Production and Operations Analysis, Seventh Edition
Production and Operations Analysis, Seventh Edition
7th Edition
ISBN: 9781478623069
Author: Steven Nahmias, Tava Lennon Olsen
Publisher: Waveland Press, Inc.
bartleby

Concept explainers

Question
Book Icon
Chapter 10.3, Problem 9P
Summary Introduction

Interpretation:The real life situations of the cost time curve in comparison to the assumption of its being linear.

Concept Introduction: Everyactivity /a set of activities have the costs to be incurred and the time of completion. The time and the cost always have a relationship i.e. cost of completion in a given time and vice versa i.e. time of completion for a given cost budget. Both are variable and each may or may not vary in direct proportion to the variation in the other variable. This is discussed below in terms of normal time/cost; crash time/cost; de-crashed time/cost wart projects.(De-crashing is used to reduce costs of non-critical activities by increasing the times because such time increase does not increase the total project time but reduces the resource requirements).

Blurred answer
Students have asked these similar questions
Discuss the assumption that the cost–time curve is linear. What shape might bemore realistic in practice?
Answer all the following questions based on Table 2 (a) Feasibility studies for a project is an early study before the project begins. List and briefly explain the feasibility processes. (b) Walkers Corporation is analyzing three capital projects with expected cash flows given in the Table 2 below. Each cash flow with an estimated of five years life and four year life. Interest rate of the cash flows is 10 % per annum. The Walkers Corporation uses investment appraisal techniques which is Payback Method. Analyze the appropriate calculations under the investment techniques stated above and give reasons for your investment advice. Table 2 Year Projects / Cash Flow (RM) Delta Gamma Beta 0 (250,000) (450,000) (650,000) 1 60,000 110,000 150,000 2 60,000 130,000 150,000 3 60,000 160,000 150,000 4 60,000 190,000 150,000 5 60,000 - 150,000
The table below contains data for the installation of new equipment in a manufacturing process for a steel corporation. Your company is responsible for the installation project. Indirect costs are $6,000 per week, and a penalty cost of $10,000 per week will be incurred by your company for every week the project is delayed beyond week 15. Activity Immediate Predecessor(s) Normal Time (weeks) Crash Time (weeks) Normal Cost ($) Crash Cost ($) A None 2 1 7,000 10,000 B None 2 2 3,000 3,000 C A 3 1 12,000 40,000 D B 3 2 12,000 28,000 E C 1 1 8,000 8,000 F  D, E 5 3 5,000 15,000 G E 3 2 9,000 18,000 H F, G 8 6 14,000 32,000 Construct a network diagram for the project. What are the project completion time and the total cost under normal conditions? What is the shortest time duration for this project regardless of cost? What is the resulting total cost? What is the…
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,