Interpretation:The method in which the following planned orders will be released so that the yields are less than 100 percent is to be determined.
Concept Introduction:
The operational feasibility can be defined as the measurement of the problem solving capacity of the proposed system and it also checks that in which manner this proposed system is satisfying the requirements which are identified in the requirement analysis phase during the system development.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The Alpha Beta Company produces two products; A and B,
that are made from components C and D. Given the follow-ing product structures, master scheduling requirements,
and inventory information, determine when orders shouldbe released for A, B, C, and D and the size of those orders.
The MRP gross requirements for Item X are shown here for the next 10 weeks. Lead time for A is two weeks, and setup
cost is $10. There is a carrying cost of $0.02 per unit per week. Beginning Inventory is 72 units.
WTEK
10
Gross requirenente
21
12
15
45
10
30
100
20
40
150
Use the least total cost lot-sizing method to determine the quantity to order with the first order released and which
periods' requirements will be covered by that order.
Least total cost method indicates that
unite nhould be ondered to cover the needs for periods
A company produces skateboards. Each skateboard (A) consists of one unit of board (B), and two units of sub-assembly of roller-set (C). Roller-sets comprise of 2
components: 2 rollers (D) and one axle (E). The MPS is as follows:
Week
1
2
3
4
5
6
7
8
9
10
A
D
40
50
60
80
What are the planned order releases for item A? A has an on-hand inventory of 10, safety stock of 0. The lead time is 1 week and the ordering policy is Lot-for-Lot
(L4L).
Chapter 8 Solutions
EBK PRODUCTION AND OPERATIONS ANALYSIS
Ch. 8.1 - Prob. 1PCh. 8.1 - Prob. 2PCh. 8.1 - Prob. 3PCh. 8.1 - Prob. 4PCh. 8.1 - Prob. 5PCh. 8.1 - Prob. 6PCh. 8.1 - Prob. 7PCh. 8.1 - Prob. 8PCh. 8.1 - Prob. 9PCh. 8.2 - Prob. 10P
Ch. 8.2 - Prob. 11PCh. 8.2 - Prob. 12PCh. 8.2 - Prob. 13PCh. 8.2 - Prob. 14PCh. 8.2 - Prob. 15PCh. 8.2 - Prob. 16PCh. 8.2 - Prob. 17PCh. 8.2 - Prob. 18PCh. 8.2 - Prob. 19PCh. 8.2 - Prob. 20PCh. 8.2 - Prob. 21PCh. 8.2 - Prob. 22PCh. 8.3 - Prob. 23PCh. 8.3 - Prob. 24PCh. 8.3 - Prob. 25PCh. 8.4 - Prob. 26PCh. 8.4 - Prob. 27PCh. 8.4 - Prob. 28PCh. 8.4 - Prob. 29PCh. 8.5 - Prob. 30PCh. 8.5 - Prob. 31PCh. 8.5 - Prob. 32PCh. 8.5 - Prob. 33PCh. 8.5 - Prob. 34PCh. 8.6 - Prob. 35PCh. 8.6 - Prob. 36PCh. 8.6 - Prob. 37PCh. 8.6 - Prob. 38PCh. 8.6 - Prob. 39PCh. 8.6 - Prob. 40PCh. 8 - Prob. 41APCh. 8 - Prob. 42APCh. 8 - Prob. 43APCh. 8 - Prob. 44APCh. 8 - Prob. 45APCh. 8 - Prob. 46APCh. 8 - Prob. 48APCh. 8 - Prob. 49APCh. 8 - Prob. 50APCh. 8 - Prob. 51AP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Phil's first step was to prepare a master schedule for one of the engine types produced by Brunswick: the Model 1000 engine. This schedule indicates the number of units of the Model 1000 engine to be assembled each week during the last 12 weeks and is shown on the next page. Next, Phil decided to simplify his requirements planning example by considering only two of the many components that are needed to complete the assembly of the Model 1000 engine. These two components, the gear box and the input shaft, are shown in the product structure diagram below. Phil noted that the gear box is assembled by the Subassembly Department and subsequently is sent to the main engine assembly line. The input shaft is one of several component parts manufactured by Brunswick that are needed to produce a gear box subassembly. Thus, levels 0, 1, and 2 are included in the product structure diagram to indicate the three manufacturing stages that are involved in producing an engine: the Engine Assembly…arrow_forwardHeather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, which are to be shipped in week 8. Assume lot-for- lot ordering. Below is information about the steppers and the quantity required for each parent. Item Lead Time On Hand Inventory Components Stepper 2 20 A(1), B(3), C(2) A 1 10 D(1), F(2) B 2 30 E(1), F(3) C 3 10 D(2), E(3) D 1 15 E 2 5 F 2 20 Develop a product structure diagram for Develop a net material requirements plan forarrow_forwardAssume material A calls out material B (qty per = 1). Material A has a stock quantity of 10. Material A has a demand for 100 due on 7/1 and there is an order for 90 with a due date of 7/1 and start date of 6/15. What is the requirement QUANTITY that will be generated for product B?arrow_forward
- The planned order releases (POR) for three components: A, B, and C, are giving below. Suppose that the yields for these components are respectively 88 percent, 90 percent, and 78 percent. Assuming lot-for-lot scheduling, how should these planned order releases be adjusted to account for the fact tha the yields are less than 100 percent? Be specific with calculations. Week 11 12 13 POR (A) 200 80 80 200 POR (B) 100 100 40 40 100 200 POR (C) 200 400 280 100 280 600 800 800 400 = 6 ccessibility. Unavailable Recovered F4 Q Search 0:- F5 7 % 8 + F6 9 10 200 09 F7 & F8 * 14 15 16 17 400 400 400 200 200 F9 F10 DOD F11 Focus Earrow_forwardPlease do not give solution in image format thankuarrow_forwardAssume you are the manager of a shop that assembles power tools. You have just received an order for 55 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws follows: Item Lead Time (weeks) On Hand Saw A B C D E F 2 1 2 2 1 1 2 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipt Planned order release Ĉ E(3) & E(2) LT = 1 week Lot size: Lot-for-Lot 15 10 5 65 20 10 30 Skip Extension Tip: Double click to open in new tab Show Transcribed Text Develop the material requirements plan for component E using lot-for-lot ordering for all items. (Leave no cells blank - be certain to enter "0" wherever required.) Components A(2), B(1), C(4) E(3), D(1) D (2), F(3) E(2), D (2) Beg. Inv. 1 2 3 190 5 210 6arrow_forward
- Courtney Kamauf schedules production of a popular Rustic Coffee Table at Kamauf Enterprises, Inc. The tablerequires a top, four legs, 18 gallon of stain, 116 gallon of glue, 2 shortbraces between the legs and 2 long braces between the legs, anda brass cap that goes on the bottom of each leg. She has 100 gallons of glue in inventory, but none of the other components. Allitems except the brass caps, stain, and glue are ordered on a lotfor-lot basis. The caps are purchased in quantities of 1,000, stainand glue by the gallon. Lead time is 1 day for each item. Schedulethe order releases necessary to produce 640 coffee tables on days5 and 6, and 128 on days 7 and 8.arrow_forwardPlease do not give solution in image format thankuarrow_forwardGiven an order cost of $100, a, per period holding cost of $.50, and the following requirements schedule: Period Demand 150 90 60 70 100 60 What is the part-period method lot size for the order for the first period? Select one а. 300 Ob. 470 c. 240 d. 370 e. 150 3arrow_forward
- Complete the MPS record below for a single item. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Item: A Order Policy: 60 units Lead Time: 1 week Quantity on Hand: 40 Week 1 4 5 6 7 8 Forecast 20 18 28 28 21 33 36 41 Customer orders 17 19 7 11 11 (booked) Projected on-hand inventory MPS quantity LO 3.arrow_forward7arrow_forwarda. If demand for the new videotape recorder is expected to be constant with a rate of 20 units per month, what is the recommended order quantity for the videotape recorder? b. What are the estimated annual inventory holding and ordering costs associated with this product? c. How many orders will be placed per year? d. With 250 working days per year, what is the cycle time for this product?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY