To determine
Concept introduction:
Price variance:
It is the difference between price per unit in standard and actual price of product and multiplying that with quantity purchased in actual.
Quantity variance:
It is referred to as the amount which is computed by multiplying the standard price per unit with the difference between quantity in actual term and standard term of product.
Direct Material spending variance:
This is calculated by combining material price variance and material quantity variance.
To compute:
The direct material price, quantity and spending variances.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionChapter 9 Solutions
GEN COMBO LOOSE LEAF FOR MANAGERIAL ACCOUNTING; CONNECT ACCESS CARD
Ch. 9 - Briefly describe the difference between budgetary...Ch. 9 - What are standard costs? When are they set?Ch. 9 - Prob. 3QCh. 9 - Prob. 4QCh. 9 - Prob. 5QCh. 9 - Prob. 6QCh. 9 - Prob. 7QCh. 9 - Prob. 8QCh. 9 - Prob. 9QCh. 9 - How do the master budget, flexible budget, and...
Ch. 9 - Prob. 11QCh. 9 - What type of variance is calculated by comparing...Ch. 9 - Prob. 13QCh. 9 - Prob. 14QCh. 9 - Prob. 15QCh. 9 - Prob. 16QCh. 9 - Prob. 17QCh. 9 - Prob. 18QCh. 9 - What are the two variable overhead variances? What...Ch. 9 - Prob. 20QCh. 9 - Prob. 21QCh. 9 - Prob. 22QCh. 9 - Prob. 23QCh. 9 - Prob. 1MCCh. 9 - Prob. 2MCCh. 9 - Variances are always noted as favorable or...Ch. 9 - What type of budget is ail integrated set of...Ch. 9 - Prob. 5MCCh. 9 - Prob. 6MCCh. 9 - Prob. 7MCCh. 9 - Prob. 8MCCh. 9 - Prob. 9MCCh. 9 - Prob. 10MCCh. 9 - Prob. 1MECh. 9 - Creating Grading Scale Based on Ideal, Tight but...Ch. 9 - Prob. 3MECh. 9 - Prob. 4MECh. 9 - Calculating Unknown Values for Direct Labor...Ch. 9 - Prob. 6MECh. 9 - Prob. 7MECh. 9 - Prob. 8MECh. 9 - Prob. 9MECh. 9 - Prob. 10MECh. 9 - Prob. 11MECh. 9 - Prob. 12MECh. 9 - Preparing Journal Entries to Record Direct Labor...Ch. 9 - Prob. 1ECh. 9 - Prob. 2ECh. 9 - Interpreting Direct Materials Price, Quantity...Ch. 9 - Calculating Direct Materials and Direct Labor...Ch. 9 - Calculating Direct Materials and Direct Labor...Ch. 9 - Prob. 6ECh. 9 - Prob. 7ECh. 9 - Prob. 8ECh. 9 - Prob. 9ECh. 9 - Preparing Journal Entries to Record Direct...Ch. 9 - Prob. 11ECh. 9 - Calculating Fixed Manufacturing Overhead Spending,...Ch. 9 - Prob. 13ECh. 9 - Prob. 14ECh. 9 - Prob. 15ECh. 9 - Prob. 16ECh. 9 - Prob. 17ECh. 9 - Determining Actual, Standard Costs, and Variances...Ch. 9 - Prob. 1.1GAPCh. 9 - Prob. 1.2GAPCh. 9 - Prob. 1.3GAPCh. 9 - Prob. 2.1GAPCh. 9 - Prob. 2.2GAPCh. 9 - Prob. 2.3GAPCh. 9 - Prob. 3.1GAPCh. 9 - Prob. 3.2GAPCh. 9 - Prob. 3.3GAPCh. 9 - Prob. 4GAPCh. 9 - Prob. 5.1GAPCh. 9 - Prob. 5.2GAPCh. 9 - Prob. 5.3GAPCh. 9 - Prob. 6.1GAPCh. 9 - Prob. 6.2GAPCh. 9 - Prob. 6.3GAPCh. 9 - Prob. 7.1GAPCh. 9 - Prob. 7.2GAPCh. 9 - Prob. 7.3GAPCh. 9 - Preparing Journal Entries to Record Fixed...Ch. 9 - Prob. 9.1GAPCh. 9 - Prob. 9.2GAPCh. 9 - Prob. 10.1GAPCh. 9 - Prob. 10.2GAPCh. 9 - Prob. 1.1GBPCh. 9 - Prob. 1.2GBPCh. 9 - Prob. 1.3GBPCh. 9 - Prob. 2.1GBPCh. 9 - Prob. 2.2GBPCh. 9 - Prob. 2.3GBPCh. 9 - Prob. 3.1GBPCh. 9 - Prob. 3.2GBPCh. 9 - Prob. 3.3GBPCh. 9 - Prob. 4GBPCh. 9 - Prob. 5.1GBPCh. 9 - Prob. 5.2GBPCh. 9 - Prob. 5.3GBPCh. 9 - Prob. 6.1GBPCh. 9 - Prob. 6.2GBPCh. 9 - Prob. 6.3GBPCh. 9 - Prob. 7.1GBPCh. 9 - Prob. 7.2GBPCh. 9 - Prob. 7.3GBPCh. 9 - Prob. 8GBPCh. 9 - Prob. 9.1GBPCh. 9 - Prob. 9.2GBPCh. 9 - Calculating Variable Manufacturing Overhead, Fixed...Ch. 9 - Prob. 9.4GBPCh. 9 - Prob. 9.5GBPCh. 9 - Prob. 9.6GBPCh. 9 - Prob. 10.1GBPCh. 9 - Prob. 10.2GBP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Calculation of materials and labor variances Fritz Corp. manufactures and sells a single product. The company uses a standard cost system. The standard cost per unit of product follows: The charges to the manufacturing department for November, when 5,000 units were produced, follow: The Purchasing department normally buys about the same quantity as is used in production during a month. In November, 5,500 lb were purchased at a price of $2.90 per pound. Required: Calculate the following from standard costs for the data given, using the formulas on pages 421–422 and 424: Materials quantity variance. Materials purchase price variance (at time of purchase). Labor efficiency variance. Labor rate variance. Give some reasons as to why both the materials quantity variance and labor efficiency variance might be unfavorable.arrow_forwardCalculating factory overhead: two variances Monrovia Manufacturing Inc. normally produces 10,000 units of product A each month. Each unit requires 4 hours of direct labor, and factory overhead is applied on a direct labor hour basis. Fixed costs and variable costs in factory overhead at the normal capacity are 10 and 5 per unit, respectively. Cost and production data for June follow: a. Calculate the flexible-budget variance. b. Calculate the production-volume variance. c. Was the total factory overhead under- or overapplied? By what amount?arrow_forwardDirect materials and direct labor variance analysis Lenni Clothing Co. manufactures clothing in a small manufacturing facility. Manufacturing has 25 employees. Each employee presently provides 40 hours of productive labor per week. Information about a production week is as follows: Instructions Determine (A) the standard cost per unit for direct materials and direct labor; (B) the price variance, quantity variance, and total direct materials cost variance; and (C) the rate variance, time variance, and total direct labor cost variance.arrow_forward
- Factory overhead cost variance report Tannin Products Inc. prepared the following factory overhead cost budget for the Trim Department for July of the current year, during which it expected to use 20,000 hours for production: Tannin has available 25,000 hours of monthly productive capacity in the Trim Department under normal business conditions. During July, the Trim Department actually used 22,000 hours for production. The actual fixed costs were as budgeted. The actual variable overhead for July was as follows: Construct a factory overhead cost variance report for the Trim Department for July.arrow_forwardDirect materials and direct labor variances At the beginning of June, Bezco Toy Company budgeted 5,000 toy action figures to be manufactured in June at standard direct materials and direct labor costs as follows: The standard materials price is 4.00 per pound. The standard direct labor rate is 18.00 per hour. At the end of June, the actual direct materials and direct labor costs were as follows: There were no direct materials price or direct labor rate variances for June. In addition, assume no changes in the direct materials inventory balances in June. Bezco Toy Company actually produced 4,850 units during June. Determine the direct materials quantity and direct labor time variances.arrow_forwardCalculating factory overhead: two variances Munoz Manufacturing Co. normally produces 10,000 units of product X each month. Each unit requires 2 hours of direct labor, and factory overhead is applied on a direct labor hour basis. Fixed costs and variable costs in factory overhead at the normal capacity are 2.50 and 1.50 per direct labor hour, respectively. Cost and production data for May follow: a. Calculate the flexible-budget variance. b. Calculate the production-volume variance. c. Was the total factory overhead under- or overapplied? By what amount?arrow_forward
- Direct materials variances Bellingham Company produces a product that requires 2.5 standard pounds per unit. The standard price is 3.75 per pound. If 15,000 units used 36,000 pounds, which were purchased at 4.00 per pound, what is the direct materials (A) price variance, (B) quantity variance, and (C) cost variance?arrow_forwardControl Limits During the last 6 weeks, the actual costs of labor for Solsana Company were as follows: The standard materials cost for each week was 40,000 with an allowable deviation of 5,000. Required: Plot the actual costs over time against the upper and lower limits. Comment on whether or not there is a need to investigate any of the variances. Use the following information to complete Brief Exercises 10-34 and 10-35: Young Inc. produces plastic bottles. Production of 16-ounce bottles has a standard unit quantity of 0.45 ounce of plastic per bottle. During the month of June, 240,000 bottles were produced using 110,000 ounces of plastic. The actual cost of plastic was 0,042 per ounce, and the standard price was 0,045 per ounce. There is no beginning or ending inventories of plastic.arrow_forwardControl Limits During the last 6 weeks, the actual costs of materials for Brennen Company were as follows: The standard materials cost for each week was 60,000 with an allowable deviation of 6,000. Required: Plot the actual costs over time against the upper and lower limits. Comment on whether or not there is a need to investigate any of the variances. Use the following information to complete Brief Exercises 10-23 and 10-24: Krumple Inc. produces aluminum cans. Production of 12-ounce cans has a standard unit quantity of 4.7 ounces of aluminum per can. During the month of April, 450,000 cans were produced using 1,875,000 ounces of aluminum. The actual cost of aluminum was 0.10 per ounce and the standard price was 0.08 per ounce. There are no beginning or ending inventories of aluminum.arrow_forward
- Kavallia Company set a standard cost for one item at 328,000; allowable deviation is 14,500. Actual costs for the past six months are as follows: Required: 1. Calculate the variance from standard for each month. Which months should be investigated? 2. What if the company uses a two-part rule for investigating variances? The allowable deviation is the lesser of 4 percent of the standard amount or 14,500. Now which months should be investigated?arrow_forwardThe normal capacity of a manufacturing plant is 30,000 direct labor hours or 20,000 units per month. Standard fixed costs are 6,000, and variable costs are 12,000. Data for two months follow: For each month, make a single journal entry to charge overhead to Work in Process, to close Factory Overhead, and to record variances. Indicate the types of variances and state whether each is favorable or unfavorable. (Hint: You must first compute the flexible-budget and production-volume variances.)arrow_forwardGeorgia Gasket Co. budgets 8,000 direct labor hours for the year. The total overhead budget is expected to amount to 20,000. The standard cost for a unit of the companys product estimates the variable overhead as follows: The actual data for the period follow: Using the four-variance method, calculate the overhead variances. (Hint: First compute the budgeted fixed overhead rate.)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegeFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,
- Principles of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage LearningManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
What is variance analysis?; Author: Corporate finance institute;https://www.youtube.com/watch?v=SMTa1lZu7Qw;License: Standard YouTube License, CC-BY