a)

To determine

Lead Time: Lead time is the time consumed for the creation of a product. It refers to the time period between the time the order is placed and the product is completed. Lesser lead time creates a more competitive edge for the company.

Lead Time = Wait time + Process time + Queue time + Move time + Inspection Time

To Compute: The value added, non value added and lead time of this process.

b)

To determine

To Compute: The value added ratio (rounded to one place).

Blurred answer
Students have asked these similar questions
Lead Time Pockets Inc. manufactures cargo pants in the cutting and sewing process. Cargo pants are manufactured in batches of 30. The cutting time is 4 minutes per unit. The sewing time is 12 minutes per unit. It takes 20 minutes to move a batch of jeans from cutting to sewing. a. Compute the value-added, non-value-added, and total lead time of this process. Value-added lead time Non-value-added lead time Total lead time b. Compute the value-added ratio. Round to one decimal place. % minutes minutes minutes
Pockets Inc. manufactures cargo pants in the cutting and sewing process. Cargo pants are manufactured in batches of 30. The cutting time is 4 minutes per unit. The sewing time is 12 minutes per unit. It takes 20 minutes to move a batch of jeans from cutting to sewing. a.  Compute the value-added, non-value-added, and total lead time of this process. Line Item Description Lead Time Value-added lead time fill in the blank 1 minutes Non-value-added lead time fill in the blank 2 minutes Total lead time fill in the blank 3 minutes b.  Compute the value-added ratio. Round to one decimal place.fill in the blank 1 of 1%
8. Rough Riders Inc. manufactures jeans in the cutting and sewing process. Jeans are manufactured in 50-jean batch sizes. The cutting time is 6 minutes and the sewing time is 15 minutes per jean. It takes 5 minutes to move a batch of jeans from cutting to sewing.   (a) Compute the value-added, non-value-added, and total lead time of this process. (b) Compute the value-added ratio. Round to one decimal place.
Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Text book image
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
alue Chain Analysis EXPLAINED | B2U | Business To You; Author: Business To You;https://www.youtube.com/watch?v=SI5lYaZaUlg;License: Standard Youtube License