PM_FPX5018_ThompsonNia_Assessment2-1
.doc
keyboard_arrow_up
School
Purdue University, Fort Wayne *
*We aren’t endorsed by this school
Course
MISC
Subject
Marketing
Date
Jan 9, 2024
Type
doc
Pages
18
Uploaded by DrRoseWallaby25
Project Management Plan
Project Scope and
Work Breakdown
Schedule
Assessment 2: Cosmo Inc
Nia Thompson
PM-FPX5018
December 18, 2023
1
Table of Contents
Executive Summary (Assessment 4)
........................................................................................................
3
Project Charter (Assessment 1)
...............................................................................................................
4
Project Scope (Assessment 2)
................................................................................................................
10
Work Breakdown Structure (WBS) (Assessment 2)
...............................................................................
11
Project Management Cost (Budget) (Assessment 3)
.............................................................................
12
Project Management Schedule (Assessment 3)
.....................................................................................
12
Risk Management Plan (Assessment 4)
.................................................................................................
13
Project Quality Plan (Assessment 4)
......................................................................................................
13
Project Close and Lessons Learned (Assessment 4)
...............................................................................
14
Appendices
............................................................................................................................................
15
References
.............................................................................................................................................
16
2
Executive Summary (Assessment 4)
3
Project Charter (Assessment 1)
Project Title: Cosmo Marketing Strategy for 2024
Project Start Date: January 8, 2024
Projected Finish Date: April 8, 2024, with a launch date of June 3, 2024
Budget Information: $150,000 Project Manager: Nia B. Thompson
Business Need
Cosmo, Inc. is a leading developer and distributor of wearable technology. This includes everything from fitness coaching and nutritional coaching to lifestyle advising. They currently hold a 33 percent market share for this category. Members of the senior leadership team have done a complete analysis of the market and realize that a competitor will soon be launching technology that could potentially have a negative effect on future earnings for Cosmo, Inc. As a result of this analysis, the CEO and President Harold Living has asked the senior leadership team to develop an innovative marketing strategy that will allow Cosmo to not only maintain their status, but also increase their market share. The current market is extremely competitive and the global pandemic that we all faced in 2020 only increased the need for wearable technology. To
ensure the continued growth of the organization, we will have to make sure that we consider and include the technological trends that have occurred over the last three years. Project Objectives
The main objective for Cosmo, Inc is to create a goal that will allow the organization to continue with the advantage over the competitors currently in the market as well as incoming competitors. The following are the goals of the campaign:
Create a marketing strategy that will increase the production of wearable technology by 25 percent.
Increase the customer base by 20 percent by identifying unknown customer segments that are based on age, income, education, demographics, and technology.
Make use of current technologies which include the use of social media and data analytics, for predictive analytics to identify known and unknown customer segments.
Become a leading competitor in wearable technologies.
Use trending technologies, including IoT (Internet of Things), mobile technology, and artificial intelligence applications to continue the trend of being a lead competitor of wearable technology.
4
Integrate technology into current ERP and Marketing systems. Doing this will allow for an improved customer experience as well as improving our digital business as “meshed” with embedded services of people, devices, and content.
Develop and implement new processes within the Customer Service department that will establish new product support services.
Meet all current and future neutrality regulations.
Approach
“A project is a temporary endeavor undertaken to create a unique product, service, or result” (Project Management Institute, 2017). In following with the process outlined in the PMBOK Guide (Project Management Body of Knowledge), a project management has a life cycle that goes through five especially important phases. They are project initiation, project planning, project execution, project monitoring and controlling, and project closure. One important thing to note is that these phases may overlap with one another over the course of managing this project.
Project initiation – This is the first stage where the project will be formally stated. When Living stated what the need was for the organization was, the project was initiated. A project charter should be created during this phase which will outline constraints, goals, the budget, etc. The initiation phase will also assign roles and responsibilities for each project member.
Project planning – This phase will require refining the details discussed in the initiation phase. During this phase, the project scope is created, and the objectives are clearly defined. Some other important activities during this phase are schedule development, setting aside resources, establishing important dates, methods of communicating with one another, and what plan will be in place to identify and minimize risks.
Project execution – During this phase, the team has started working on the project. As the project manager, it will be up to me to make sure the team has the proper information to do their part. I will also be monitoring
whether the outline established will lead to this project being a success. Technology changes quickly and the team must be able to adjust to remain at a competitive advantage.
Project monitoring and controlling phase – This phase is usually done in
collaboration with the execution phase. The reason these two are often done simultaneously is to make sure that objectives are being met. My role as the project manager will be calculating key performance indicators for cost efficiency and time constraints. While assessing this, I will also be determining any corrective measures that will aid in ensuring that the project is staying on track and within the budget.
Project closing – The closing phase is the final phase of the project management process. When it is time to close the project, there will be a series of important tasks that will need to be completed. They are analyzing that objectives outline lead to a successful product launch, rewarding the team members, if the project was considered a success, 5
and lastly the delivery of the product and vital reports will be done during this phase.
Assumptions:
The company will see an increase in sales and revenue because of this project.
Cosmo, Inc. allotted $150,000 for this project and this amount is large enough
to meet all the project necessities for completion within the appropriate period.
The market will show we have the leading advantage in wearable technology that includes fitness and nutritional coaching. Constraints:
The budget is limited to $150,000, but technological advances may require us
to exceed this amount.
We are working within a limited 10-week timeframe to finish a 6-month marketing campaign strategy.
Identifying how to reach consumers that are outside of the age range and are not as tech savvy as the initial market.
Dependencies:
By requesting a new product, the demand for production will also increase.
The cost of production in lower income areas could impact consumer satisfaction.
Initial Risk Factors: “
Analyzing risk is an important part of the project planning process” (Asana, 2022). Risk factors associated with this project were assessed during the initial process of collecting the information needed to meet the project deadline. The risk factors and what strategies to use to overcome them are as follow (Asana, 2022):
If the initial project objectives are unclear, then there is an initial risk of “Scope
risk, also known as scope creep” (Asana, 2022). If these objectives are unclear, it is possible that the stakeholders can step in and try and make changes in the middle of the project. To avoid scope creep, as the project manager, it will be important to set clear parameters and once they are agreed to stick to them. It will also be important to regularly check in with other members of the project team to ensure that the parameters are in line and being followed. 6
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
- Access to all documents
- Unlimited textbook solutions
- 24/7 expert homework help
Related Questions
5]
51
Ex-2/ Find the project's total duration and date of completion (assume the project
start date is 1/12/2014). Use the following details to draw the A-O-A Network and
build its Table:
Activity
BC
E
H.
R.
Duration
4
3
4.
5
6.
(days)
Following B,D,E C,FGF,G
Activity
H,I
R
arrow_forward
Q1. Using a suitable example each, describe what the following project planning
process activities involve:
a. Establish project objective;
b. Define scope;
c. Create a Work Breakdown Structure (WBS);
d. Estimate activity durations;
e. Sequencing activities.
arrow_forward
1. Draw AOA network and Find the project duration.
arrow_forward
q6
arrow_forward
Q2.
The table below presents the information required in order to carry
out a critical path analysis of an engineering project.
a) Describe what is meant by the terms Scope and Functional
Requirements with respect to project management.
b) Complete a full forward and backwards pass analysis of the
project and highlight the critical path.
c) What is meant by the terms: critical path and float with respect to
critical path analysis?
Task
Duration
Dependency
Plan (A)
Hardware Design (B)
Hardware Test (C)
Software Design (D)
Software Test (E)
Complete Test (F)
6.
A
2
4
A
1
2
C, E
arrow_forward
*(a.) Enter the above information into Microsoft Project (submit the Microsoft Project file).
arrow_forward
Fine-Carpets Ltd. reports the following free cash flows from its recent project: - 3,000,000 + 1,160,000 + 1,273,500 + 1,492,650 What is the project's NPV if the cost of its capital is 12%? Question 2Answer a. $113,379.48 b. $311,937.48 c. $131,379.48 d. $113,397.48 e. $113,973.48
arrow_forward
i need the answer quickly
arrow_forward
Q2: Explain briefly the concept of "Project", what can it create, and what are the
main examples of it ?
arrow_forward
Q1 ) Scenarios of a project activities (tables given below) and their required times to be completed in addition to their predecessors for developing a ‘Website’:
Activity
Description
Duration (weeks)
Preceding Activities
A
Determine user needs
8
--
B
Review s/w and languages
4
--
C
Purchase software
10
--
D
Design format and style
10
B
E
Write programs
6
A
F
Review outcome product with user
12
C
G
Make revisions
4
C
H
Select server site
8
E
I
Install on server
14
D,F
J
Test
8
G,H,I
Draw the path.
Calculate the early finishing time (forwards calculations)
Highlight the total time to complete the project (days)
Calculate the late finishing time (backwards calculations)
Calculate the slack time of the non-critical path activities
Identify the critical path (highlight critical path activities)
what would happen if activity D revised to take 14 instead of 10 days?
arrow_forward
Practice Question EVM:
A simple project consists of five tasks and is scheduled to take 13 weeks to complete. The actual
status of the project at the end of week 9 is given in the following table:
Project Plan
Task | Duration Start
(weeks)
Actual status
Actual
current cost complete
S350
S225
$475
$300
End
Budget
Percent
week week
$300
100%
100%
$250
$450
$600
$500
B
2
100%
75%
75%
C
4
4
7.
9.
13
D
3
6
8
$300
a) For each activity, compute the ACWP, BCWP, BCWS and add the columns to get the
projected total. Record your answers in the table below.
Task
ACWP
BCWP
BCWS
E
b) Calculate: CV,SV,CPI, and SPI:
arrow_forward
Project management
arrow_forward
Q3) A small project consisting of eight activities has the following characteristics:
Time-Estimates (in weeks)
Afest apostle
dime (2)
Activity
ABCDEFGH
(a) Draw the network for the project.
(b) Determine the critical path.
(c) Calculate the variance of the project.
-Preceding
ectivity
None
None
A
A
A
B.C
D
EFO
N22rann
10
10
7
3
Most likely
dime (m)
4
12
9
15
75
9
3.5
5
Most Pesshmestle
alme (D)
AR2R=an
12
26
10
11
arrow_forward
Q1: You have the following activities of a project and the time to complete each one (note that the time in weeks)
Required:
1 - Draw a network of project activities
2 - Determine the project implementation schedule.
3 - Calculate the completion time for the project implementation and the slack time for each activity.
Activity
Duration
Star
Finish
Slack
ES
LS
EF
LF
1-2
2
1-3
5
2-4
9
2-5
7
2-6
12
3-6
10
4-6
7
4-7
8
5-7
3
6-8
5
7-8
6
8-9
4
Q2: Draw the Network Diagram and determine the Critical Path and duration of the project (in days)
Activity
Duration
Predecessor(s)
A
2
-----
B
5
-----
C
9
A
D
7
A
E
12
A
F
10
B, C
G
7
D
H
8
E
I
3
F
J
5
H, G
K
6
I, J
L
4
H, G
M
3…
arrow_forward
Q1. Project Planning and Quality Management:
a) Develop a comprehensive project plan that includes the scope, objectives, timeline, and
resource requirements for the development and production of the product related to Central
Cable Berhad (CCB).
b) Identify key quality management principles that will be crucial in ensuring the product meets
industry standards and customer expectations.
c) Propose a quality control plan outlining methods, tools, and checkpoints to ensure the
consistent quality of the electric wires.
arrow_forward
1.Steps in Project Scope Management process
2. Define Scope Planning
3. Purpose of Scope Definition
arrow_forward
Q3.When we start a project how we know this project or program is feasible for our future? Explain with help of diagram
arrow_forward
Develop a project network.
Determine the expected project completion time.
What is the probability that the project completion time will be completed?
With in 2 weeks earlier than the expected project completion time?
With in 1.5 week more than the expected project completion time ?
arrow_forward
Hello. Can you assist with the following
Q.1.2. Using a suitable example for each, describe any three factors that could constrain a project.
Q.1.3. Using suitable examples, describe any two attributes of a project.
arrow_forward
Q3: Kuala Lumpur Hospital is renovating the emergency department to
accommodate more patients during the current pandemic "COVID-19". You have
engaged as the project manager for this project and divided the tasks into 11
activities.
ALL RIGHTS RESERVED
CONFIDENTIAL
2
CONFIDENTIALGUC/ JAN - APR / MPSM230
You are required to draw the Critical Path Method (CPI) and complete all the
necessary calculations to figure out the Slack Time.
No
Activity
Predecessor
Duration
1
A
0
2
B
3
3
C
1
4
D
2
5
E
2
6
F
4
7
G
2
8
H
4
9
J
1
10
K
2
11
L
0
BUUEFG
C
D, E
E, F
F, G
H
H
J, K
arrow_forward
Q1. Based on the table below, solve the questions (1-4).
Activity
Predecessor
Optimistic
Duration
Most Likely
Duration
4
Pessimistic
Duration
10
A
B
A
5.
8.
15
H.
B
1.
2
10
3.
12
4
B.
4
7.
6.
11
14
21
17
DE
6.
13
E.F
1. What is the probability that the project finishes in less than 40 days.
2. What is the probability that the Activity "G" finishes between 3 and 5 days.
3. Estimate project completion date with at least a 96. confidence level.
4. What is the probability that node "D" has a float more than Zero.
arrow_forward
i need the answer quickly
arrow_forward
SEE MORE QUESTIONS
Recommended textbooks for you
Principles Of Marketing
Marketing
ISBN:9780134492513
Author:Kotler, Philip, Armstrong, Gary (gary M.)
Publisher:Pearson Higher Education,
Marketing
Marketing
ISBN:9781259924040
Author:Roger A. Kerin, Steven W. Hartley
Publisher:McGraw-Hill Education
Foundations of Business (MindTap Course List)
Marketing
ISBN:9781337386920
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning
Marketing: An Introduction (13th Edition)
Marketing
ISBN:9780134149530
Author:Gary Armstrong, Philip Kotler
Publisher:PEARSON
Contemporary Marketing
Marketing
ISBN:9780357033777
Author:Louis E. Boone, David L. Kurtz
Publisher:Cengage Learning
Related Questions
- 5] 51 Ex-2/ Find the project's total duration and date of completion (assume the project start date is 1/12/2014). Use the following details to draw the A-O-A Network and build its Table: Activity BC E H. R. Duration 4 3 4. 5 6. (days) Following B,D,E C,FGF,G Activity H,I Rarrow_forwardQ1. Using a suitable example each, describe what the following project planning process activities involve: a. Establish project objective; b. Define scope; c. Create a Work Breakdown Structure (WBS); d. Estimate activity durations; e. Sequencing activities.arrow_forward1. Draw AOA network and Find the project duration.arrow_forward
- q6arrow_forwardQ2. The table below presents the information required in order to carry out a critical path analysis of an engineering project. a) Describe what is meant by the terms Scope and Functional Requirements with respect to project management. b) Complete a full forward and backwards pass analysis of the project and highlight the critical path. c) What is meant by the terms: critical path and float with respect to critical path analysis? Task Duration Dependency Plan (A) Hardware Design (B) Hardware Test (C) Software Design (D) Software Test (E) Complete Test (F) 6. A 2 4 A 1 2 C, Earrow_forward*(a.) Enter the above information into Microsoft Project (submit the Microsoft Project file).arrow_forward
- Fine-Carpets Ltd. reports the following free cash flows from its recent project: - 3,000,000 + 1,160,000 + 1,273,500 + 1,492,650 What is the project's NPV if the cost of its capital is 12%? Question 2Answer a. $113,379.48 b. $311,937.48 c. $131,379.48 d. $113,397.48 e. $113,973.48arrow_forwardi need the answer quicklyarrow_forwardQ2: Explain briefly the concept of "Project", what can it create, and what are the main examples of it ?arrow_forward
- Q1 ) Scenarios of a project activities (tables given below) and their required times to be completed in addition to their predecessors for developing a ‘Website’: Activity Description Duration (weeks) Preceding Activities A Determine user needs 8 -- B Review s/w and languages 4 -- C Purchase software 10 -- D Design format and style 10 B E Write programs 6 A F Review outcome product with user 12 C G Make revisions 4 C H Select server site 8 E I Install on server 14 D,F J Test 8 G,H,I Draw the path. Calculate the early finishing time (forwards calculations) Highlight the total time to complete the project (days) Calculate the late finishing time (backwards calculations) Calculate the slack time of the non-critical path activities Identify the critical path (highlight critical path activities) what would happen if activity D revised to take 14 instead of 10 days?arrow_forwardPractice Question EVM: A simple project consists of five tasks and is scheduled to take 13 weeks to complete. The actual status of the project at the end of week 9 is given in the following table: Project Plan Task | Duration Start (weeks) Actual status Actual current cost complete S350 S225 $475 $300 End Budget Percent week week $300 100% 100% $250 $450 $600 $500 B 2 100% 75% 75% C 4 4 7. 9. 13 D 3 6 8 $300 a) For each activity, compute the ACWP, BCWP, BCWS and add the columns to get the projected total. Record your answers in the table below. Task ACWP BCWP BCWS E b) Calculate: CV,SV,CPI, and SPI:arrow_forwardProject managementarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles Of MarketingMarketingISBN:9780134492513Author:Kotler, Philip, Armstrong, Gary (gary M.)Publisher:Pearson Higher Education,MarketingMarketingISBN:9781259924040Author:Roger A. Kerin, Steven W. HartleyPublisher:McGraw-Hill EducationFoundations of Business (MindTap Course List)MarketingISBN:9781337386920Author:William M. Pride, Robert J. Hughes, Jack R. KapoorPublisher:Cengage Learning
- Marketing: An Introduction (13th Edition)MarketingISBN:9780134149530Author:Gary Armstrong, Philip KotlerPublisher:PEARSONContemporary MarketingMarketingISBN:9780357033777Author:Louis E. Boone, David L. KurtzPublisher:Cengage Learning
Principles Of Marketing
Marketing
ISBN:9780134492513
Author:Kotler, Philip, Armstrong, Gary (gary M.)
Publisher:Pearson Higher Education,
Marketing
Marketing
ISBN:9781259924040
Author:Roger A. Kerin, Steven W. Hartley
Publisher:McGraw-Hill Education
Foundations of Business (MindTap Course List)
Marketing
ISBN:9781337386920
Author:William M. Pride, Robert J. Hughes, Jack R. Kapoor
Publisher:Cengage Learning
Marketing: An Introduction (13th Edition)
Marketing
ISBN:9780134149530
Author:Gary Armstrong, Philip Kotler
Publisher:PEARSON
Contemporary Marketing
Marketing
ISBN:9780357033777
Author:Louis E. Boone, David L. Kurtz
Publisher:Cengage Learning