Question
Chapter 10.6, Problem 24P
A.
Summary Introduction
Interpretation: The load profiles for welders and pipe fitters are to be determined assuming an early start
Concept Introduction: Resource loading is a method of allocating manpower, equipment and materials required for completion of a project.
B.
Summary Introduction
Interpretation:The load profiles for welders and pipe fitters are to be determined assuminga late start schedule.
Concept Introduction: Resource loading is a method of allocating manpower, equipment and materials required for completion of a project.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
You have prepared the following schedule for a project in which the key resources is a tractor. There are three tractors available to the project. Activities A and D require one tractor to complete while activities B, C, E and F require 2 tractors.Develop a resource-constrained schedule in the loading chart that follows. Use the parallel method and heuristics given. Be sure to update each period as the computer would do. Record the early start (ES), late finish (LF) and slack (SL) for the new schedule
Activities K, M and S immediately follow activity H, and their latest start times are 14, 18, and 1 The latest finish time for activity H
A. is 11.
B. is 14.
C.is 18
D.annot be determined.
( don't hand writing solution)
Regarding section D with assigning the workstations:
How would Task F go first if it could not be completed with Task D? Usint LOT. regardless of the time each took, doesn't one still have to bare in mind the predecessors? I would assume Tasks A and B would be Workstation 1, considering that 45 plus 20 seconds is less than the cycle time and factoring in the fact that C only requires A to be completed, hence why the workstation should start at A followed by C.
Chapter 10 Solutions
Production and Operations Analysis, Seventh Edition
Ch. 10.2 - Prob. 1PCh. 10.2 - Prob. 2PCh. 10.2 - Prob. 3PCh. 10.2 - Prob. 4PCh. 10.2 - Prob. 5PCh. 10.2 - Prob. 6PCh. 10.3 - Prob. 7PCh. 10.3 - Prob. 8PCh. 10.3 - Prob. 9PCh. 10.3 - Prob. 10P
Ch. 10.4 - Prob. 11PCh. 10.4 - Prob. 12PCh. 10.4 - Prob. 13PCh. 10.4 - Prob. 14PCh. 10.4 - Prob. 15PCh. 10.4 - Prob. 16PCh. 10.5 - Prob. 17PCh. 10.5 - Prob. 18PCh. 10.5 - Prob. 19PCh. 10.5 - Prob. 20PCh. 10.5 - Prob. 21PCh. 10.6 - Prob. 22PCh. 10.6 - Prob. 23PCh. 10.6 - Prob. 24PCh. 10.6 - Prob. 25PCh. 10 - Prob. 26APCh. 10 - Prob. 27APCh. 10 - Prob. 28APCh. 10 - Prob. 29APCh. 10 - Prob. 30AP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- For the network schedule shown below, which statement is true? a. This is an example of the Activity-on-Node (AON) method of network diagramming.b. Activity F can start without waiting for the completion of Activity B.c. Activity B can occur concurrently with Activity D.d. To simplify the network, Activities F and G can be combined without changing the logic.arrow_forwardCreate a schedule for this house to be completed within the time frame Jan 4 to April 4. The following persons were selected to do various jobs. John-The guy responsible for the roughing, dry wall, and plastering Tom -clearing the construction site Jerry-Pouring the foundation and Masonry Craig-Plumber Mike-Electrician Steven- Tiling Joe-Carpenter The 10 Steps to Build a New Home Are: Prepare construction site and pour the foundation Construct rough framing Complete rough plumbing, electrical and HVAC Install insulation Complete drywall and interior textures; start exterior finishes Finish interior trim; install exterior driveways and walkways Install hard-surface flooring and countertops, and complete exterior grading Finish mechanical trims; install bathroom fixtures Install mirrors, shower doors and finish flooring, and finish exterior landscaping Final walkthrough with the builder Make sure to mark milestones.arrow_forwardActivities A, B, and C are started at Week 0 and are the immediatepredecessors for Activity J. If the earliest finish times for the threeactivities are Week 11, Week 15, and Week 10, respectively, then the earlieststart time for J will be A. Week 10B. Week 11C. Week 12D. Week 15arrow_forward
- Amanufacturer is designing a product layout for a new product production. It plans to use a production line for 8 hours per day in order to meet forecasted demand of 150 units per dayThe product requires 7 tasks in total. These tasks are namely, ABC, DE, Fand GrespectivelyTask A does not have any predecessor to start. To start Task B, it requires Task A to be completedStarting tasks C needs, the task B to be completed. Also starting task D needed task B to be completed. Task E can only start upon completion of Task C. Whereas starting task F needs the completion of both the tasks and E. Finally, starting task G needed, task F to be completed. The processing times for tasks, AB 3, C, D, E, F , and Gare are2.4,2.2,0.9, . 10.12. 1.8. are 1.5 minutes respectively. What should be the cycle time in minutes? .4.80 O2.67. c 4.56 d is the correct answer e3.20arrow_forwardThe achievement of the objectives of a project will be possible only by applying the appropriate scheduling methods and techniques. Differentiate between the most used scheduling methods and scheduling techniques.arrow_forwardA project consisting of eight activities satisfies the following precedence constraints: a. Construct a network for this project. (You should need only one pseudoactivity.)b. Compute the earliest and the latest starting and finishing times for each activity and identify the critical path.c. Draw a Gantt chart of the schedule for this project based on earliest starting times.arrow_forward
- Using Johnson's rule for 2-machine scheduling, the sequence is: Scheduled Order Job 1 ▼ B C E F A D Part 2 2 ▼ F C A D B E Part 3 3 ▼ A B D F C E Part 4 4 ▼ E D C B F A Part 5 5 ▼ F C D A E B Part 6 6 ▼ D C F B E A Part 7 For the schedule developed using Johnson's rule, the total length of time taken to complete the six jobs (including the 2nd operation) = enter your response here hours (enter your response as a whole number). ... Question content area right Part 1 Six jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows: Job Operation 1 (hours) Operation 2 (hours) A 4 8 B 10 5 C 3 11 D…arrow_forward. With activities B and C as immediate predecessors, the earliest start time for activity H must be equal to the largest of the earliest finish times for activities B and C. Thus, with EF = 6 for activity B and EF = 9 for activity C, 9 is the earliest start time for activity H (ES = 9). And with an activity time of 12 as shown in the node for activity H, what is the earliest finish time?arrow_forwardFor the activity on arrow network information given below (activity durations are givenin the table under part b): a. Compute the earliest event occurrence time (TEj), the latest allowable eventoccurrence time (TLj), and the event slack (ESj) for all nodes/events. b. Compute the four schedule dates (ESDij, EFDij, LSDij, LFDij) and the floats(TFij, FFij) for all activities.arrow_forward
- Task C is directly preceded by two tasks–task A and task B. Task A has an expected task completion time of five weeks and an ES time of week 6. Task B has an expected task completion time of seven weeks and an ES time of week 7. Task C has an expected task completion time of 10 weeks. The ES for activity C is?arrow_forwardThe Mowry Machine Shop still has five jobs to be processedas of 8 a.m. today (day 23) at its bottleneck operation. The daywhen the order arrived, processing time, and promised duedates are given in the following table. The jobs are listed inthe order of arrival.a. Develop separate schedules by using the FCFS and EDDrules. Compare the schedules on the basis of averageflow time and average days past due.b. Which rule gives the best schedule, in your judgment?Why?arrow_forwardThis section explains project scheduling strategies such as the WBS, Activity Definition, and Activity Sequencing (AS) (AS). Define and describe in accordance with the instructions.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY