Chapter 10, Problem 13P
a)
Summary Introduction
To determine:The presence of any non-randomness variations in data.
Introduction: Quality is a measure of excellence or a state of being free from deficiencies, defects and important variations. It is obtained by consistent and strict commitment to certain standards to attain uniformity of a product to satisfy consumers’ requirement.
b)
Summary Introduction
To determine: The presence of any non-randomness variations in data.
Introduction: Quality is a measure of excellence or a state of being free from deficiencies, defects and important variations. It is obtained by consistent and strict commitment to certain standards to attain uniformity of a product to satisfy consumers’ requirement.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
p-chart and c-chart. Using the appropriate control chart, determine two-sigma control limits for each Problem 4 case:a. An inspector found an average of 3.9 scratches in the exterior paint of each of the automobilesbeing prepared for shipment to dealers.b. Before shipping lawn mowers to dealers, an inspector attempts to start each mower and notes anythat do not start on the first try. The lot size is 100 mowers, and an average of 4 did not start (4percent).
P-chart and c-chart. Using the appropriate control chart, determine two-sigma controllimits for each Problem case,
a. An inspector found an average of 3.9 scratches in the exterior paint of each of theautomobiles being prepared for shipment to dealers.
b. Before shipping lawnmowers to dealers, an inspector attempts to start each mowerand notes any that do not start on the first try. The lot size is 100 mowers, and anaverage of 4 did not start (4 percent).
The following data were collected on the number of nonconformities per unit for
10
time periods. Complete parts (a) and (b).
Time
1
2
3
4
5
6
7
8
9
10
Nonconformities
Per Unit
23
11
14
15
6
14
11
9
13
6
a. Construct the appropriate control chart and determine the LCL and UCL.
What is the lower control limit? Select the correct choice below and fill in any answer boxes within your choice.
A.
LCL=enter your response here
(Round to three decimal places as needed.)
B.
There is no lower control limit.
Chapter 10 Solutions
Operations Management
Ch. 10.2 - A potato chip is a delicate thing Fragile A pound...Ch. 10.2 - A potato chip is a delicate thing Fragile A pound...Ch. 10.5 - It's estimated that more than 7 000 hospital...Ch. 10.5 - It's estimated that more than 7 000 hospital...Ch. 10 - Prob. 1DRQCh. 10 - Prob. 2DRQCh. 10 - Prob. 3DRQCh. 10 - Prob. 4DRQCh. 10 - Prob. 5DRQCh. 10 - Prob. 6DRQ
Ch. 10 - Prob. 7DRQCh. 10 - Prob. 8DRQCh. 10 - Prob. 9DRQCh. 10 - Prob. 10DRQCh. 10 - Prob. 11DRQCh. 10 - Prob. 12DRQCh. 10 - Prob. 13DRQCh. 10 - Prob. 14DRQCh. 10 - Prob. 15DRQCh. 10 - Prob. 16DRQCh. 10 - Prob. 1TSCh. 10 - Prob. 2TSCh. 10 - Prob. 3TSCh. 10 - Prob. 1CTECh. 10 - Prob. 2CTECh. 10 - Prob. 3CTECh. 10 - Prob. 4CTECh. 10 - Prob. 1PCh. 10 - Prob. 2PCh. 10 - Prob. 3PCh. 10 - Prob. 4PCh. 10 - Prob. 5PCh. 10 - Prob. 6PCh. 10 - Prob. 7PCh. 10 - Prob. 8PCh. 10 - Prob. 9PCh. 10 - Prob. 10PCh. 10 - Prob. 11PCh. 10 - Prob. 12PCh. 10 - Prob. 13PCh. 10 - Prob. 14PCh. 10 - Prob. 15PCh. 10 - Prob. 16PCh. 10 - Prob. 17PCh. 10 - A production process consists of a three-step...Ch. 10 - Prob. 19PCh. 10 - Prob. 20PCh. 10 - Prob. 21PCh. 10 - Prob. 22PCh. 10 - Prob. 23PCh. 10 - Prob. 24PCh. 10 - Prob. 25PCh. 10 - Prob. 26PCh. 10 - Prob. 27PCh. 10 - Prob. 28PCh. 10 - Prob. 29PCh. 10 - Prob. 1.1CQCh. 10 - Prob. 2.1CQCh. 10 - Prob. 2.2CQCh. 10 - Prob. 2.3CQCh. 10 - Prob. 2.4CQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Pertaining to the OC curve for any control chart, which of the following is INCORRECT? Select one: a. None of those listed b.OC stands for Operating Characteristics c. The error shown in the OC curve is type 2 error d. For a given sample size, the probability of error is inversely proportional to the amount of deviation (away from the target value) e. An OC curve corresponding to a larger sample size is steeperarrow_forwardWhat does a run of 5 points above or below the centerline in a control chart imply?arrow_forwardConstruct the appropriate control chart for the 11 observations, and determine if the process is in control using two sigma limits. No. of defects per unit for the observations are: 11, 6, 5, 2, 7, 7, 8, 4, 9, 3, 1. a. 3 observations out of control b. 1 observations out of control c. 2 observations out of control d. Under controlarrow_forward
- What trade-offs are involved in each of these decisions?a. Deciding whether to use two-sigma or three-sigma control limits.b. Choosing between a large sample size and a smaller sample size.c. Trying to increase the capability of a process that is barely capable.arrow_forwardMcDaniel Shipyards wants to develop control charts to assess the quality of its steel plate. They take ten sheets of 1" steel plate and compute the number of cosmetic flaws on each roll. Each sheet is 20' by 100'. Based on the following data, develop limits for the control chart, plot the control chart, and determine whether the process is in control. Sheet Number of flaws 1 1 2 1 3 2 4 0 5 1 6 5 7 0 8 2 9 0 10 2arrow_forwardThe inner diameter of piston rings follows a normal distribution with mean 75mm and variance =9. The sample size is 5, X-bar chart is established. If L =2, what is the type I error rate when process is in-control? If we change the control limits to UCL = 78.354, and LCL = 71.646, what is Type I error rate?arrow_forward
- A quality inspector took five samples in five hours, each with four observations, of the length time for glue to dry. The analyst compute the mean of each sample and the computed the grand mean. All values are in minutes. Use this information to obtain three-sigma control limits for means. It is known from previous experience that the standard deviation of the process is 0.02 minutes. Draw a control chart Please provide a step-by-step solutionarrow_forwardcontrol charts for means and rangers. processing times for new accounts at bank are shown in the following table. five samples of four observations each have been taken. use the sample data in conjunction with table 10.3 to construct upper and lower control limits for both mean chart and range chart. do the result suggest that the process is in control? sample 1 sample 2 sample 3 sample 4 sample 5 10.2 10.3 9.7 9.9 9.8 9.9 98 9.9 10.3 10.2 9.8 9.9 9.9 10.1 10.3 10.1 10.4 10.1 10.5 9.7 40.0 40.4 39.6 40.8 40.0arrow_forwardCheckout time at a supermarket is monitored using a mean and a range chart. Six samples of n = 20 observations have been obtained and the sample means and ranges computed: Sample Mean Range 1 3.06 .42 2 3.15 .50 3 3.11 .41 4 3.13 .46 5 3.06 .46 6 3.09 .45 Using the factors in Table 10.3 , determine upper and lower limits for mean and range charts. Is the process in control?arrow_forward
- 10. To monitor the quality of pepperoni pizzas, a quality control manager collects random samples of pizzas and evaluates them. The process mean and standard deviation for the weight and diameter of pizzas are not known. Which of the following(s) is a correct matching between the type of data collected and the choice of control chart used? Select all correct matchings. Select one: a. The manager weighed the sampled pizzas and constructed a c-chart. b. The manager rated the appearance of sampled pizzas as acceptable or unacceptable and then constructed a c-chart. c. The manager counted the number of pepperonis per each inspected pizza and constructed a mean chart. d. The manager measured the diameter of the sampled pizzas and constructed a range chart.arrow_forwardwe have seen various methods to set control limits for control charts. Which method would you prefer and why?arrow_forwardLinda Boardman, I nc., an equipment manufacturerin Boston, has submitted a sample cutoff valve to improve yourmanufacturing process. Your process engineering department basconducted experiments and found that the valve has a mean (J.L)of 8.00 and a standard deviation (cr) of .04. Your desired performanceis f..L = 8.0 ±3cr, where cr = .045. What is the Cpk of theBoardman valve?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.