OPERATIONS MANAGEMENT(LL)-W/CONNECT >IC<
7th Edition
ISBN: 9781260839456
Author: SCHROEDER
Publisher: MCG CUSTOM
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 15, Problem 5P
The master
- a. What information would you need to decide whether you should make this change?
- b. Suppose that each widget takes one hour of press time and three hours of assembly time three weeks before delivery. Can the additional 100 widgets be made in view of the following shop loadings?
- a. If the additional widgets cannot be made in part b above, what actions might be taken to make it possible to produce the required widgets?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Assume that you are the manager of Assembly, Inc. You have just received an order for 25 units of an industrial robot, which is to be delivered at the start of week 7 of your schedule. Using the following information, determine how many units of subassembly G to order and the timing of those orders, given that subassembly G must be ordered in multiples of 80 units and all other components are ordered lot-for-lot. Assume that the components are used only for this particular robot.
Item
Lead Time (weeks)
On Hand
Components
Robot
2
10
B, G, C(3)
B
1
5
E, F
C
1
20
G(2), H
E
2
4
—
F
3
8
—
G
2
15
—
H
1
10
—
Subassembly G order quantity (in units)
Subassembly G should start at beginning of Week
(Click to select) 1 2 3 4
Assume that you are the manager of Assembly, Inc. You have just received an order for 26 units of an industrial robot, which is to be delivered at the start of week 7 of your schedule. Using the following information, determine how many units of subassembly G to order and the timing of those orders, given that subassembly G must be ordered in multiples of 80 units and all other components are ordered lot-for-lot. Assume that the components are used only for this particular robot.
Item
Lead Time (weeks)
On Hand
Components
Robot
2
10
B, G, C(3)
B
1
5
E, F
C
1
20
G(2), H
E
2
4
—
F
3
8
—
G
2
15
—
H
1
10
—
Subassembly G order quantity (in units)
Subassembly G should start at beginning of Week
Assume you are the manager of Assembly, Inc. You have just received an order for 27 units of an industrial robot, which is to be delivered at the start of week 7 of your schedule. Using the following information, determine how many units of subassembly G to order and the timing of those orders, given that subassembly G must be ordered in multiples of 80 units and all other components are ordered lot-for-lot. Assume that the components are used only for this particular robot.
Chapter 15 Solutions
OPERATIONS MANAGEMENT(LL)-W/CONNECT >IC<
Ch. 15.7 - Prob. 1OLCh. 15 - Prob. 1DQCh. 15 - Prob. 2DQCh. 15 - With regard to inventory management, discuss the...Ch. 15 - Prob. 4DQCh. 15 - How much safety stock should be carried in a MRP...Ch. 15 - Prob. 6DQCh. 15 - Prob. 7DQCh. 15 - Prob. 8DQCh. 15 - Prob. 9DQ
Ch. 15 - Describe how MRP? concepts could be used for the...Ch. 15 - How are MRP and ERP related?Ch. 15 - The following information is given for a...Ch. 15 - eXcel The Old Hickory Furniture Company...Ch. 15 - Product A consists of subassemblies B and C....Ch. 15 - eXcel The BOM for product A given below Part on...Ch. 15 - The master scheduler in the ABC Widget Company is...Ch. 15 - A firm makes a basic scissors consisting of three...Ch. 15 - Prob. 7PCh. 15 - Prob. 8PCh. 15 - A small toy robot is assembled from sis parts: a...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Prepare a master schedule given this information: It is now the end of week 1; customer orders are 25 for week 2, 16 for week 3, 11 for week 4, 8 for week 5, and 3 for week 6. Use the MPS rule of ordering production when projected on-hand inventory would be negative without production. Suppose that there were 64 pumps in inventory at the beginning of week 1. A production lot size of 70 pumps is used. (Leave no cells blank - be certain to enter "0" wherever required.)arrow_forwardAssume that you are the manager of Assembly, Inc. You have just received an order for 40 units ofan industrial robot, which is to be delivered at the start of week 7 of your schedule. Using the following information, determine how many units of subassembly G to order and the timing of thoseorders, given that subassembly G must be ordered in multiples of 80 units and all other componentsare ordered lot-for-lot. Assume that the components are used only for this particular robot.Item Lead Time (weeks) On Hand ComponentsRobot 2 10 B, G, C(3)B 1 5 E, FC 1 20 G(2), HE 2 4 —F 3 8 —G 2 15 —H 1 10 —arrow_forwardEach unit of A is composed of one unit of B, two units of C, and one unit of D. C is composed of two units of D and three units of E. Items A, C, D, and E have on-hand inventories of 20, 10, 20, and 15 units, respectively. Item B has a scheduled receipt of 10 units in Period 1, and C has a scheduled receipt of 50 units in Period 1. Lot-for-lot (L4L) is used for Items A and B. Item C requires a minimum lot size of 50 units. D and E are required to be purchased in multiples of 95 and 55, respectively. Lead times are one period for Items A, B, and C, and two periods for Items D and E. The gross requirements for A are 30 in Period 2, 30 in Period 5, and 40 in Period 8.arrow_forward
- Each unit of A is composed of one unit of B, two units of C, and one unit of D. C is composed of two units of D and three units of E. Items A, C, D, and E have on-hand inventories of 20, 10, 20, and 10 units, respectively. Item B has a scheduled receipt of 10 units in Period 1, and C has a scheduled receipt of 50 units in Period 1. Lot-for-lot (L4L) lot sizing is used for Items A and B. Item C requires a minimum lot size of 50 units. D and E are required to be purchased in multiples of 100 and 50, respectively. Lead times are one period for Items A, B, and C, and two periods for Items D and E. The gross requirements for A are 30 in Period 2, 30 in Period 5, and 40 in Period 8. Find the planned-order releases for all itemsarrow_forwardecently, Phil Harris, the production control manager at Brunswick, read an article on time-phased requirements planning. He was curious about how this technique might work in scheduling Brunswick's engine assembly operations and decided to prepare an example to illustrate the use of time-phased requirements planning. Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown on the next page. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram below. Phil noted that the gear box is assembled by the Subassembly Department and subsequently is sent to the main engine…arrow_forwardMontague Composite makes a unit A, which consists of two units of B, three units of C, and four units of D. C is composed of three units of D and two units of E. Items A, C, D and E have on-hand inventories of 10, 20, 30 and 40 units respectively. Item B has a scheduled receipt of 50 units in period 1, and C has a scheduled receipt of 90 units in period 1. Lot-for-lot sizing is used for items A and B. Item C requires a minimum lot size of 60 units. D and E must be purchased in multiples of 35 and 55 respectively. Lead times are one period for items A, B and C, and two periods for items D and E. The gross requirements for A are 180 in period 5, and 220 in period 8. Determine the planned-order releases for all items using template 2 (provided at the end of the paper)arrow_forward
- Eighty units of end item E are needed at the beginning of week 6. Three cases (30 units per case) of Jhave been ordered and one case is scheduled to arrive in week 3, one in week 4, and one in week 5.Note: J must be ordered by the case, and B must be produced in multiples of 120 units. There are 60 unitsof B and 20 units of J now on hand. Lead times are two weeks each for E and B, and one week for J.E a. Prepare a material requirements plan for component J.b. Suppose that in week 4 the quantity of E needed is changed from 80 to 70. The planned-order releasesthrough week 3 have all been executed. How many more Bs and Js will be on hand in week 6?arrow_forwardMaster production schedule is a medium-range planning and it is used for quantity and timing of components and raw material Finished goods Both A & Barrow_forwardOne unit of A is made of three units of B, one unit of C, and two units of D. B is composedof two units of E and one unit of D. C is made of one unit of B and two units of E. E ismade of one unit of F.Items B, C, E, and F have one-week lead times; A and D have lead times oftwo weeks.Assume that lot-for-lot (L4L) lot sizing is used for Items A, B, and F; lots of size50, 50, and 200 are used for Items C, D, and E, respectively. Items C, E, and F have onhand(beginning) inventories of 10, 50, and 150, respectively; all other items have zerobeginning inventory. We are scheduled to receive 10 units of A in Week 2, 50 units of Ein Week 1, and also 50 units of F in Week 1. There are no other scheduled receipts. If30 units of A are required in Week 8, use the low-level-coded bill-of-materials to i nd thenecessary planned order releases for all components.arrow_forward
- Some of the units processed in a department are sold without further processing. Others are transferred to a second department for further processing. How will this reflect on the cost of production report? Reported on separate lines in Quantity Schedule and Cost Schedule Shown only in the Quantity Schedule Shown only in Cost Schedule Only the cost transferred to Finished Goods Inventory are reported in Cost Schedulearrow_forwardNow you are being hired as a scheduler in the manufacturing unit of surgical instruments. Your job is to schedule four jobs on the two machines. The job processing time in minutes for the four jobs is given below: A с D Machine 1 Machine 2 3.43 0.11 B 1.58 0.46 3.62 2.29 4.05 4.52 The optimal schedule using Johnson method and makespan for the jobs is: (A)BCBA, 12.79 minutes (B) ABCD, 5.41 minutes (C) DCBA, 12.79 minutes (D) CDBA, 5.41 minutesarrow_forwardWhat term is used to identify the difference between the number of units of an item listedon the master schedule and the number of i rm customer orders?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY