Textbook Question
Chapter 23, Problem P23.31BPGB
Preparing a flexible budget computing
Root Recliners manufactures leather recliners and uses flexible budgeting and a standard cost system. Root allocates
The company’s performance report includes the following selected data: | |||
Static Budget (1,000 recliners) | Actual Results(980 recliners) | ||
Sales | (1,000 recliners × $505 each) | $ 505,000 | |
(980 recliners × $490 each) | $ 480,200 | ||
Variable |
|||
Direct Materials | (6,000 yds. @ $8.70/yd.) | 52,200 | |
(6,143 yds. @ $8.50/yd.) | 52,216 | ||
Direct Labor | (10,000 DLHr @ $9.00/DLHr) | 90,000 | |
(9,600 DLHr @ $9.10/DLHr) | 87,360 | ||
Variable Overhead | (6,000 yds. @ $5.00/yd) | 30,000 | |
(6,143 yds @ $6.40/yd.) | 39,315 | ||
Fixed Manufacturing Costs | |||
Fixed Overhead | |||
60,000 | 62,000 | ||
Total Cost of Goods Sold | 232,200 | 240,891 | |
Gross Profit | |||
$ 272,800 | $ 239,309 |
Requirements
- Prepare a flexible budget, based on the actual number of recliners sold.
- Compute the cost variance and the efficiency variance for direct materials and for direct labor. For manufacturing overhead, compute the variable overhead cost, variable overhead efficiency, fixed overhead cost, and fixed overhead volume variances. Round to the nearest dollar.
- Have Root’s managers done a good job or a poor job controlling materials, labor, and overhead costs? Why?
- Describe how Root’s managers can benefit from the standard cost system.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionChapter 23 Solutions
Horngren's Accounting Plus MyAccountingLab with Pearson eText -- Access Card Package (11th Edition) (Miller-Nobles et al., The Horngren Accounting Series)
Ch. 23 - Prob. 1QCCh. 23 - MajorNet Systems is a start-up company that makes...Ch. 23 - MajorNet Systems is a start-up company that makes...Ch. 23 - MajorNet Systems is a start-up company that makes...Ch. 23 - MajorNet Systems has budgeted three hours of...Ch. 23 - MajorNet Systems has budgeted three hours of...Ch. 23 - FrontGrade Systems allocates manufacturing...Ch. 23 - FrontGrade Systems allocates manufacturing...Ch. 23 - FrontGrade Systems allocates manufacturing...Ch. 23 - The person probably most responsible for the...
Ch. 23 - HajorNet System’s static budget predicted...Ch. 23 - What is a variance?Ch. 23 - Explain the difference between a favorable and an...Ch. 23 - What is a static budget performance report?Ch. 23 - How do flexible budgets differ from static...Ch. 23 - How is a flexible budget used?Ch. 23 - What are the two components of the static budget...Ch. 23 - What is a flexible budget performance report?Ch. 23 - What is a standard cost system?Ch. 23 - Explain the difference between a cost standard and...Ch. 23 - Give the general formulas for determining cost and...Ch. 23 - How does the static budget affect cost and...Ch. 23 - List the direct materials variances, and briefly...Ch. 23 - List the direct labor variances, and briefly...Ch. 23 - List the variable overhead variances, and briefly...Ch. 23 - List the fixed overhead variances, and briefly...Ch. 23 - How is the fixed overhead volume variance...Ch. 23 - What is management by exception?Ch. 23 - List the eight product variances and the manager...Ch. 23 - Briefly describe how journal entries differ in a...Ch. 23 - What is a standard cost income statement?Ch. 23 - Matching terms Learning Objective 1 Match each...Ch. 23 - Prob. S23.2SECh. 23 - Prob. S23.3SECh. 23 - Matching terms Learning Objective 2 Match each...Ch. 23 - Identifying the benefits of standard costs...Ch. 23 - Prob. S23.6SECh. 23 - Prob. S23.7SECh. 23 - Interpreting material and labor variances Learning...Ch. 23 - Prob. S23.9SECh. 23 - Prob. S23.10SECh. 23 - Prob. S23.11SECh. 23 - Prob. S23.12SECh. 23 - Prob. S23.13SECh. 23 - Prob. S23.14SECh. 23 - Prob. E23.15ECh. 23 - Prob. E23.16ECh. 23 - Prob. E23.17ECh. 23 - Prob. E23.18ECh. 23 - Prob. E23.19ECh. 23 - Prob. E23.20ECh. 23 - Prob. E23.21ECh. 23 - Prob. E23.22ECh. 23 - Preparing journal entries Hayesvillc Company uses...Ch. 23 - Prob. E23.24ECh. 23 - Prob. P23.25APGACh. 23 - Preparing a flexible budget computing standard...Ch. 23 - Prob. P23.27APGACh. 23 - P23-28A Computing and journalizing standard cost...Ch. 23 - Prob. P23.29APGACh. 23 - Prob. P23.30BPGBCh. 23 - Preparing a flexible budget computing standard...Ch. 23 - P23-32B Computing standard cost variances and...Ch. 23 - P23-33B Computing and journalizing standard cost...Ch. 23 - Preparing a standard cost income statement...Ch. 23 - Prob. P23.35CPCh. 23 - Decision Case 23-1 Suppose you manage the local...Ch. 23 - Fraud Case 23-1 Drew Castello, general manager of...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Titanium Blades refines titanium for use in all brands of razor blades. It prepared a static budget for the sales of 5,000 units. These variances were observed: Determine the static budget and use the information to prepare a flexible budget and analysis for the 6,000 units actually sold.arrow_forwardFlexible budgeting and variance analysis Im Really Cold Coat Company makes womens and mens coats. Both products require filler and lining material. The following planning information has been made available: Im Really Cold Coat Company does not expect there to be any beginning or ending inventories of filler and lining material. At the end of the budget year, Im Really Cold Coat Company experienced the following actual results: The expected beginning inventory and desired ending inventory were realized. Instructions 1. Prepare the following variance analyses for both coats and the total, based on the actual results and production levels at the end of the budget year: A. Direct materials price, quantity, and total variance. B. Direct labor rate, time, and total variance. 2. Why are the standard amounts in part (1) based on the actual production at the end of the year instead of the planned production at the beginning of the year?arrow_forwardFlexible budgeting and variance analysis I Love My Chocolate Company makes dark chocolate and light chocolate. Both products require cocoa and sugar. The following planning information has been made available: I Love My Chocolate Company does not expect there to be any beginning or ending inventories of cocoa or sugar. At the end of the budget year, I Love My Chocolate Company had the following actual results: Instructions 1. Prepare the following variance analyses for both chocolates and the total, based on the actual results and production levels at the end of the budget year: A. Direct materials price, quantity, and total variance. B. Direct labor rate, time, and total variance. 2. Why are the standard amounts in part (1) based on the actual production for the year instead of the planned production for the year?arrow_forward
- Determining Budgeted Overhead The overhead application rate for a company is 10 per unit, made up of 6 per unit of fixed overhead and 4 per unit of variable overhead. Normal capacity is 10,000 units. In one month there was a favorable flexible budget variance of 2,500. Actual overhead for the month was 110,000 and actual units produced were 13,125. Based on this information, determine the amount of the budgeted overhead for the actual level of production.arrow_forwardCalculating factory overhead: two variances Monrovia Manufacturing Inc. normally produces 10,000 units of product A each month. Each unit requires 4 hours of direct labor, and factory overhead is applied on a direct labor hour basis. Fixed costs and variable costs in factory overhead at the normal capacity are 10 and 5 per unit, respectively. Cost and production data for June follow: a. Calculate the flexible-budget variance. b. Calculate the production-volume variance. c. Was the total factory overhead under- or overapplied? By what amount?arrow_forwardCalculating factory overhead: two variances Munoz Manufacturing Co. normally produces 10,000 units of product X each month. Each unit requires 2 hours of direct labor, and factory overhead is applied on a direct labor hour basis. Fixed costs and variable costs in factory overhead at the normal capacity are 2.50 and 1.50 per direct labor hour, respectively. Cost and production data for May follow: a. Calculate the flexible-budget variance. b. Calculate the production-volume variance. c. Was the total factory overhead under- or overapplied? By what amount?arrow_forward
- Cortez Manufacturing, Inc. has the following flexible budget formulas and amounts: Actual results for May for the production and sale of 5,000 units were as follows: Prepare a performance report for May that includes the identification of the favorable and unfavorable variances.arrow_forwardPreparing a performance report Use the flexible budget prepared in P7-6 for the 31,000-unit level and the actual operating results listed below for the 31,000-unit level. Required: 1. Prepare a performance report. 2. List the major reasons why the actual operating income at 31,000 units differs from the master budget operating income at 30,000 units in Figure 7-12. 3. Given the level at which the company operated, how was its cost control? Item Direct materials: Direct labor:arrow_forwardPreparing a performance report Use the flexible budget prepared in P7-6 for the 29,000-unit level of activity and the actual operating results listed below for the 29,000- unit level. Required: 1. Prepare a performance report. 2. List the major reasons why the actual operating income at 29,000 units differs from the master budget operating income at 30,000 units in Figure 7-12. 3. Given the level at which the company operated, how was its cost control? Item Direct materials: Direct labor:arrow_forward
- Refer to the data in Exercise 9.15. Required: 1. Compute overhead variances using a two-variance analysis. 2. Compute overhead variances using a three-variance analysis. 3. Illustrate how the two- and three-variance analyses are related to the four-variance analysis. Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 120,000 units requiring 480,000 direct labor hours. (Practical capacity is 500,000 hours.) Annual budgeted overhead costs total 787,200, of which 556,800 is fixed overhead. A total of 119,400 units using 478,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were 230,600, and actual fixed overhead costs were 556,250. Required: 1. Compute the fixed overhead spending and volume variances. How would you interpret the spending variance? Discuss the possible interpretations of the volume variance. Which is most appropriate for this example? 2. Compute the variable overhead spending and efficiency variances. How is the variable overhead spending variance like the price variances of direct labor and direct materials? How is it different? How is the variable overhead efficiency variance related to the direct labor efficiency variance?arrow_forwardFactory overhead cost variance report Tannin Products Inc. prepared the following factory overhead cost budget for the Trim Department for July of the current year, during which it expected to use 20,000 hours for production: Tannin has available 25,000 hours of monthly productive capacity in the Trim Department under normal business conditions. During July, the Trim Department actually used 22,000 hours for production. The actual fixed costs were as budgeted. The actual variable overhead for July was as follows: Construct a factory overhead cost variance report for the Trim Department for July.arrow_forwardDirect labor time variance Maywood City Police uses variance analysis to monitor police staffing. The following table identifies three common police activities, the standard time to perform each activity, and their actual frequency to establish the expected cost to serve these activities. The police are paid 25 per hour. The actual amount of hours per activity for the year were as follows: A. Determine the total budgeted cost to perform the three police activities. B. Determine the total actual cost to perform the three police activities. C. Determine the direct labor time variance. D. What does the time variance suggest?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningPrinciples of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage LearningFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage LearningPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Cost control, Why cost control is necessary for a business?; Author: Educationleaves;https://www.youtube.com/watch?v=yMg3gJx48Fg;License: Standard youtube license