Textbook Question
Chapter 8, Problem 8.34E
Flexible-
At the beginning of 2017, DDC budgeted annual production of 420,000 doorknobs and adopted the following standards for each doorknob:
Input | Cost/Doorknob | |
Direct materials (brass) | 0.3 lb. @ $10/lb. | $ 3.00 |
Direct manufacturing labor | 1.2 hours @ $17/hour | 20.40 |
Manufacturing overhead: | ||
Variable | $5/lb. × 0.3 lb. | 1.50 |
Fixed | $15/lb. × 0.31lb. | 4.50 |
$29.40 |
Actual results for April 2017 were as follows:
Production | 29,000 doorknobs |
Direct materials purchased | 12,400 lb. at $11/lb. |
Direct materials used | 8,500 lbs. |
Direct manufacturing labor | 29,200 hours for $671,600 |
Variable manufacturing overhead | $ 65,100 |
Fixed manufacturing overhead | $158,000 |
- A. For the month of April, compute the following variances, indicating whether each is favorable (F) or unfavorable (U):
Required
- a. Direct materials price variance (based on purchases)
- b. Direct materials efficiency variance
- c. Direct manufacturing labor price variance
- d. Direct manufacturing labor efficiency variance
- e. Variable manufacturing overhead spending variance
- f. Variable manufacturing overhead efficiency variance
- g. Production-volume variance
- h. Fixed manufacturing overhead spending variance
- B. Can Williams use any of the variances to help explain any of the other variances? Give examples.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionChapter 8 Solutions
CUSTOM COST ACCT 2521 SWP W/ ACCESS
Ch. 8 - How do managers plan for variable overhead costs?Ch. 8 - How does the planning of fixed overhead costs...Ch. 8 - How does standard costing differ from actual...Ch. 8 - What are the steps in developing a budgeted...Ch. 8 - What are the factors that affect the spending...Ch. 8 - Assume variable manufacturing overhead is...Ch. 8 - Describe the difference between a direct materials...Ch. 8 - What are the steps in developing a budgeted fixed...Ch. 8 - Why is the flexible-budget variance the same...Ch. 8 - Explain how the analysis of fixed manufacturing...
Ch. 8 - Provide one caveat that will affect whether a...Ch. 8 - The production-volume variance should always be...Ch. 8 - What are the variances in a 4-variance analysis?Ch. 8 - Overhead variances should be viewed as...Ch. 8 - Describe how flexible-budget variance analysis can...Ch. 8 - Each of the following statements is correct...Ch. 8 - Steed Co. budgets production of 150,000 units in...Ch. 8 - As part of her annual review of her companys...Ch. 8 - Culpepper Corporation had the following...Ch. 8 - Fordham Corporation produces a single product. The...Ch. 8 - Variable manufacturing overhead, variance...Ch. 8 - Fixed manufacturing overhead, variance analysis...Ch. 8 - Variable manufacturing overhead variance analysis....Ch. 8 - Fixed manufacturing overhead variance analysis...Ch. 8 - Manufacturing overhead, variance analysis. The...Ch. 8 - 4-variance analysis, fill in the blanks. ProChem...Ch. 8 - Straightforward 4-variance overhead analysis. The...Ch. 8 - Straightforward coverage of manufacturing...Ch. 8 - Overhead variances, service sector. Meals Made...Ch. 8 - Total overhead, 3-variance analysis. Pampered...Ch. 8 - Production-volume variance analysis and...Ch. 8 - Overhead variances, service setting. Carlyle...Ch. 8 - Identifying favorable and unfavorable variances....Ch. 8 - Flexible-budget variances, review of Chapters 7...Ch. 8 - Comprehensive variance analysis. Cooking Whiz...Ch. 8 - Journal entries (continuation of 8-35). A. Prepare...Ch. 8 - Graphs and overhead variances. Best Around, Inc.,...Ch. 8 - Overhead variance, missing information. Consider...Ch. 8 - Flexible budgets, 4-variance analysis. (CMA,...Ch. 8 - Activity-based costing, batch-level variance...Ch. 8 - Overhead variances and sales-volume variance. The...Ch. 8 - Activity-based costing, batch-level variance...Ch. 8 - Comprehensive review of Chapters 7 and 8, working...Ch. 8 - Review of Chapters 7 and 8, 3-variance analysis....Ch. 8 - Nonfinancial variances. Kathys Kettle Potato Chips...Ch. 8 - Overhead variances, service sector. Cavio is a...Ch. 8 - Direct-cost and overhead variances, income...Ch. 8 - Overhead variances, ethics. Carpenter Company uses...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Flexible budgeting and variance analysis Im Really Cold Coat Company makes womens and mens coats. Both products require filler and lining material. The following planning information has been made available: Im Really Cold Coat Company does not expect there to be any beginning or ending inventories of filler and lining material. At the end of the budget year, Im Really Cold Coat Company experienced the following actual results: The expected beginning inventory and desired ending inventory were realized. Instructions 1. Prepare the following variance analyses for both coats and the total, based on the actual results and production levels at the end of the budget year: A. Direct materials price, quantity, and total variance. B. Direct labor rate, time, and total variance. 2. Why are the standard amounts in part (1) based on the actual production at the end of the year instead of the planned production at the beginning of the year?arrow_forwardListed below are the budgeted factory overhead costs for 2011 for Moss Industries at a projected level of 2,000 units: Required: Prepare flexible budgets for factory overhead at the 1,000, 2,000, and 4,000 unit levels. (Hint: You must first decide which of the listed costs should be considered variable and which should be fixed.)arrow_forwardCortez Manufacturing, Inc. has the following flexible budget formulas and amounts: Actual results for May for the production and sale of 5,000 units were as follows: Prepare a performance report for May that includes the identification of the favorable and unfavorable variances.arrow_forward
- As part of its cost control program, Tracer Company uses a standard costing system for all manufactured items. The standard cost for each item is established at the beginning of the fiscal year, and the standards are not revised until the beginning of the next fiscal year. Changes in costs, caused during the year by changes in direct materials or direct labor inputs or by changes in the manufacturing process, are recognized as they occur by the inclusion of planned variances in Tracers monthly operating budgets. The following direct labor standard was established for one of Tracers products, effective June 1, 2012, the beginning of the fiscal year: The standard was based on the direct labor being performed by a team consisting of five persons with Assembler A skills, three persons with Assembler B skills, and two persons with machinist skills; this team represents the most efficient use of the companys skilled employees. The standard also assumed that the quality of direct materials that had been used in prior years would be available for the coming year. For the first seven months of the fiscal year, actual manufacturing costs at Tracer have been within the standards established. However, the company has received a significant increase in orders, and there is an insufficient number of skilled workers to meet the increased production. Therefore, beginning in January, the production teams will consist of eight persons with Assembler A skills, one person with Assembler B skills, and one person with machinist skills. The reorganized teams will work more slowly than the normal teams, and as a result, only 80 units will be produced in the same time period in which 100 units would normally be produced. Faulty work has never been a cause for units to be rejected in the final inspection process, and it is not expected to be a cause for rejection with the reorganized teams. Furthermore, Tracer has been notified by its direct materials supplier that lower-quality direct materials will be supplied beginning January 1. Normally, one unit of direct materials is required for each good unit produced, and no units are lost due to defective direct materials. Tracer estimates that 6 percent of the units manufactured after January 1 will be rejected in the final inspection process due to defective direct materials. Required: 1. Determine the number of units of lower quality direct materials that Tracer Company must enter into production in order to produce 47,000 good finished units. 2. How many hours of each class of direct labor must be used to manufacture 47,000 good finished units? 3. Determine the amount that should be included in Tracers January operating budget for the planned direct labor variance caused by the reorganization of the direct labor teams and the lower quality direct materials. (CMA adapted)arrow_forwardRefer to Cornerstone Exercise 8.13. In March, Nashler Company produced 163,200 units and had the following actual costs: Required: 1. Prepare a performance report for Nashler Company comparing actual costs with the flexible budget for actual units produced. 2. What if Nashler Companys actual direct materials cost were 1,175,040? How would that affect the variance for direct materials? The total cost variance?arrow_forwardDirect materials and direct labor variances At the beginning of June, Bezco Toy Company budgeted 5,000 toy action figures to be manufactured in June at standard direct materials and direct labor costs as follows: The standard materials price is 4.00 per pound. The standard direct labor rate is 18.00 per hour. At the end of June, the actual direct materials and direct labor costs were as follows: There were no direct materials price or direct labor rate variances for June. In addition, assume no changes in the direct materials inventory balances in June. Bezco Toy Company actually produced 4,850 units during June. Determine the direct materials quantity and direct labor time variances.arrow_forward
- Georgia Gasket Co. budgets 8,000 direct labor hours for the year. The total overhead budget is expected to amount to 20,000. The standard cost for a unit of the companys product estimates the variable overhead as follows: The actual data for the period follow: Using the four-variance method, calculate the overhead variances. (Hint: First compute the budgeted fixed overhead rate.)arrow_forwardThe normal capacity of a manufacturing plant is 30,000 direct labor hours or 20,000 units per month. Standard fixed costs are 6,000, and variable costs are 12,000. Data for two months follow: For each month, make a single journal entry to charge overhead to Work in Process, to close Factory Overhead, and to record variances. Indicate the types of variances and state whether each is favorable or unfavorable. (Hint: You must first compute the flexible-budget and production-volume variances.)arrow_forwardFlexible budget for factory overhead Presented below are the monthly factory overhead cost budget (at normal capacity of 5,000 units or 20,000 direct labor hours) and the production and cost data for a month. The predetermined overhead rate is based on normal capacity. Required: 1. Assuming that variable costs will vary in direct proportion to the change in volume, prepare a flexible budget for production levels of 80%, 90%, and 110% of normal capacity. Also determine the predetermined factory overhead rate at each level of volume in both units and direct labor hours. 2. Prepare a flexible budget for production levels of 80%, 90%, and 110%, assuming that variable costs will vary in direct proportion to the change in volume, but with the following exceptions. (Hint: Set up a third category for semi-variable expenses.) a. At 110% of capacity, another supervisor will be needed at a salary of 24,000 annually. b. At 80% of capacity, the repairs expense will drop to one-half of the amount at 100% capacity. c. At 80% of capacity, one part-time maintenance worker, earning 10,000 a year, will be laid off. d. At 110% of capacity, a machine not normally in use and on which no depreciation is normally recorded will be used in production. Its cost was 12,000, it has a 10-year life, and straight-line depreciation will be taken.arrow_forward
- Fargo Co. manufactures products in batches of 100 units per batch. The company uses a standard cost system and prepares budgets that call for 500 of these batches per period. Budgeted fixed overhead is $60,000 per period. The standard costs per batch follow: During the period, 503 batches were manufactured, and the following costs were incurred: Required: Calculate the variances for materials, labor, and overhead. For overhead, use the two-variance method. (Hint: Please use the information given about the budgeted fixed overhead to compute the variable overhead rate.)arrow_forwardDetermining Budgeted Overhead The overhead application rate for a company is 10 per unit, made up of 6 per unit of fixed overhead and 4 per unit of variable overhead. Normal capacity is 10,000 units. In one month there was a favorable flexible budget variance of 2,500. Actual overhead for the month was 110,000 and actual units produced were 13,125. Based on this information, determine the amount of the budgeted overhead for the actual level of production.arrow_forwardFlexible budgeting and variance analysis I Love My Chocolate Company makes dark chocolate and light chocolate. Both products require cocoa and sugar. The following planning information has been made available: I Love My Chocolate Company does not expect there to be any beginning or ending inventories of cocoa or sugar. At the end of the budget year, I Love My Chocolate Company had the following actual results: Instructions 1. Prepare the following variance analyses for both chocolates and the total, based on the actual results and production levels at the end of the budget year: A. Direct materials price, quantity, and total variance. B. Direct labor rate, time, and total variance. 2. Why are the standard amounts in part (1) based on the actual production for the year instead of the planned production for the year?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College PubFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,Principles of Cost AccountingAccountingISBN:9781305087408Author:Edward J. Vanderbeck, Maria R. MitchellPublisher:Cengage Learning
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Principles of Cost Accounting
Accounting
ISBN:9781305087408
Author:Edward J. Vanderbeck, Maria R. Mitchell
Publisher:Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
What is variance analysis?; Author: Corporate finance institute;https://www.youtube.com/watch?v=SMTa1lZu7Qw;License: Standard YouTube License, CC-BY