Question
Chapter 2, Problem 1.1Q
Summary Introduction
Interpretation: The overall per crane productivity of the Port of Endover last week is to be calculated.
Concept Introduction: The per crane productivity is calculated by dividing the total fright container loaded or unloaded by the total number of cranes.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
a) Last week employees at Bluegill produced 46 chairs after working a total of 200hours. Of the 46 chairs produced, 12 were damaged due to a problem with thenew sanding machine. The damaged chairs can be discounted and sold for K250each. The undamaged chairs are sold to a department store retail chain for $700each.(i) What was the labor productivity ratio for last week? (ii) If labor productivity was $150 in sales per hour the previous week, whatwas the change in labor productivity as a percentage?b) In the bakery, the design capacity is 30 pies per day and effective capacity is 20pies per day. Currently, the bakery is producing 27 pies per day. What is thebakery’s capacity utilization relative to both design and effective capacity?
Suggest measurements of productivity which are often usedby operations managers in:a. Airline b. Bus c. Hotel
A fast-food restaurant serves hamburgers, cheeseburgers, and chicken sandwiches. The restaurant counts a cheeseburger as equivalent to 1.25 hamburgers and chicken sandwiches as 0.8 hamburger. Current employment is i ve full-time employees who each work a 40-hour week. If the restaurant sold 700 hamburgers, 900 cheeseburgers, and 500 chicken sandwiches in one week, what is its productivity? What would its productivity have been if it had sold the same number of sandwiches (2,100), but the mix was 700 of each type?
Chapter 2 Solutions
Practical Operations Management
Ch. 2 - Prob. 1DQCh. 2 - Prob. 2DQCh. 2 - Prob. 3DQCh. 2 - Prob. 4DQCh. 2 - Prob. 5DQCh. 2 - Prob. 1PCh. 2 - Prob. 2PCh. 2 - Prob. 3PCh. 2 - Prob. 4PCh. 2 - Prob. 5P
Ch. 2 - Prob. 6PCh. 2 - Prob. 7PCh. 2 - Prob. 8PCh. 2 - Prob. 9PCh. 2 - Prob. 10PCh. 2 - Prob. 11PCh. 2 - Prob. 12PCh. 2 - Prob. 13PCh. 2 - Prob. 14PCh. 2 - Prob. 15PCh. 2 - Prob. 16PCh. 2 - Prob. 17PCh. 2 - Prob. 18PCh. 2 - Prob. 19PCh. 2 - Prob. 20PCh. 2 - Prob. 21PCh. 2 - Prob. 22PCh. 2 - Prob. 23PCh. 2 - Prob. 1.1QCh. 2 - Prob. 1.2QCh. 2 - Prob. 1.3QCh. 2 - Prob. 2.1QCh. 2 - Prob. 2.2QCh. 2 - Prob. 2.3QCh. 2 - Prob. 3.1QCh. 2 - Prob. 3.2QCh. 2 - Prob. 3.3QCh. 2 - Prob. 3.4Q
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Susan Williams runs a small Flagstaff job shop where garments are made. The job shop employs eight workers. Each worker is paid $8 per hour. During the first week of March, each worker worked 45 hours. Together, they produced a batch of 156 garments. Of these garments, 54 were 'seconds' (meaning that they were flawed). The seconds were sold for $100 each at a factory outlet store. The remaining 102 garments were sold to retail outlets at a price of $198 per garment. What was the labor productivity, in dollars per labor-hour, at this job shop during the first week of March? Labor productivity =______ dollars/labor hour (round your response to two decimal places). Please don't just send the answer, I need to know how to do this. Thanksarrow_forwardMr. ichul is a Director of a pastry factory in Bandung. To produce 350 cakes per day it takes the following things Labor : 350 hours / day @ $5 / hourRaw Material : 2 ton / day @ $1 / kgEnergy : $2,000 / dayCapital Cost : $500 / day a. What is the labor productivity per labor-hour for cake production at the factory?b. What is the multifactor productivity for cake production at the factory?c. In order to meet the needs for Eid later, Mr. ichul wants to increase his production to500 more per day than the previous cake production without changing other variables, what is the productivity now?arrow_forwardIn December, General Motors produced 6,600 customized vans at its plant in Detroit. The labor productivity at this plant is known to have been 0.10 vans per labor-hour during that month. 300 laborers were employed at the plant that month. a. How many hours did the average laborer work that month? b. If productivity can be increased to 0.11 vans per labor-hour, how many hours would the average laborer work that month? Please show work. Thank youarrow_forward
- A catering company prepared and served 300 meals at an anniversary celebration last week usingeight workers. The week before, six workers prepared and served 240 meals at a wedding reception.a. For which event was the labor productivity higher? Explain.b. What are some possible reasons for the productivity differences?arrow_forwardThe following data was recorded last period for production department that under the management of Mr. Cobblepot. Budgeted labour hours = 2,700 hoursNumber of units of product X manufactured = 350 unitsNumber of units of product Y manufactured = 400 unitsStandard hours to produce one unit of X = 3 hoursStandard hours to produce one unit of Y = 4 hoursActual labour hours worked = 3,110 hours In order to measure the productivity of a labour , calculate the efficiency ratio ? show solutionarrow_forward“Partial productivity measures should be calculated only for high-value-added activities.” Do youagree and why or why not?arrow_forward
- Describe an operation in which higher quality comes at a higher cost. What does "efficiency" mean to you?arrow_forwardIn December, General Motors produced 6,600 customizedvans at its plant in Detroit. The labor productivity at thisplant is known to have been 0.10 vans per labor-hour during thatmonth. 300 laborers were employed at the plant that month.a) How many hours did the average laborer work that month?b) If productivity can be increased to 0.11 vans per laborhour,how many hours would the average laborer work thatmonth?arrow_forwardGeorge Kyparisis makes bowling balls in his Miamiplant. With recent increases in his costs, he has a newfound interestin efficiency. George is interested in determining the productivityof his organization. He would like to know if his organization is maintaining the manufacturing average of 3% increase in produc-tivity per year? He has the following data representing a month from last year and an equivalent month this year:arrow_forward
- The production line at Josie’s Sports completes 10 hats in an hour. The factory’s standard minute value to complete 1 hat is 5 minutes. What is the actual line productivity? Round your answer to the nearest whole number, but do not round until your final answer. Group of answer choices 82% 80% 81% 83%arrow_forwardApple computers are interested in measuring productivity of all Apple's products with respect to all inputs be calculated. Keeping in mind that Apple produces a wide range of electronic products, such as, phone, laptops, smart watches, etc with different inputs, the productivity measure calculated is an example of single factor productivity: Oa Truc Ob Falsearrow_forwardCompany tuca has 30000 rupees of output and it's human input is 5 percent of the total output, so calculate the human productivity of the firm ?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.