OPERATIONS MANAGEMENT W/ CNCT+
12th Edition
ISBN: 9781259574931
Author: Stevenson
Publisher: MCG CUSTOM
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 11, Problem 20P
Update the master
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
Prepare a master schedule given this information: It is now the end of week 1; customer orders are 25 for week 2, 16 for week 3, 11 for week 4, 8 for week 5, and 3 for week 6. Use the MPS rule of ordering production when projected on-hand inventory would be negative without production. Suppose that there were 64 pumps in inventory at the beginning of week 1. A production lot size of 70 pumps is used. (Leave no cells blank - be certain to enter "0" wherever required.)
Assume you are the manager of Assembly, Inc. You have just received an order for 27 units of an industrial robot, which is to be delivered at the start of week 7 of your schedule. Using the following information, determine how many units of subassembly G to order and the timing of those orders, given that subassembly G must be ordered in multiples of 80 units and all other components are ordered lot-for-lot. Assume that the components are used only for this particular robot.
Assume that you are the manager of Assembly, Inc. You have just received an order for 25 units of an industrial robot, which is to be delivered at the start of week 7 of your schedule. Using the following information, determine how many units of subassembly G to order and the timing of those orders, given that subassembly G must be ordered in multiples of 80 units and all other components are ordered lot-for-lot. Assume that the components are used only for this particular robot.
Item
Lead Time (weeks)
On Hand
Components
Robot
2
10
B, G, C(3)
B
1
5
E, F
C
1
20
G(2), H
E
2
4
—
F
3
8
—
G
2
15
—
H
1
10
—
Subassembly G order quantity (in units)
Subassembly G should start at beginning of Week
(Click to select) 1 2 3 4
Chapter 11 Solutions
OPERATIONS MANAGEMENT W/ CNCT+
Ch. 11 - What three levels of planning involve operations...Ch. 11 - What are the three phases of intermediate...Ch. 11 - Prob. 3DRQCh. 11 - Why is there a need for aggregate planning?Ch. 11 - What are the most common decision variables for...Ch. 11 - Prob. 6DRQCh. 11 - Briefly discuss the advantages and disadvantages...Ch. 11 - What are the primary advantages and limitations of...Ch. 11 - Briefly describe the planning techniques listed as...Ch. 11 - What are the inputs to master scheduling? What are...
Ch. 11 - Prob. 11DRQCh. 11 - What general trade-offs are involved in master...Ch. 11 - Who needs to interface with the master schedule...Ch. 11 - How has technology had an impact on master...Ch. 11 - Service operations often face more difficulty in...Ch. 11 - Name several behaviors related to aggregate...Ch. 11 - Compute the total cost for each aggregate plan...Ch. 11 - A manager would like to know the total cost of a...Ch. 11 - Determine the total cost for this plan given the...Ch. 11 - a. Given the following forecast and steady regular...Ch. 11 - Manager T. C. Downs of Plum Engines, a producer of...Ch. 11 - Manager Chris Channing of Fabric Mills, Inc., has...Ch. 11 - SummerFun. Inc., produces a variety of recreation...Ch. 11 - Nowjuice, Inc., produces Shakewell fruit juice. A...Ch. 11 - Wormwood, Ltd., produces a variety of furniture...Ch. 11 - Refer to Solved Problem 1. Prepare two additional...Ch. 11 - Refer to Solved Problem 1. Suppose another option...Ch. 11 - Prob. 12PCh. 11 - Prob. 13PCh. 11 - Prob. 14PCh. 11 - Prob. 15PCh. 11 - Refer to Example 3. Suppose that regular-time...Ch. 11 - Prob. 17PCh. 11 - Prob. 18PCh. 11 - Prepare a master production schedule for...Ch. 11 - Update the master schedule shown in Figure 11.11...Ch. 11 - Prepare a master schedule like that shown in...Ch. 11 - Determine the available-to-promise (ATP)...Ch. 11 - Prepare a schedule like that shown in Figure 11.12...Ch. 11 - The objective is to choose the plan that has the...Ch. 11 - Prob. 2CQ
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Assume that you are the manager of Assembly, Inc. You have just received an order for 26 units of an industrial robot, which is to be delivered at the start of week 7 of your schedule. Using the following information, determine how many units of subassembly G to order and the timing of those orders, given that subassembly G must be ordered in multiples of 80 units and all other components are ordered lot-for-lot. Assume that the components are used only for this particular robot. Item Lead Time (weeks) On Hand Components Robot 2 10 B, G, C(3) B 1 5 E, F C 1 20 G(2), H E 2 4 — F 3 8 — G 2 15 — H 1 10 — Subassembly G order quantity (in units) Subassembly G should start at beginning of Weekarrow_forwardWhat precisely is the key distinction between planning for the long term and planning for the short term when it comes to process scheduling?arrow_forwardEighty units of end item E are needed at the beginning of week 6. Three cases (30 units per case) of Jhave been ordered and one case is scheduled to arrive in week 3, one in week 4, and one in week 5.Note: J must be ordered by the case, and B must be produced in multiples of 120 units. There are 60 unitsof B and 20 units of J now on hand. Lead times are two weeks each for E and B, and one week for J.E a. Prepare a material requirements plan for component J.b. Suppose that in week 4 the quantity of E needed is changed from 80 to 70. The planned-order releasesthrough week 3 have all been executed. How many more Bs and Js will be on hand in week 6?arrow_forward
- Prepare a Master Schedule like that shown in Figure 11.11 given the following information:The forecast for each week of an eight-week schedule is 50 units. The MPS tule is to schedule production if the projected on-hand inventory would be negative without it. Customer orders (committed) are as follows:Week 1.2.3.4Customer Orders 52.35.20.12Use a production lot size of 75 units and no beginning inventory.arrow_forwardExplain what is the purpose of the Gantt chart as a scheduling tools and discuss when do they use a Gantt chart instead of a network based method?arrow_forwardWhy is it important to integrate cost and schedule controls? Give an example for which separate cost and schedule control systems may not function properly.arrow_forward
- describe what is the purpose of the Gantt chart as a scheduling tool and when do they using a Gantt chart instead of a network based method?arrow_forwardJob Costing Johnson Inc. is a job-order manufacturing company that uses a predetermined overhead ratebased on direct labor hours to apply overhead to individual jobs. For the current year, estimated direct laborhours are 95,000 and estimated factory overhead is $617,500. The following information is for Septemberof the current year. Job A was completed during September, and Job B was started but not finished.[LO 4-3, 4-4, 4-5]September 1, InventoriesMaterials Inventory $ 7,500Work-in-Process Inventory (All Job A) 31,200Finished Goods Inventory 67,000Material purchases 104,000Direct materials requisitionedJob A 65,000Job B 33,500Direct labor hoursJob A 4,200Job B 3,500Labor costs incurredDirect labor ($8.50/hour) 65,450Indirect labor 13,500Supervisory salaries 6,000Rental costsFactory 7,000Administrative offices 1,800Total equipment depreciation costsFactory 7,500Administrative offices 1,600Indirect materials used 12,000Required1. What is the total cost of Job A?2. What is the total…arrow_forwardWhat is the use of Total float(TF), Free Float(FF), Independent float(IF) in scheduling. How it affects project.arrow_forward
- Prepare a Master Production Schedule (MPS) for an Agri-Chemical company given the following information: The forecast for each week of an eightweek schedule is 50 units. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Customer orders (committed) are as follows:Week Customer Orders1 522 353 204 12Use a production lot size of 75 units and no beginning inventory.arrow_forwardConsider the master flight schedule of a major airline, such as Air New Zealand. Discuss the ways in which it is analogous to an MPS for a manufacturer.arrow_forwardExplain the physical and practical meaning of slack and surplus variables with an examplearrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY