Question
Chapter 3, Problem 13P
(a)
Summary Introduction
Interpretation:
To design a p-chart showing upper and lower control limits.
Concept Introduction:
P-charts are used to identify the defective items, from a group of items. It is a form of control chart which is used to analyze the proportion of nonconforming units into a specified sample.
(b)
Summary Introduction
Interpretation:
Tax information process in statistical control.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The IRS is concerned with improving the accuracy of tax information given by its representatives over the telephone. Previous studies involved asking a set of 25 questions of a large number of IRS telephone representatives to determine the proportion of correct responses. Historically, the averageproportion of correct responses has been 72 percent. Recently, IRS representatives have been receiving more training. On April 26, the set of 25 tax questions were again asked of 20 randomly selected IRS telephone representatives. The numbers of correct answers were 18, 16, 19, 21, 20, 16,21, 16, 17, 10, 25, 18, 25, 16, 20, 15, 23, 19, 21, and 19. a. What are the upper and lower control limits for the appropriate p-chart for the IRS? Use z = 3. b. Is the tax information process in statistical control?
Designing an x -Chart Using the Process Standard DeviationThe Sunny Dale Bank monitors the time required to serve customers at the drive-through window because it is an important quality factor in competing with other banks in the city. After analyzing the data gathered in an extensive study of the window operation, bank management determined that the mean time to process a customer at the peak demand period is 5 minutes, with a standard deviation of 1.5 minutes. Management wants to monitor the mean time to process a customer by periodically using a sample size of six customers. Assume that the process variability is in statistical control. Design an x-chart that has a type I error of 5 percent. That is, set the control limits so that there is a 2.5 percent chance a sample result will fall below the LCL and a 2.5 percent chance that a sample result will fall above the UCL. After several weeks of sampling, two successive samples came in at 3.70 and 3.68 minutes, respectively. Is the…
com sells books, videos, DVDs, and CDs through its internet Web site. The company ships thousands of orders each day from seven national distribution centers. BooksCDs.com wants to monitor the quality of its distribution process, specifically the number of “problems” orders. A problem order is one that is delivered to a customer late (i.e., after five days), incorrect or incomplete. The company sampled 500 orders every other day for 20 samples and tracked them to final customer delivery. The results of which are as follows:
Sample
Numbers of Problems Orders
Sample
Numbers of Problems Orders
1
2
3
4
5
6
7
8
9
10
9
21
18
12
25
41
18
19
26
28
11
12
13
14
15
16
14
22
36
17
38
24
15
12
10
16
17
18
19
20
Construct an appropriate control chart for this process using 3-sigma limits and indicate if the process was out of control.
Show work, show how to do the computation
Chapter 3 Solutions
OPERATIONS MANAGEMENT LL PACKAGE
Ch. 3 - Should a very pricey handcrafted object of beauty...Ch. 3 - Prob. 2DQCh. 3 - Prob. 3DQCh. 3 - Prob. 1PCh. 3 - Prob. 2PCh. 3 - Prob. 3PCh. 3 - Prob. 4PCh. 3 - Prob. 5PCh. 3 - Prob. 6PCh. 3 - Prob. 7P
Ch. 3 - Prob. 8PCh. 3 - Prob. 9PCh. 3 - Prob. 10PCh. 3 - Prob. 11PCh. 3 - Prob. 12PCh. 3 - Prob. 13PCh. 3 - Prob. 14PCh. 3 - Prob. 15PCh. 3 - Prob. 16PCh. 3 - Prob. 17PCh. 3 - Prob. 18PCh. 3 - Prob. 19PCh. 3 - Prob. 20PCh. 3 - Prob. 21PCh. 3 - Prob. 22PCh. 3 - Prob. 23PCh. 3 - Prob. 24PCh. 3 - Prob. 26PCh. 3 - Prob. 27PCh. 3 - Prob. 28PCh. 3 - Prob. 29PCh. 3 - Prob. 31PCh. 3 - Prob. 1AMECh. 3 - Prob. 2AMECh. 3 - Prob. 3AMECh. 3 - Prob. 4AMECh. 3 - Prob. 5AMECh. 3 - Prob. 1VCCh. 3 - Prob. 2VCCh. 3 - Prob. 3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- At Gleditsia Triacanthos Company, a certain manufactured part is deemed acceptable if its length is between 12.45 to 12.55 inches. The process is normally distributed with an average of 12.49 inches and a standard deviation of 0.014 inches.arrow_forwardAt Gleditsia Triacanthos Company, a certain manufactured part is deemed acceptable if its lengthis between 12.45 to 12.55 inches. The process is normally distributed with an average of 12.49inches and a standard deviation of 0.014 inches. A) Is the process capable of meeting specifications? B) Does the process meet specifications?arrow_forwardAn automatic filling machine is used to fill 1-liter bottles of cola. The machine’s output is approximately normal with a mean of 1.0 liter and a standard deviation of .01 liter. Output is monitoredusing means of samples of 25 observations.a. Determine upper and lower control limits that will include roughly 97 percent of the samplemeans when the process is in control.b. Given these sample means: 1.005, 1.001, .998, 1.002, .995, and .999, is the process in control?arrow_forward
- The Scottsdale fire department aims to respond to fire calls in 7 minutes or less, on average. Response times are normally distributed with a standard deviation of 1 minute 42 seconds. Would a sample of 18 fire calls with a mean response time of 7 minutes 21 seconds provide sufficient evidence to show that the goal is not being met at α = .01?arrow_forwardBlueMoon Bottlers has a bottle-filling process with a mean value of 64 ounces and a standard deviation of 8 ounces. Suppose the upper and lower specification limits are 71 and 57 ounces, respectively. What is the process capability index of this process? (Note: You MUST show every single step and detailed derivation for full credit)arrow_forwardC-Spec, Inc., is attempting to determine whether an existing machine is capable of milling an engine part that has a key specification of 5 ± 0.006 inches. After a trial run on this machine, C-Spec has determined that the machine has a sample mean of 5.001 inches with a standard deviation of 0.005 inch. Calculate the Cpk for this machine. (Round your answer to 3 decimal places.)arrow_forward
- A Quality Analyst wants to construct a control chart for determining whether three machines, all producing the same product, are under control with regard to a particular quality variable. Accordingly, he sampled four units of output from each machine, with the following results : Machine #1 measurements [14, 13, 24, 22]; Machine #2 measurements [ 14, 19, 23, 14]; Machine #3 measurements [ 14, 16, 13, 16]. Using the factors for three sigma control limits, what are x-bar chart upper and lower control limits? a. 24.65and 9.013 b. 22.43and 11.24 c. 18.9and 14.76 d. 39.83and -6.167arrow_forwardThe mean of the sample mean will tend to be worse of an estimate, then a single samplearrow_forwardWhen plotting a process, with the intention of monitoring trends, which of the following apply? Select one: a. An increase in the mean and a decrease in variation is desirable b. A decrease in both the mean and variation is desirable c. The optimum mean may be lower or higher than current values d. The mean is not as important as the variationarrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.