Question
Chapter 10, Problem 2P
a)
Summary Introduction
To determine: The upper and lower control limits.
Introduction:
Control chart:
It is a graph used to analyze the process change over a time period. A control chart has a upper control limit, and lower control which are used plot the time order.
b)
Summary Introduction
To determine: Whether the process is in a controlled state.
Introduction:
Control chart:
It is a graph used to analyze the process change over a time period. A control chart has a upper control limit, and lower control which are used plot the time order.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
An automatic filling machine is used to fill 1-liter bottles of cola. The machine’s output is approximately normal with a mean of 1.0 liter and standard deviation of .01 liter. Output is monitored using means of samples of 25 observations.
Determine upper and lower control limits that will include roughly 97% of the sample means when the process is in control. Using Appendix B, Table A to find the value of Z corresponding to the mean control limits.
Your supervisor, Lisa Lehmann, has asked that you report on the output of a machine on the factory floor. This machine is supposed to be producing optical lenses with a meanweight of 50 grams and a range of 3.5 grams. The following table contains the data for a sample size of n = 6 taken during the past 3 hours: a) What are the :X-chart control limits when the machine is working properly?b) What are the R-charL control limits when the machine is working properly?c) What seems to be happening? (Hint: Graph the data points. Run charts may be helpful.)
The Watson Electric Company produces incandescent light bulbs. The following data on the number oflumens for 40-watt light bulbs were collected when the process was in control.
a. Calculate control limits for an R-chart and an x-chart.b. Since these data were collected, some new employees were hired. A new sample obtained the following readings: 625, 592, 612, and 635. Is the process still in control?
Chapter 10 Solutions
OPERATIONS MANAGEMENT W/ CNCT+
Ch. 10.2 - A potato chip is a delicate thing Fragile A pound...Ch. 10.2 - A potato chip is a delicate thing Fragile A pound...Ch. 10.5 - It's estimated that more than 7 000 hospital...Ch. 10.5 - It's estimated that more than 7 000 hospital...Ch. 10 - Prob. 1DRQCh. 10 - Prob. 2DRQCh. 10 - Prob. 3DRQCh. 10 - Prob. 4DRQCh. 10 - Prob. 5DRQCh. 10 - Prob. 6DRQ
Ch. 10 - Prob. 7DRQCh. 10 - Prob. 8DRQCh. 10 - Prob. 9DRQCh. 10 - Prob. 10DRQCh. 10 - Prob. 11DRQCh. 10 - Prob. 12DRQCh. 10 - Prob. 13DRQCh. 10 - Prob. 14DRQCh. 10 - Prob. 15DRQCh. 10 - Prob. 16DRQCh. 10 - Prob. 1TSCh. 10 - Prob. 2TSCh. 10 - Prob. 3TSCh. 10 - Prob. 1CTECh. 10 - Prob. 2CTECh. 10 - Prob. 3CTECh. 10 - Prob. 4CTECh. 10 - Prob. 1PCh. 10 - Prob. 2PCh. 10 - Prob. 3PCh. 10 - Prob. 4PCh. 10 - Prob. 5PCh. 10 - Prob. 6PCh. 10 - Prob. 7PCh. 10 - Prob. 8PCh. 10 - Prob. 9PCh. 10 - Prob. 10PCh. 10 - Prob. 11PCh. 10 - Prob. 12PCh. 10 - Prob. 13PCh. 10 - Prob. 14PCh. 10 - Prob. 15PCh. 10 - Prob. 16PCh. 10 - Prob. 17PCh. 10 - A production process consists of a three-step...Ch. 10 - Prob. 19PCh. 10 - Prob. 20PCh. 10 - Prob. 21PCh. 10 - Prob. 22PCh. 10 - Prob. 23PCh. 10 - Prob. 24PCh. 10 - Prob. 25PCh. 10 - Prob. 26PCh. 10 - Prob. 27PCh. 10 - Prob. 28PCh. 10 - Prob. 29PCh. 10 - Prob. 1.1CQCh. 10 - Prob. 2.1CQCh. 10 - Prob. 2.2CQCh. 10 - Prob. 2.3CQCh. 10 - Prob. 2.4CQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A Quality Analyst wants to construct a control chart for determining whether three machines, all producing the same product, are under control with regard to a particular quality variable. Accordingly, he sampled four units of output from each machine, with the following results: For upper and lower control limits of 23.29 and 16.71, which machine(s), if any, appear(s) to have an out-of-control process mean?arrow_forward10. To monitor the quality of pepperoni pizzas, a quality control manager collects random samples of pizzas and evaluates them. The process mean and standard deviation for the weight and diameter of pizzas are not known. Which of the following(s) is a correct matching between the type of data collected and the choice of control chart used? Select all correct matchings. Select one: a. The manager weighed the sampled pizzas and constructed a c-chart. b. The manager rated the appearance of sampled pizzas as acceptable or unacceptable and then constructed a c-chart. c. The manager counted the number of pepperonis per each inspected pizza and constructed a mean chart. d. The manager measured the diameter of the sampled pizzas and constructed a range chart.arrow_forwardMcDaniel Shipyards wants to develop control charts to assess the quality of its steel plate. They take ten sheets of 1" steel plate and compute the number of cosmetic flaws on each roll. Each sheet is 20' by 100'. Based on the following data, develop limits for the control chart, plot the control chart, and determine whether the process is in control. Sheet Number of flaws 1 1 2 1 3 2 4 0 5 1 6 5 7 0 8 2 9 0 10 2arrow_forward
- An automatic filling machine is used to fill 1-liter bottles of cola. The machine’s output is approximately normal with a mean of 1.0 liter and a standard deviation of .01 liter. Output is monitoredusing means of samples of 25 observations.a. Determine upper and lower control limits that will include roughly 97 percent of the samplemeans when the process is in control.arrow_forwardA process considered to be in control measures an ingredient in ounces. A quality inspector took 10 samples, each with 5 observations as follows: Using this information, obtain three-sigma (i.e., z=3) control limits for a mean control chart and control limits for a range chart, respectively. It is known from previous experience that the standard deviation of the process is 1.36. Discuss whether the process is in control or not.arrow_forwardThe Watson Electric Company produces incandescent light bulbs. The following data on the number of lumens for 40-watt light bulbs were collected when the process was in control. The standard deviation of the process is 15. Calculate control limits for an x-bar chart with 3-sigma limit and draw the chart. Since these data were collected, some new employees were hired. A new sample obtained the following readings: 625, 592, 612, and 650. Is the process still in control?arrow_forward
- A process considered to be in control measures an ingredient in ounces. Roberto Baggio, a quality inspector took 20 samples, each with 8 observations as follows: thats in the pictuer after that using this information, obtain three-sigma (i.e., z=3) control limits for a mean control chart and control limits for a range chart, respectively. It is known from previous experience that the standard deviation of the process is 0.693. First: perform all actions and calculations needed to answer the question. All equations/calculations needed to be fully written STEP by STEP. No short calculations or direct answers/results will be accepted. This applies to the calculations for both types of control limits (mean and range). Second: Explain the process followed to identify each type of control limit and any observations made in the problem-solving process. thank you very mucharrow_forwardA quality inspector took five samples in five hours, each with four observations, of the length time for glue to dry. The analyst compute the mean of each sample and the computed the grand mean. All values are in minutes. Use this information to obtain three-sigma control limits for means. It is known from previous experience that the standard deviation of the process is 0.02 minutes. Draw a control chart Please provide a step-by-step solutionarrow_forwardWhy are most processes not in statistical control when they are first sampled for control chart purposes? *250 words minimum. Thank you!arrow_forward
- What is it important to prove that a process is proven capable before developing statistical control limit ?arrow_forwardAn automatic filling machine is used to fill 1-liter bottles of cola. The machine’s output is approximately normal with a mean of 1.0 liter and a standard deviation of .01 liter. Output is monitoredusing means of samples of 25 observations.a. Determine upper and lower control limits that will include roughly 97 percent of the samplemeans when the process is in control.b. Given these sample means: 1.005, 1.001, .998, 1.002, .995, and .999, is the process in control?arrow_forwardA Quality Analyst wants to construct a control chart for determining whether three machines, all producing the same product, are under control with regard to a particular quality variable. Accordingly, he sampled four units of output from each machine, with the following results : Machine #1 measurements [14, 13, 24, 22]; Machine #2 measurements [ 14, 19, 23, 14]; Machine #3 measurements [ 14, 16, 13, 16]. Using the factors for three sigma control limits, what are x-bar chart upper and lower control limits? a. 24.65and 9.013 b. 22.43and 11.24 c. 18.9and 14.76 d. 39.83and -6.167arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.