Refer to Figure 18.26b. Let L = 15.24 m, γfill = 17.29 kN/m3, γsat(clay) = 19.49 kN/m3, ϕ′clay = 20°, Hf = 3.05 m, and D = 0.406 m. The water table coincides with the top of the clay layer. Determine the total downward drag on the pile. Assume that δ′ = 0.6 ϕ′clay.
FIG. 18.26 Negative skin friction
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
An anchored sheet-pile bulkhead is shown in Figure P14.10. Let L1 = 2 m, L2 = 6 m, l1 = 1 m, γ = 16 kN/m3, γsat = 18.86 kN/m3, Φ' = 32º, and c = 27 kN/m2.a. Determine the theoretical depth of embedment, D.b. Calculate the anchor force per unit length of the sheet-pile wall. Use the free earth support method.
Problem #1 The figure below shows a cantilever sheet-pile wall penetrating a granular soil. Here, L1 = 4 m, L2 = 8 m, unit weight above water table= 16.1 kN/m3, saturated unit weight = 5 18.2 kN/m3, and friction angle of sand = 32 degrees. a. What is the theoretical depth of embedment, D? b. For a 30% increase in D, what should be the total length of the sheet piles? c. Determine the theoretical maximum moment of the sheet pile. d. If the allowable flexural stress = 170 MPa, compute the required section modulus of the sheet pile.
A vertical sheet pile supports a horizontal backfill having a height of 4.5m. The backfill has a unit weight (γsat) of 19.67 kN/m^3 and an angle of internal friction of 35o. (1) Compute the required depth of penetration, (2) compute the total active force on the sheet pile, (3) compute the maximum bending moment in the cantilever sheet pile.
Chapter 18 Solutions
Fundamentals of Geotechnical Engineering (MindTap Course List)
Ch. 18 - State whether the following are true or false. a....Ch. 18 - A 1500 kN load was applied on two 20 m long and...Ch. 18 - A 500 mm diameter and 20 m long concrete pile is...Ch. 18 - A 400-mm diameter and 15 m long concrete pile is...Ch. 18 - A 400 mm 400 mm square precast concrete pile of...Ch. 18 - Prob. 18.6PCh. 18 - Prob. 18.7PCh. 18 - Prob. 18.8PCh. 18 - Determine the maximum load that can be allowed on...Ch. 18 - Prob. 18.10P
Ch. 18 - Redo Problem 18.10 using the method for...Ch. 18 - Determine the maximum load that can be allowed on...Ch. 18 - Prob. 18.13PCh. 18 - A steel pile (H-section; HP 360 1.491; see Table...Ch. 18 - A concrete pile is 18 m long and has a cross...Ch. 18 - Prob. 18.16PCh. 18 - Prob. 18.17PCh. 18 - Prob. 18.18PCh. 18 - Prob. 18.19PCh. 18 - Figure 18.26a shows a pile. Let L = 20 m, D = 450...Ch. 18 - Refer to Figure 18.26b. Let L = 15.24 m, fill =...Ch. 18 - Prob. 18.22PCh. 18 - Figure 18.39 shows a 3 5 pile group consisting of...Ch. 18 - The section of a 4 4 group pile in a layered...Ch. 18 - Prob. 18.25PCh. 18 - Prob. 18.26CTP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Similar questions
- For the braced cut described in Problem 15.16, assume that all = 170 MN/m2. a. Determine the sheet pile section (section modulus) b. What is the section modulus of the wales at level A? 15.16 Refer to the braced cut in Figure 15.50, for which = 17 kN/m3, = 30, and c = 0. The struts are located at 3 m on center in the plan. Draw the earth pressure envelope and determine the strut loads at levels A, B, and C. FIG. 15.50arrow_forwardA 5 m wide braced excavation is made in a saturated clay, as shown in Figure P19.1, with the following properties: c = 20 kN/m2, = 0, and = 18.5 kN/m3. The struts are spaced at 5 m center to center in plan. a. Determine the strut forces. b. Determine the section modulus of the sheet pile required, assuming all = 170 MN/m2. c. Determine the maximum moment for the wales at levels B and C.arrow_forwardThe cross section of a braced cut supporting a sheet pile installation in a clay soil is shown in Figure 14.22. Given: H = 12 m, clay = 17.9 kN/m3, = 0, c = 75 kN/m2, and the center-to-center spacing of struts in plan view, s = 3 m. a. Using Pecks empirical pressure diagrams, draw the earth-pressure envelope. b. Determine the strut loads at levels A, B, and C.arrow_forward
- Figure 15.53 below shows a cantilever sheet pile driven into a granular soil where the water table is 2 m below the top of the sand. The properties of thesand are: ' = 40, m = 17.5 kN/m3, and sat = 19 kN/m3. It is proposed toexcavate to a depth of 6 m below the ground level. Determine the depth towhich the sheet pile mast be driven, using the net lateral pressure diagram. Fig. 15.53arrow_forwardRefer to Figure 18.9. A cantilever sheet pile is driven into a granular soil where the water table is 2 m (L1) below the top of the sand. The properties of the sand are =40, =17.5kN/m3, and sat=19kN/m3. It is proposed to excavate to a depth of 6 m (L) below the ground level. Determine the actual depth to which the sheet pile must be driven (L + D), using the net lateral pressure diagram. Note: Dactual=1.3(L3+L4)theoryarrow_forwardA cantilever sheet pile 8.20m long is embedded to a depth of 3.20m. It supports dry sand with a dry unit weight of 15.72kN/m3 and an angle of shearing resistance of 34°. The water table is located at the bottom of the sheet pile. Which of the following most nearly gives the total active pressure acting on the sheet pile per meter width?arrow_forward
- The cross section of a braced cut supporting a sheet pile installation in a clay soil is shown in the figure below. Given: H = 12 m , clay = 17.9 kN/m3 , = 0 , C = 75 kN/m2 , and the center-to-center spacing of struts in plan view , S = 3 m.arrow_forwardIn Problem 18.4, find the maximum bending moment in the sheet pile and determine the required section modulus, assuming an allowable stress of 190 MN/m2. 18.4 Refer to Figure 18.13. Given L1 = 1.5 m, L2 = 3 m; for the sand, =33, =16.5kN/m3, sat=19.0kN/m3; and, for the clay, c=50kN/m2, =0, sat=20kN/m3. Determine the depth of sheet pile required, allowing for a 50% increase from the theoretical estimate.arrow_forwardRefer to the braced cut shown below. Given: unit weight = 17 kN/m3, Friction angle = 35degrees, and c = 0. The struts are located at 3 m center-to-center in the plan. a. Draw the earth-pressure envelope and determine the strut loads at levels A, B, and C. b. Determine the sheet-pile section modulus c. Determine the section modulus of the wales at level B Assume that = 170 MN/m2.arrow_forward
- A circular pile having a diameter of 0.35 m is embedded through a layer of 4.5 m thick of clay layer into a dense sand having a bearing capacity factor of 78. Unit weight of clay is 16 kN/m3 and saturated unit weight of sand is 18 kN/m3. Water table is located at the top of the sand layer. Lateral pressure factor of compression K = 1.20 and coefficient of friction of concrete pile is 0.42. The allowable capacity 600 kN. Using a factor of safety of 3. Determine the effective vertical stress at the critical depth.arrow_forwardDetermine the depth of penetration of the wall into the silty clay soil and the maximum bending moment by FSM method . A cantilever sheet pile wall is required to temporarily support an embankment for an access road, as shown in Figure.Groundwater is 10 mbelow the surface.arrow_forwardIn Problem 14.6, assume that Dactual = 1.3 Dtheory.a. Determine the theoretical maximum moment.b. Using Rowe’s moment reduction technique, choose a sheet-pile section. Take E = 210 x 103 MN/m2 and σall = 210,000 kN/m2.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Fundamentals of Geotechnical Engineering (MindTap...Civil EngineeringISBN:9781305635180Author:Braja M. Das, Nagaratnam SivakuganPublisher:Cengage LearningPrinciples of Foundation Engineering (MindTap Cou...Civil EngineeringISBN:9781337705028Author:Braja M. Das, Nagaratnam SivakuganPublisher:Cengage LearningPrinciples of Foundation Engineering (MindTap Cou...Civil EngineeringISBN:9781305081550Author:Braja M. DasPublisher:Cengage Learning
- Principles of Geotechnical Engineering (MindTap C...Civil EngineeringISBN:9781305970939Author:Braja M. Das, Khaled SobhanPublisher:Cengage Learning
Fundamentals of Geotechnical Engineering (MindTap...
Civil Engineering
ISBN:9781305635180
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning
Principles of Foundation Engineering (MindTap Cou...
Civil Engineering
ISBN:9781337705028
Author:Braja M. Das, Nagaratnam Sivakugan
Publisher:Cengage Learning
Principles of Foundation Engineering (MindTap Cou...
Civil Engineering
ISBN:9781305081550
Author:Braja M. Das
Publisher:Cengage Learning
Principles of Geotechnical Engineering (MindTap C...
Civil Engineering
ISBN:9781305970939
Author:Braja M. Das, Khaled Sobhan
Publisher:Cengage Learning
How to build angle braces; Author: Country Living With The Harnish's;https://www.youtube.com/watch?v=3cKselS6rxY;License: Standard Youtube License