problem 3E
The project manager is responsible for material. So, he has to find out the reason for the variance and also take necessary actions.
Explanation of Solution
P.P.C. has an unfavorable direct material quantity variance. The reason of this is purchasing of poor quality of material, i.e., to produce one unit, different types of ingredients are used. So, it is important that the manager should find out the reason and correct the variances.
(f)
Concept introduction:
Price variance:
It is the difference between price per unit in standard and actual price of product and multiplying that with quantity purchased in actual.
Quantity variance:
It is referred to the amount which is computed by multiplying the standard price per unit with the difference between quantity in actual term and standard term of product.
Direct Material cost variance:
This amount is calculated as the difference between standard cost and actual cost of direct material. The result is favorable when price variance is more than quantity variance. The result is unfavorable when price variance is less than quantity variance.
To compute:
The direct material price and quantity variances.
Answer to Problem 3E
Direct material price variance is
Direct material quantity variance is
Explanation of Solution
Calculation of direct material price variance:
Hence, the direct material price variance is
Calculation of direct material quantity variance:
Hence, the direct material quantity variance is
Want to see more full solutions like this?
Chapter 9 Solutions
GEN COMBO LOOSE LEAF FOR MANAGERIAL ACCOUNTING; CONNECT ACCESS CARD
- Direct materials variances Bellingham Company produces a product that requires 2.5 standard pounds per unit. The standard price is 3.75 per pound. If 15,000 units used 36,000 pounds, which were purchased at 4.00 per pound, what is the direct materials (A) price variance, (B) quantity variance, and (C) cost variance?arrow_forwardCalculation of materials and labor variances Fritz Corp. manufactures and sells a single product. The company uses a standard cost system. The standard cost per unit of product follows: The charges to the manufacturing department for November, when 5,000 units were produced, follow: The Purchasing department normally buys about the same quantity as is used in production during a month. In November, 5,500 lb were purchased at a price of $2.90 per pound. Required: Calculate the following from standard costs for the data given, using the formulas on pages 421–422 and 424: Materials quantity variance. Materials purchase price variance (at time of purchase). Labor efficiency variance. Labor rate variance. Give some reasons as to why both the materials quantity variance and labor efficiency variance might be unfavorable.arrow_forwardUse the following standard cost card for 1 gallon of ice cream to answer the questions. Actual direct costs incurred to make 50 gallons of ice cream: 275 quarts of cream at $1.05 per quart 832 ounces of sugar at $0.075 per ounce 165 minutes of labor at $37 per hour All materials used were bought during the current period. A. Compute the material and labor variances. B. comment on the results and possible causes of the variances.arrow_forward
- Use the following standard cost card for 1 gallon of ice cream to answer the questions. Actual direct costs incurred to make 50 gallons of ice cream: 275 quarts of cream at $1.05 per quart 832 ounces of sugar at $0.075 per ounce 165 minutes of labor at $37 per hour All material used was bought during the current period. A. Compute the material and labor variances. B. Comment on the results and possible causes of the variances.arrow_forwardThe production cost for UV protective sunglasses is $5.50 per unit and fixed costs are $19,400 per month. How much is the favorable or unfavorable variance if 14,000 units were produced for a total of $97,000?arrow_forwardUse the following information to complete Brief Exercises 10-25 and 10-26: Tico Inc. produces plastic bottles. Each bottle has a standard labor requirement of 0.03 hour. During the month of April, 900,000 bottles were produced using 25,200 labor hours @ 15.00. The standard wage rate is 13.50 per hour. 10-26 Labor Rate and Efficiency Variances Refer to the information above for Tico Inc. on the previous page Required: Calculate the labor rate and efficiency variances using the columnar and formula approaches.arrow_forward
- The Whizbang Company makes a special type of toy. Each top takes 6 ounces of a special material that costs $3 per ounce. Whizbang bought 4,000 ounces of the material at a cost of $11,300. They used 3,400 ounces to make 534 toys. Compute the direct materials price variance, the direct materials quantity variance, and the total direct materials cost variance.arrow_forwardDirect materials and direct labor variance analysis Lenni Clothing Co. manufactures clothing in a small manufacturing facility. Manufacturing has 25 employees. Each employee presently provides 40 hours of productive labor per week. Information about a production week is as follows: Instructions Determine (A) the standard cost per unit for direct materials and direct labor; (B) the price variance, quantity variance, and total direct materials cost variance; and (C) the rate variance, time variance, and total direct labor cost variance.arrow_forwardCalculating factory overhead: two variances Munoz Manufacturing Co. normally produces 10,000 units of product X each month. Each unit requires 2 hours of direct labor, and factory overhead is applied on a direct labor hour basis. Fixed costs and variable costs in factory overhead at the normal capacity are 2.50 and 1.50 per direct labor hour, respectively. Cost and production data for May follow: a. Calculate the flexible-budget variance. b. Calculate the production-volume variance. c. Was the total factory overhead under- or overapplied? By what amount?arrow_forward
- Kavallia Company set a standard cost for one item at 328,000; allowable deviation is 14,500. Actual costs for the past six months are as follows: Required: 1. Calculate the variance from standard for each month. Which months should be investigated? 2. What if the company uses a two-part rule for investigating variances? The allowable deviation is the lesser of 4 percent of the standard amount or 14,500. Now which months should be investigated?arrow_forwardFitzgerald Company manufactures sewing machines, and they produced 2,500 this past month. The standard variable manufacturing overhead (M0H) rate used by the company is $6.75 per machine hour. Each sewing machine requires 13.5 machine hours. Actual machine hours used last month were 33,500, and the actual variable MOH rate last month was $7.00. Calculate the variable overhead rate variance and the variable overhead efficiency variance.arrow_forwardCorolla Manufacturing has a standard cost for steel of $20 per pound for a product that uses 4 pounds of steel. During September, Corolla purchased and used 4,200 pounds of steel to make 1,040 units. They paid $20.75 per pound for the steel. Compute the direct materials price variance, the direct materials quantity variance, and the total direct materials cost variance for the month of September. What would change if Corolla had made 2,200 units?arrow_forward
- Principles of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegeManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,
- Principles of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage LearningManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning