To determine
Lead Time: Lead time is the time consumed for the creation of a product. It refers to the time period between the time the order is placed and the product is completed. Lesser lead time creates a more competitive edge for the company.
Lead Time = Wait time + Process time + Queue time + Move time + Inspection Time
If the Company P is correct in calculating the lead time.
To determine
The lead time for each product.
Expert Solution & Answer
![Check Mark](/static/check-mark.png)
Want to see the full answer?
Check out a sample textbook solution![Blurred answer](/static/blurred-answer.jpg)
Students have asked these similar questions
Desayuno Products, Inc., produces cornflakes and branflakes. The manufacturing process is highly mechanized; both products are produced by the same machinery by using different settings. For the coming period, 200,000 machine hours are available. Management is trying to decide on the quantities of each product to produce. The following data are available:
Cornflakes Branflakes
Machine hours per unit 1.00 0.50
Unit Selling Price $2.50 $3.00
Unit Variable Cost $1.50 $2.25
Determine the units of each product that should be produced in order to…
Lead Time Analysis
Furry Friends Inc. manufactures toy stuffed animals. The direct labor time required to cut, sew, and stuff a toy is 10 minutes per unit. The company makes two types of stuffed toys—a lion and a bear. The lion is assembled in lot sizes of 50 units per batch, while the bear is assembled in lot sizes of 8 units per batch. Since each product has direct labor time of 10 minutes per unit, management has determined that the lead time for each product is 10 minutes.
a. Lead time includes ___, ___, and ___.
Value-added time, wait time and other non-value-added time.
Production time, packing time and value-added time.
Idle time, direct labor hours, and wait time.
None of the above.
b. A toy manufacturing unit produces two types of products and the labor time for the each product is 10 minutes. The batch size of product A is 50 units and batch size of product B is 8 units. The company considers the lead time of the products is equal to the labor hour’s. Is the decision…
Compute Lead Time
Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 50 parts. A part requires 5 minutes in milling and 10 minutes in finishing. The move time between the two operations for a complete batch is 11 minutes.
Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 6 parts and the move time is eliminated.
Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methods. If required, round percentages to one decimal place.
Traditional Philosophy
Lean Manufacturing Philosophy
Value-added time
?
min
?
min
Non-value-added time
?
min
?
min
Total lead time
?
min
?
min
Value-added ratio…
Chapter 12 Solutions
Managerial Accounting
Ch. 12 - What is the benefit of the lean philosophy?Ch. 12 - Prob. 2DQCh. 12 - Prob. 3DQCh. 12 - Prob. 4DQCh. 12 - Prob. 5DQCh. 12 - Why would a lean manufacturer strive to produce...Ch. 12 - Prob. 7DQCh. 12 - Prob. 8DQCh. 12 - Prob. 9DQCh. 12 - Prob. 10DQ
Ch. 12 - Prob. 11DQCh. 12 - Prob. 12DQCh. 12 - Prob. 13DQCh. 12 - Prob. 1BECh. 12 - Prob. 2BECh. 12 - Prob. 3BECh. 12 - Prob. 4BECh. 12 - Prob. 5BECh. 12 - Prob. 1ECh. 12 - Prob. 2ECh. 12 - Prob. 3ECh. 12 - Prob. 4ECh. 12 - Prob. 5ECh. 12 - Prob. 6ECh. 12 - Calculate lead time Williams Optical Inc. is...Ch. 12 - Prob. 8ECh. 12 - Prob. 9ECh. 12 - Prob. 10ECh. 12 - Prob. 11ECh. 12 - Prob. 12ECh. 12 - Lean accounting Modern Lighting Inc. manufactures...Ch. 12 - Prob. 14ECh. 12 - Prob. 15ECh. 12 - Prob. 16ECh. 12 - Prob. 17ECh. 12 - Prob. 18ECh. 12 - Process activity analysis The Brite Beverage...Ch. 12 - Prob. 20ECh. 12 - Prob. 21ECh. 12 - Prob. 1PACh. 12 - Prob. 2PACh. 12 - Lean accounting Dashboard Inc. manufactures and...Ch. 12 - Prob. 4PACh. 12 - Prob. 1PBCh. 12 - Lead time Master Chef Appliance Company...Ch. 12 - Lean accounting Com-Tel Inc. manufactures and...Ch. 12 - Pareto chart and cost of quality report for a...Ch. 12 - Prob. 1ADMCh. 12 - Prob. 2ADMCh. 12 - Prob. 3ADMCh. 12 - Ethics in Action In August, Lannister Company...Ch. 12 - Prob. 3TIF
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Vollmer Manufacturing makes three components for sale to refrigeration companies. The components are processed on two machines: a shaper and a grinder. The times (in minutes) required on each machine are as follows: The shaper is available for 120 hours, and the grinder for 110 hours. No more than 200 units of component 3 can be sold, but up to 1,000 units of each of the other components can be sold. In fact, the company already has orders for 600 units of component 1 that must be satisfied. The profit contributions for components 1, 2, and 3 are 8, 6, and 9, respectively. a. Formulate and solve for the recommended production quantities. b. What are the objective coefficient ranges for the three components? Interpret these ranges for company management. c. What are the right-hand-side ranges? Interpret these ranges for company management. d. If more time could be made available on the grinder, how much would it be worth? e. If more units of component 3 can be sold by reducing the sales price by 4, should the company reduce the price?arrow_forwardCarltons Kitchens makes two types of pasta makers: Strands and Shapes. The company expects to manufacture 70,000 units of Strands, which has a per-unit direct material cost of $10 and a per-unit direct labor cost of $60. It also expects to manufacture 30.000 units of Shapes, which has a per-unit material cost of $15 and a per-unit direct labor cost of $40. It is estimated that Strands will use 140,000 machine hours and Shapes will require 60,000 machine hours. Historically, the company has used the traditional allocation method and applied overhead at a rate of $21 per machine hour. It was determined that there were three cost pools, and the overhead for each cost pool is shown: The cost driver for each cost pool and its expected activity is shown: A. What is the per-unit cost for each product under the traditional allocation method? B. What is the per-unit cost for each product under ABC costing?arrow_forwardBox Springs. Inc., makes two sizes of box springs: queen and king. The direct material for the queen is $35 per unit and $55 is used in direct labor, while the direct material for the king is $55 per unit, and the labor cost is $70 per unit. Box Springs estimates it will make 4,300 queens and 3,000 kings in the next year. It estimates the overhead for each cost pool and cost driver activities as follows: How much does each unit cost to manufacture?arrow_forward
- Box Springs, Inc., makes two sizes of box springs: twin and double. The direct material for the twin is $25 per unit and $40 s used in direct labor, while the direct material for the double is $40 per unit, and the labor cost is $50 per unit. Box Springs estimates it will make 5,000 twins and 9,000 doubles in the next year. It estimates the overhead for each cost pool and cost driver activities as follows: How much does each unit cost to manufacture?arrow_forwardCarsen Company produces handcrafted pottery that uses two inputs: materials and labor. During the past quarter, 24,000 units were produced, requiring 96,000 pounds of materials and 48,000 hours of labor. An engineering efficiency study commissioned by the local university revealed that Carsen can produce the same 24,000 units of output using either of the following two combinations of inputs: The cost of materials is 8 per pound; the cost of labor is 12 per hour. Required: 1. Compute the output-input ratio for each input of Combination F1. Does this represent a productivity improvement over the current use of inputs? What is the total dollar value of the improvement? Classify this as a technical or an allocative efficiency improvement. 2. Compute the output-input ratio for each input of Combination F2. Does this represent a productivity improvement over the current use of inputs? Now, compare these ratios to those of Combination F1. What has happened? 3. Compute the cost of producing 24,000 units of output using Combination F1. Compare this cost to the cost using Combination F2. Does moving from Combination F1 to Combination F2 represent a productivity improvement? Explain.arrow_forwardPower Corp. makes 2 products: blades for table saws and blades for handsaws. Each product passes through the sharpening machine area, which is the chief constraint during production. Handsaw blades take 15 minutes on the sharpening machine and have a contribution margin per blade of $15. Table saw blades take 20 minutes on the sharpening machine and have a contribution margin per blade of $35. If it is assumed that Power Corp. has 5,000 hours available on the sharpening machine to service a minimum demand for each product of 4,000 units, how much will profits increase if 200 more hours of machine time can be obtained?arrow_forward
- Power Corp. makes 2 products: blades for table saws and blades for handsaws. Each product passes through the sharpening machine area, which is the chief constraint during production. Handsaw blades take 15 minutes on the sharpening machine and have a contribution margin per blade of $15. Table saw blades take 20 minutes on the sharpening machine and have a contribution margin per blade of $35. If it is assumed that Power Corp. has 5,000 hours available on the sharpening machine to service a minimum demand for each product of 4,000 units, how many of each product should be made?arrow_forwardCLEAR MY CHOICE XYZ Co. manufactures baseball bats and wooden tops. Currently, the company makes 5,000 baseball bats each month. Each bat uses $1.00 in direct materials and $0.50 in direct labor. The company uses two activities in manufacturing the baseball bats: Cutting and Finishing. The cost associated with Cutting is $7,500 a month, allocated on the basis of direct labor hours. The cost associated with Finishing is $12,000 a month, allocated on the basis of batches. Baseball bats use 1/3 of the direct labor hours, and 40% of total batches. What is the total manufacturing cost for one baseball bat? O a. $3.5 O b. $3.46 O c. None of the given answer is correct. O d. $3 O e. $2.96 NEXT PAGE PAGE TOSHIBAarrow_forwardIsaacson Dental Inc. is considering a new lean product cell. The present manufacturing approach produces a product in four separate steps. The production batch sizes are 50 units. The process time for each step is as follows: Line Item Description Time Process Step 1 6 minutes Process Step 2 12 minutes Process Step 3 9 minutes Process Step 4 3 minutes The time required to move each batch between steps is 6 minutes. In addition, the time to move raw materials to Process Step 1 is also 6 minutes, and the time to move completed units from Process Step 4 to finished goods inventory is 6 minutes. The new lean layout will allow the company to reduce the batch sizes from 50 units to 2 units. The time required to move each batch between steps and the inventory locations will be reduced to 1 minute. The processing time in each step will stay the same. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the (a) present and (b)…arrow_forward
- Using the following information for question 8-10 Honeydew Company produces two products, a high-end laptop computer under the label Bunsen Laptops, and an inexpensive desktop computer under the label Beaker Computers. The two products use two overhead activities, with the following costs: Setting up equipment Machining $2,000 12,000 The controller has collected the expected annual prime costs for each product, the machine the setup hours, and the expected production. Bunsen Beaker Direct Labor Direct Materials Expected Production in Units Machine hours $20,000 $5,000 15,000 4,000 2,000 2,000 750 1,500 Setup hours 50 50 8. Calculate Beaker's consumption ratio for setup hours. a. 0.50 b. 0.45 c. 0.90 d. 0.25arrow_forwardCompute Lead Time Jackson Fabricators Inc. machines metal parts for the automotive industry. Under the traditional manufacturing approach, the parts are machined through two processes: milling and finishing. Parts are produced in batch sizes of 70 parts. A part requires 4 minutes in milling and 9 minutes in finishing. The move time between the two operations for a complete batch is 10 minutes. Under the lean philosophy, the part is produced in a cell that includes both the milling and finishing operations. The operating time is unchanged; however, the batch size is reduced to 4 parts and the move time is eliminated. Determine the value-added, non-value-added, and total lead times, and the value-added ratio under the traditional and lean manufacturing methods. If required, round percentages to one decimal place. Value-added time Non-value-added time Total lead time Value-added ratio (as a percent) Traditional Philosophy Lean Manufacturing Philosophy min min min % min min min %arrow_forwardUsing the following information for question 8-10 Honeydew Company produces two products, a high-end laptop computer under the label Bunsen Laptops, and an inexpensive desktop computer under the label Beaker Computers. The two products use two overhead activities, with the following costs: Setting up equipment Machining $2,000 12,000 The controller has collected the expected annual prime costs for each product, the machine hours, the setup hours, and the expected production. Direct Labor Direct Materials Expected Production in Units Machine hours Setup hours 8. Calculate Beaker's consumption ratio for setup hours. a. 0.50 b. 0.45 c. 0.90 d. 0.25 Bunsen Beaker $20,000 $5,000 15,000 4,000 2,000 2,000 750 1,500 50 50arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax CollegeEssentials of Business Analytics (MindTap Course ...StatisticsISBN:9781305627734Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. AndersonPublisher:Cengage Learning
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337912020/9781337912020_smallCoverImage.jpg)
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
![Text book image](https://www.bartleby.com/isbn_cover_images/9781305627734/9781305627734_smallCoverImage.gif)
Essentials of Business Analytics (MindTap Course ...
Statistics
ISBN:9781305627734
Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781305970663/9781305970663_smallCoverImage.gif)
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
alue Chain Analysis EXPLAINED | B2U | Business To You; Author: Business To You;https://www.youtube.com/watch?v=SI5lYaZaUlg;License: Standard Youtube License