OPERATIONS MANAGEMENT(LL)-W/CONNECT >IC<
7th Edition
ISBN: 9781260839456
Author: SCHROEDER
Publisher: MCG CUSTOM
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 15, Problem 6P
A firm makes a basic scissors consisting of three parts: the left side, the right side, and the screw that holds the sides together. At the present time, the firm has the following numbers of parts on hand and on order. The lead times for reorder of each part are also shown along with a BOM and a sketch of the scissors.
0 | On Hand | Weeks of Lead Time | Scheduled Receipts |
Scissors | 100 | 1 | |
Left side | 50 | 2 | 100 in week 2 |
Right side | 75 | 2 | 200 in week 2 |
Screw | 300 | 1 | 200 in week 1 |
- a. Assume the master
schedule calls for 200 scissors to be shipped in week 4 and 500 in week 5: work out a complete materials plan. - b. Suppose the supplier of right-hand sides calls to say that deliveries of the 200 parts on order will be one week late. What effect will this have on the materials plan?
- c. If demand for scissors is uncertain and has a standard deviation of 50 units, what would you recommend the firm do to maintain a 95 percent service level for scissors?
- d. If the delivery of the scissors parts is unreliable and the standard deviation of delivery' lead time is one week for each of the parts, what would you recommend the firm do to maintain its production schedule?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A’s lead time is 1 week; B’s lead time is 2 weeks; and C’s lead time is 2 weeks. This is true regardless of order size. Currently you have the following amounts in on-hand inventory; A = 50. a) How many units of B and C will I need to produce for A if I have an order for 100 units of A? b) Give me a time-phased assembly plan for A, B, and C such that I will receive 100 units of A at the beginning of Week 5. Assume that I can work on B and C at the same time (overlap).
Jean-Ma rie Bourjolly's restau rant has the followinginventory items that it orders on a weekly basis: a) Which is the most expensive item, using annual dollar volume?b) Which are C items?c) What is the annual dollar volume for all 20 items?
i was reading this answer and the way its calculated is a longer process then what someone else wrote can you check if ishould use this one that bartleby has given me or the other one:
Step 1: Basic Information
The question is related to Economic order quantiy Economic Order Quantity is that level of inventory at which ordering cost and handling cost are minimum. It is calculated with the help of following formula
Economic Order Quantity = √2RO ÷ C
R = Annual Requirment
C = Carrying or Holding cost
O = Ordering Cost
Step 2: Solution
Economic Order Quantity = √2RO ÷ C
Economic Order Quantity = √2 × 3000 × 20 ÷ 4.25
Economic Order Quantity = √28,235.294117647
Economic Order Quantity = 168.0336100834 pounds
R = Annual Requirment i.e.250 × 12 = 3000 pounds per annum.
C = Carrying or Holding cost i.e. £4.25
O = Ordering Cost i.e. £20
Quantity to be ordered = 168.03 pounds.
Supplier = Vendor 1 should be used as the cost per pound for 168 pounds is £32.25 (as per table…
Chapter 15 Solutions
OPERATIONS MANAGEMENT(LL)-W/CONNECT >IC<
Ch. 15.7 - Prob. 1OLCh. 15 - Prob. 1DQCh. 15 - Prob. 2DQCh. 15 - With regard to inventory management, discuss the...Ch. 15 - Prob. 4DQCh. 15 - How much safety stock should be carried in a MRP...Ch. 15 - Prob. 6DQCh. 15 - Prob. 7DQCh. 15 - Prob. 8DQCh. 15 - Prob. 9DQ
Ch. 15 - Describe how MRP? concepts could be used for the...Ch. 15 - How are MRP and ERP related?Ch. 15 - The following information is given for a...Ch. 15 - eXcel The Old Hickory Furniture Company...Ch. 15 - Product A consists of subassemblies B and C....Ch. 15 - eXcel The BOM for product A given below Part on...Ch. 15 - The master scheduler in the ABC Widget Company is...Ch. 15 - A firm makes a basic scissors consisting of three...Ch. 15 - Prob. 7PCh. 15 - Prob. 8PCh. 15 - A small toy robot is assembled from sis parts: a...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- For Question 1 you are required to mannualy (without the use of excel) develop two MRP matrices: one with no lot sizing (you order what is required) and a lot seize equal to the EOQ. To determine the EOQ note that the inventory carrying cost is given as R1/unit/period. This means that you have to calculate the average demand per period and use this demand value in your EOQ calculation. This is then the order quantity to be used for the second MRP matrix.arrow_forwardComplete the master production schedule based on the following information On-hand Inventory - 160 schedule production whenever projected on-hand inventory drops below - 30 MPS lot size - 300 Week 1 2 3 4 5 6 7 8Forecast 120 100 130 110 140 140 170 180 Customer Orders 110 100 75 50 32 11 5 0Projected On-Hand Inventory 160MPSAvailable-to-Promisearrow_forwardState the types of data that would be carried in the bill-of-materials i le and the inventoryrecord file.arrow_forward
- Discuss the following statement: “Since we use a rolling production schedule, Ireally don’t need to know the demand beyond next month.”arrow_forwardA newly opened BackPack Company in Kitwe, produces a line of backpacks. The manager, Jill Bwalya, is interested in using a level aggregate plan. Inventories and back orders will be used to handle demand fluctuations. Given the following data below; Cost dataRegular-time labour cost per hour K10.00Overtime labour cost per hour K15.00Subcontracting cost per unit (labour only) K84.00Holding cost per unit per period K10.00Back-order cost per unit per period K20.00Hiring cost per employee K600.00Firing cost per employee K450.00Capacity dataBeginning workforce 210 employeesBeginning inventory 400 unitsLabour standard per unit 6 hoursRegular time available per period 160 hours Overtime available per period…arrow_forwardGiven the following data: Inventory Holding Cost is $10/unit/month on ending inventory levels. Beginning inventory of Month 1 is 100 units. Hiring (Firing) Cost is $100 ($200) per worker. Each worker produces 10 units per month. There are 20 work persons on the payroll at the end of month 0. Month 1 2 3 4 5 6 Demand 300 300 400 300 300 400 What is the total cost of a chase strategy production plan?arrow_forward
- The requirements of local motor bikes for a company are given as [25,5,25,30, 20] for week 1, 2, 3, 4 and 5 respectively. If the setup costs and holding costs assumed at $80 and $1 /unit/week respectively, find the lot sizing using both Silver Meal and LUC Heuristics.arrow_forwardItem X is a standard item stocked in a company’s inventory of spare parts. Each year, the firm uses about2,000 units of Item X, which costs Php 1,000 per unit. Storage costs, which include insurance and cost ofcapital, amount to 18 percent of item unit cost. Placing an order for more of Item X costs Php 400. Thecompany operates 360 days per year and Item X is received 9 days after placement of order. How many units of Item X should be ordered each time? A. 94 unitsB. 95 unitsC. 100 unitsD. 2,000 unitsarrow_forward2. RoadHog Inc. is a small manufacturer of motorcycle accessories. It makes muffler with fins on a linethat is also used to make a variety of other products. Because it is costly to set up the line to produce themin batches, RoadHog has an incentive them in batches. However, while customer demand is known over a6-planning horizon, it is not necessarily constant from week to week. The unit cost, fixed setup cost andmonthly holding cost are given in the table.Data for the RoadHog Dynamic Lot SizingWeek 1 2 3 4 5 6Demand 30 50 60 25 20 40Setup Cost 150 150 150 150 150 150Holding cost 3 3 3 3 3 3a. Find the production plan and the total cost for lot for lot scheduling.b. Find the production plan and the total cost for lot for the fixed order quantity (FOQ = 100)scheduling.c. Find the production plan and the total cost for the fixed order period scheduling (Use FOP = 3weeks).d. Which strategy is the best?arrow_forward
- Emery Pharmaceutical uses an unstable chemical compound that must be kept in an environment where bothtemperature and humidity can be controlled. Emery uses 200 pounds per month of the chemical, estimates the holdingcost to be £3.33 (because of spoilage), and estimates order costs to be £10 per order. The cost schedules of four suppliers are as follows:SEE PHOTO ATTACHED:What quantity should be ordered, and which supplier should be used?arrow_forwardP. Sherman Corp. purchases 8,000 transistors each year as components for fishing simulation game. The unit cost of each transistor is Php 10, and cost of carrying one transistor in inventory for a year is Php 3. Ordering cost is Php 30 per order? If you are the material planner of the company, what will be your requirements in terms of; (a) lead time between ordersarrow_forwardThe Average days of inventory is?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY