Question
Chapter 10, Problem 4P
Summary Introduction
To determine: The upper and lower control limits and decide if the process is in control.
Introduction:
Control chart:
It is a graph used to analyze the process change over a time period. A control chart has a upper control limit, and lower control which are used plot the time order.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
The results of a time study to perform a qualitycontrol test are shown in the following table. On the basis ofthese observations, determine the normal and standard timefor the test, assuming a 23% allowance factor
the solutions for the right side of the chart are incorrect. and I submitted three more parts of the same question.
You pull 5 bags of chips off of the production line every hour. The process is currently under control.
The average weights are calculated for each sample, and the average of those averages is 129.1.
The ranges are calculated for each sample, and the average of those ranges is 4.1.
What is the Upper Control Limit for the X-bar chart? Round your answer to one decimal place.
Chapter 10 Solutions
OPERATIONS MANAGEMENT W/ CNCT+
Ch. 10.2 - A potato chip is a delicate thing Fragile A pound...Ch. 10.2 - A potato chip is a delicate thing Fragile A pound...Ch. 10.5 - It's estimated that more than 7 000 hospital...Ch. 10.5 - It's estimated that more than 7 000 hospital...Ch. 10 - Prob. 1DRQCh. 10 - Prob. 2DRQCh. 10 - Prob. 3DRQCh. 10 - Prob. 4DRQCh. 10 - Prob. 5DRQCh. 10 - Prob. 6DRQ
Ch. 10 - Prob. 7DRQCh. 10 - Prob. 8DRQCh. 10 - Prob. 9DRQCh. 10 - Prob. 10DRQCh. 10 - Prob. 11DRQCh. 10 - Prob. 12DRQCh. 10 - Prob. 13DRQCh. 10 - Prob. 14DRQCh. 10 - Prob. 15DRQCh. 10 - Prob. 16DRQCh. 10 - Prob. 1TSCh. 10 - Prob. 2TSCh. 10 - Prob. 3TSCh. 10 - Prob. 1CTECh. 10 - Prob. 2CTECh. 10 - Prob. 3CTECh. 10 - Prob. 4CTECh. 10 - Prob. 1PCh. 10 - Prob. 2PCh. 10 - Prob. 3PCh. 10 - Prob. 4PCh. 10 - Prob. 5PCh. 10 - Prob. 6PCh. 10 - Prob. 7PCh. 10 - Prob. 8PCh. 10 - Prob. 9PCh. 10 - Prob. 10PCh. 10 - Prob. 11PCh. 10 - Prob. 12PCh. 10 - Prob. 13PCh. 10 - Prob. 14PCh. 10 - Prob. 15PCh. 10 - Prob. 16PCh. 10 - Prob. 17PCh. 10 - A production process consists of a three-step...Ch. 10 - Prob. 19PCh. 10 - Prob. 20PCh. 10 - Prob. 21PCh. 10 - Prob. 22PCh. 10 - Prob. 23PCh. 10 - Prob. 24PCh. 10 - Prob. 25PCh. 10 - Prob. 26PCh. 10 - Prob. 27PCh. 10 - Prob. 28PCh. 10 - Prob. 29PCh. 10 - Prob. 1.1CQCh. 10 - Prob. 2.1CQCh. 10 - Prob. 2.2CQCh. 10 - Prob. 2.3CQCh. 10 - Prob. 2.4CQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Which tool is very useful in documenting and presenting the whole process Select one a control chart b. check sheet O c flow chart O d. Pareto chart e histogramarrow_forwardWhat is it important to prove that a process is proven capable before developing statistical control limit ?arrow_forwardThe Dog Food Cereal Company fills boxes to an average weight of 30 lbs and an average range of 2 lbs. A sample size of 20 was used to assess the process. 1. What is the LCL for the R Chart? Group of answer choices -0.003 Zero 0.446 0.828 2. What is the UCL for the R Chart? Group of answer choices Rounds down to 2 2.9 Rounds down to 3.17 5 3. What is the UCL for the x bar chart? Group of answer choices The answer rounds down to 29.5 The answer rounds up to 31.5 The answer rounds up to 30.4 33.17arrow_forward
- x and R Control Charts A cereal manufacturer fills cereal boxes to an averageweight of 20 ounces and has an average range of 2 ounces when the filling process is in control. A sample size of 10 boxes is used in evaluating the process.a. What are the CL, UCL, and LCL for the x and R charts?b. A sample with the following 10 measurements was just taken: 20, 21, 19, 18, 19, 21,22, 20, 20, 19. Is the process still in control?arrow_forwardCheckout time at a supermarket is monitored using a mean and a range chart. Six samples of n = 20 observations have been obtained and the sample means and ranges computed: Sample Mean Range 1 3.06 .42 2 3.15 .50 3 3.11 .41 4 3.13 .46 5 3.06 .46 6 3.09 .45 Using the factors in Table 10.3 , determine upper and lower limits for mean and range charts. Is the process in control?arrow_forwardCheckout time at a supermarket is monitored using a mean and a range chart. Six samples of n = 20 observations have been obtained and the sample means and ranges computed: Sample Mean Range Sample Mean Range 1 3.06 .42 4 3.13 .46 2 3.15 .50 5 3.06 .46 3 3.11 .41 6 3.09 .45 a. Using the factors in Table 10.3 , determine upper and lower limits for mean and range charts. b. Is the process in control?arrow_forward
- Quality Engineering question What is Statistical Process Control? With what purpose is it used for? Please explain breifly with an example. Please answer in your own words.arrow_forwardBuilder UB, situated in Toronto, specialises in home and land packages throughout the North and South Islands. The team in charge of construction inspection examined a sample of newly constructed homes for flaws and leaks. Ten samples were examined for flaws or compliance issues. Each sample had a 50-unit size. The outcomes are listed below. Please offer your thoughts on C and P charts for process control.arrow_forwardA hospital is using X bar and R charts to record the time it takes to process patient account information. A sample of five applications is taken each day. The first four week's (20 days) data give the following values: X=16 min R= 7 min The upper and lower specifications are 21 minutes and 13 minutes respectively. What is the CPK of this process?arrow_forward
- For question 1 choose from the following: x bar-chart, c-chart, p-chart, or none of the about. 1. The process involving filling of a high value medicine into standard containers of 50 gms. 2. From a perspective of Statistical Process Control (SPC), a six-sigma process will have which of the following attributes? a) The USL and LSL will be separated by a distance of six sigma b) The process center will be aligned with the LSL c) The number of defects produced by the process will be 0.0018 parts per million d) All of the above 3. Which of the following statements depict the meaning of "total" in the term TQM? a) The total of all efforts put by the employees towards quality b) Total satisfaction of the customers about a company's products and services c) Ensuring every supplier follows quality practices in their work place d) Making quality happen everywhere in an organization by involving everyonearrow_forwardSan Angelo Manufacturing Company was concerned about a growing number of defective units being produced. At one time, the company had the percentage of defective units down to less than five per thousand, but recently rates of defects have been near, or even above, 1%. The company decided to graph its defects for the last 8 weeks (40 working days), beginning Monday, September 1 through Friday, October 24. The graph is as attached Identify two important trends evident in the quality-control chart. What might management of San Angelo do to deal with each trend?arrow_forwardDaily samples of I 00 power drills are removed fromthe assembly line at Drills by Stergios Fotopoulos and inspectedfor defects. Over the past 21 days, the following information hasbeen gathered. Develop a 3 standard deviation (99.73% confidence)p-chart and graph the samples. Is the process in control?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.