![Operations Management](https://www.bartleby.com/isbn_cover_images/9781260484687/9781260484687_largeCoverImage.gif)
Operations Management
2nd Edition
ISBN: 9781260484687
Author: CACHON, Gerard
Publisher: MCGRAW-HILL HIGHER EDUCATION
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 6, Problem 12PA
Summary Introduction
To determine: The three elements of a standard work sheet.
Expert Solution & Answer
![Check Mark](/static/check-mark.png)
Want to see the full answer?
Check out a sample textbook solution![Blurred answer](/static/blurred-answer.jpg)
Students have asked these similar questions
What are the three elements of a standard work sheet?a. They are the processing time for an activity, the work sequence of all steps making upthe activity, and the standard amount of inventory at the resource.b. They are the processing time for an activity, the most common cause of failure, andthe standard amount of inventory at the resource.c. They are the defect rate for an activity, the work sequence of all steps making up theactivity, and the standard amount of inventory at the resource.d. They are the processing time for an activity, the most common cause of failure, andthe defect rate for an activity.
Sustainable Performance Phase - The Sustainable Performance Phase transfers the process from being project oriented to an
organization driven process. The purpose of this phase is to ensure the process is able to be maintained and make it part of
business-as-usual.
The BPM project is not over once the changes are implemented. The focus then needs to shift to monitoring feedback This feedback is usually obtained through the development of feedback loops. This feedback is important so the organization can continually improve its process and maintain a competitive advantage. Consider the following question as it applies to continual improvement and feedback loops.
1. What steps (place them in order from most important to least important) should be taken to develop an effective continuous feedback loop?
2. What controls would be necessary to ensure only valid data is collected?
What are the three elements of a standard work sheet?a. They are the processing time for an activity, the work sequence of all steps making upthe activity, and the standard amount of inventory at the resource.b. They are the processing time for an activity, the responsible operator, and the standardamount of inventory at the resource.c. They are the defect rate for an activity, the work sequence of all steps making up theactivity, and the standard amount of inventory at the resource.d. None of the above
Chapter 6 Solutions
Operations Management
Ch. 6 - Prob. 1CQCh. 6 - Prob. 2CQCh. 6 - Prob. 3CQCh. 6 - Prob. 4CQCh. 6 - Prob. 5CQCh. 6 - Prob. 6CQCh. 6 - Prob. 7CQCh. 6 - A learning curve following the power law has what...Ch. 6 - Prob. 9CQCh. 6 - Prob. 10CQ
Ch. 6 - Prob. 11CQCh. 6 - The learning curve coefficient LCC(10, 0.8)...Ch. 6 - Prob. 13CQCh. 6 - Instead of using the learning curve coefficient...Ch. 6 - Prob. 15CQCh. 6 - Prob. 16CQCh. 6 - Prob. 17CQCh. 6 - Prob. 18CQCh. 6 - Prob. 19CQCh. 6 - Prob. 20CQCh. 6 - Prob. 21CQCh. 6 - Prob. 22CQCh. 6 - Prob. 23CQCh. 6 - Prob. 24CQCh. 6 - Prob. 25CQCh. 6 - Prob. 1PACh. 6 - Prob. 2PACh. 6 - Prob. 3PACh. 6 - Prob. 4PACh. 6 - Prob. 5PACh. 6 - Prob. 6PACh. 6 - Prob. 7PACh. 6 - Prob. 8PACh. 6 - Prob. 9PACh. 6 - Prob. 10PACh. 6 - A company has 2200 employees, on average, and it...Ch. 6 - Prob. 12PACh. 6 - Prob. 13PACh. 6 - Prob. 14PACh. 6 - In October 1908, just prior to the launch of his...Ch. 6 - Prob. 2CCh. 6 - Prob. 3C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Heizer and Render advises that when analyzing and designing processes to transform resources into goods, the followingquestions should be asked:- Is the process designed to achieve competitive advantage in terms of differentiation, response or low cost?- Does the process eliminate steps that do not add value?- Does the process maximize customer value as perceived by the customer?- Will the process win orders?A Time-Function Map is similar to a flow process chart, but with time added to the horizontal axis. With time-function mapping,notes indicate the activities and arrows indicate the flow direction, with time on the horizontal axis.arrow_forwardCreate two (2) Job Safety Analysis on a specific job task from your place of business or your world outside of business. Example: Job = Warehouse Worker Job Task = unloading a semi-truck parked at your dock doors Job Task = shrink-wrapping a pallet Job Task = pulling raw material from inventory The focus of the JSA is to be demonstrate your understanding of how a JSA is developed and documented.arrow_forwardHeizer and Render advises that when analyzing and designing processes to transform resources into goods, the followingquestions should be asked:- Is the process designed to achieve competitive advantage in terms of differentiation, response or low cost?- Does the process eliminate steps that do not add value?- Does the process maximize customer value as perceived by the customer?- Will the process win orders?A Time-Function Map is similar to a flow process chart, but with time added to the horizontal axis. With time-function mapping,notes indicate the activities and arrows indicate the flow direction, with time on the horizontal axis. 1. Choose a process within your organization and construct a Baseline Time-Function Maparrow_forward
- A teacher wanted to know which learning delivery modes (pure online, pure modular, combination of online and modular) is most effective and has the fastest turnaround time in the submission of accomplished activities among her Grade 12 students. She divided the students into 3 groups, gave them the same activity sheets and asked them to submit as soon as it is completed. She then compared the scores and completion time of the 3 groups. What is the independent, dependent, and extraneous variable?arrow_forwardThe following reflects the types of processes aligned with the process analysis method: a. Directional and informational b. Directed and informed c. Directional and informative d. Directional informationarrow_forwardIf you don't provide an adequate response, the experts will downvote your answer. What exactly is meant by the term "process framework"? In the process models, what are the five general actions that take place?arrow_forward
- In each of the following, name the term defined or answer the question. Answers are listed at the bottom.1. This is a part of an organization that takes inputs and transforms them into outputs.2. This is the ratio of the time that a resource is activated relative to the time it is available for use.3. This is when one or more activities stop because of a lack of work.4. This is when activity stops because there is no place to put the work that was just completed.5. This is a step in a process that is the slowest compared to the other steps. This step limits the capacity of the process.6. What is the difference between McDonald’s old and current processes?7. This refers to the fixed timing of the movement of items through a process.arrow_forwardOne of the risks that might occur from weaknesses in requirement procedures is creeping user requirements. What steps may be taken to lessen this risk?arrow_forwardThe continuous improvement system based on the UNE 66178 standard is based on these fundamental processes: a. the improvement project b. all options are correct c. improvement monitoring, assessing and review d. analysis of informationarrow_forward
- State whether the following statements are true or false. If the statement is false, write its correct answer: 1. Process and Product design should be put in a way to reach customer satisfaction, and decrease profit and selling. Answer: 2. Operations management can be utilized in Process design, for it is beneficial to reduce the value of the product at every phase of its production. Answer: 3. A flow chart is a diagram that uses arrows and different symbols to represent consecutive events of a workflow or process. Answer: 4. The five key performance factors to access a process performance are: quantity, speed, dependability, flexibility and cost. Answer: 5. The process design consists of different steps and stages that are classified in an unorganized order, for the successful creation of the final product. Answer: 6. In the service industry, it’s possible to separate service design from process design. Answer: 7. Design is any part of an organization which…arrow_forwardA teacher wanted to know which learning delivery modes (pure online, pure modular, combination of online and modular) is most effective and has the fastest turnaround time in the submission of accomplished activities among her Grade 12 students. She divided the students into 3 groups, gave them the same activity sheets and asked them to submit as soon as it is completed. She then compared the scores and completion time of the 3 groups. Identify the independent, dependent and extraneous variablearrow_forwardSuppose you are in charge of a large mailing to the alumni of your college inviting them to contribute to a scholarship fund. The letters and envelopes have been individually addressed (mailing labels were not used). The letters are to be processed (matched with correct envelope, time estimated to be 0.2 minutes each), folded (0.12 minutes each), and stuffed into the correct envelope (0.10 minutes each). The envelopes are to be sealed (0.05 minutes each), and a large commemorative stamp is to be placed in the upper right-hand corner of each envelope (0.10 minutes each).a. Make a process chart for this activity, assuming that it is aone-person operation.b. Estimate how long it will take to stuff, seal, and stamp 2,000 envelopes. Assume that the person doing this work is paid $8 per hour. How much will it cost to process 2,000 letters?c. Consider each of the following process changes. Which changes would reduce the time and cost of the current process?▪ Each letter has the same greeting,…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
![Text book image](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
![Text book image](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
![Text book image](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY