Concept explainers
A.
Interpretation: The expected time duration of the filming is to be computed including the PERT estimates is to be calculated.
Concept Introduction: Program Evaluation and review technique is a planning and control tool, wherein the work flow of various activities of a project are graphically represented and analyzed. This technique is distinct in the way that it deals with uncertainty in the activity completion times.
B.
Interpretation: The probability that the number of days required for the filming of the scene is 30 percent longer is to be computed.
Concept Introduction: Program Evaluation and review technique is a planning and control tool, wherein the work flow of various activities of a project are graphically represented and analyzed. This technique is distinct in the way that it deals with uncertainty in the activity completion times.
C.
Interpretation: The number of days to be planned for the filming, so as to be 95 percent sure of completion is to be calculated.
Concept Introduction: Program Evaluation and review technique is a planning and control tool, wherein the work flow of various activities of a project are graphically represented and analyzed. This technique is distinct in the way that it deals with uncertainty in the activity completion times.
Want to see the full answer?
Check out a sample textbook solutionChapter 10 Solutions
Production and Operations Analysis, Seventh Edition
- the budget of a project is $1 million. The actual cost for work performed is currently $700k. The budgetted cost for work performed is $660k. What is the current progress of the project? The budgeted cost for work scheduled is 700k. Is it on schedule?arrow_forwardYou are in charge of a project at the local community center. The center needs to remodel one ofthe rooms in time for the start of a new program. Delays in the project mean that the center mustrent other space at a nearby church at additional cost. Time and cost data for your project arecontained in below table. Your interest is in minimizing the cost of the project to the communitycenter.Using the normal times for each activity, what is the earliest date you can complete the project?Suppose the variable overhead costs are $50 per day for your project. Also, suppose that thecenter must pay $40 per day for a temporary room on day 15 or beyond. Find the minimum-costproject schedule using below format.The AON diagram for the community center project is below. Crash 4 times and find total cost.arrow_forwardA project has four activities that take 4, 3, 6, and 7 days, respectively. What is the totalcompletion time for the project?a. 3 days, because this is the minimum timeb. 7 days, because this is the maximum timec. 20 days, because this is the sum of the timesd. It is not possible to determine the total completion time from the given informationarrow_forward
- Suppose that a task in a project has the following time estimates: to=optimistic completion time=10 weeks tm=most likely completion time=17 weeks tp=pessimistic completion time=19 weeks Compute the expected task variance. The task expected task variance is _____ weeks. (Enter your response rounded to two decimal places.)arrow_forwardThe Cove at UP is looking to open a new location. Guillermo Santiago has been developing a project plan and has identified the following tasks, precedence relations, and normal task durations. \ tasks predecessors task duration start 0 A start 7 B A 20 C A 34 D B 39 E C,D 6 F D 15 G E,F 33 end G 0 Guillermo has studied project management at the University of Portland and knows that the starting and ending time of any task may be determined from the information in the table using the critical path method. Assume the following notation when answering the questions below: \ Metric Description ES Early start time for task EF Early finsh time for task LS Late start time for task LF Late finsh time for task TS Total slack for task FS Free slack for task IS Independent slack for task SS safety slack for task Please provide the CPM result for each of the following metrics: ES_{end} = LS_{D} = TS_{D} = EF_{G} = LF_{G} =arrow_forwardUnderstanding that, in the three-time estimate approach, the time to complete an activity is assumed to follow a Beta distribution. Write the formula illustrated in the text.arrow_forward
- In a network diagram, an activity:A) Is the largest unit of work effort consuming both time and resources that a project manager can schedule and control?B) Should always be something the company has had experience with. C) Is the smallest unit of work effort consuming both time and resources that a project manager can schedule and control?D) Must always have a single, precise estimate for the time duration.arrow_forwardYou are managing a software project with an initial budget estimate of 5 million USD. During interim cost and schedule performance analysis, you figured out that: You should have spent $650,000 till now based on your initial plans and 1,500 man/days of schedule activities You spent $425,000 till now and completed 600 man/days of schedule activities which should have cost $525,000 based on your initial plans. You re-estimated the budget required for the remaining work to be done as $4,500,000. Identify: BAC PV AC EV ETC Calculate: CPI SPI CV SV VAC EAC TCPIarrow_forwardCalculate the latest start for Task D if one of its successors, Task F, has a latest start on day 9, its other successor, Task E, has a latest start on day 10, and the duration of Task D is 2 days.arrow_forward
- PROJECT PLANNING & SCHEDULING WITH GANNT CHART Given the activities of a project, their time estimates, and their immediatepredecessors shown below:a. Draw the Gannt chart for this project.b. What’s the earliest expected time to finish the project?c. Which activities should not be delayed?d. Which activities can be delayed?e. What’s the maximum amount of time that each of the activities can be delayed without delaying the whole project? Activities Activity Times,months ImmediatePredecessors Maximum Slack,months A 2 - B 3 - C 2 A D 4 B E 4 C F 3 C G 5 D, E H 2 F, Garrow_forwardPlease answer the following multiple choice quesiton 1. Taylor knows that the team wants to receive the extra day off for getting the project launch out on time. She doesn't work as hard as she could because she knows her teammates will pick up her missed work to get the project done. What is this known as? Free rider effect Otiosum Halo effectarrow_forwardIf Activity C has an expected time estimate of 8 days, which of the following statements is TRUE? * The activity time estimates for Activity C are: 1, 7, and 19 days Activity C can be delayed for a maximum of 5 days Activity C should not be delayed The activity time estimates for Activity C are: 2, 4, and 9 daysarrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.