Playtime Industries manufactures custom-designed playground equipment for schools and city parks. Playtime expected to incur $586,600 of manufacturing
Requirements
- 1. Calculate the manufacturing cost of Job 304.
- 2. How much will the City of Jonestown pay for this playground equipment?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The actual and planned data for Underwater University for the Fall term were as follows:
Actual
Planned
Enrollment
4,500
4,125
Tuition per credit hour
$120
$135
Credit hours
60,450
43,200
Registration, records, and marketing costs per enrolled student
$275
$275
Instructional costs per credit hour
$64
$60
Depreciation on classrooms and equipment
$825,600
$825,600
Registration, records, and marketing costs vary by the number of enrolled students, while instructional costs vary by the number of credit hours. Depreciation is a fixed cost.
Prepare a variable costing income statement showing the contribution margin and operating income for the Fall term.
Underwater University
Variable Costing Income Statement
For the Fall Term
Revenue
$
Variable costs:
Registration, records, and marketing costs
$
Instructional costs
Total variable costs
$
Contribution margin
$
Depreciation on classrooms and equipment
Operating income…
Average labor cost for the first 700 units of a product is RO 50 and the average labor cost of first 1400 units is RO 45. Average time per unit is 100 minutes. The learning ratio and the average labour cost for first 2800 units will be:
a.
80% and RO 36.000
b.
90% and RO 40.500
c.
85% and RO 38.250
d.
95% and RO 42.750
In an effort to raise the demand for reading tests, managers are planning to lower the price from $36 per test to $20 per test, the current price of the math test. They believe that doing so will increase the demand for reading tests to 60,000. Prepare a contribution format income statement reflecting Abado’s new pricing and demand structure.
Abado Profiles provides testing services to school districts that wish to assess students’ reading and mathematical abilities. Last year Abado evaluated 60,000 math tests and 20,000 reading tests. An income statement for last year follows.
Math Testing
Reading Testing
Total
Per Unit
Total
Per Unit
Total Company
Sales revenue
$1,200,000
$20
$720,000
$36
$1,920,000
Variable expenses
840,000
14
360,000
18
1,200,000
Contribution margin
$360,000
$6
$360,000
$18
720,000
Fixed expenses
360,000
Operating income
$360,000
Chapter 3 Solutions
ACCESS IN BB-ACC202
Ch. 3 - (Learning Objective 1) For which of the following...Ch. 3 - (Learning Objective 2) Which of the following...Ch. 3 - (Learning Objective 2) Which of the following...Ch. 3 - (Learning Objective 3) The amount of manufacturing...Ch. 3 - (Learning Objective 4) Which of the following is...Ch. 3 - (Learning Objective 5) Which of the following is...Ch. 3 - (Learning Objective 5) Assuming the amount of...Ch. 3 - Prob. 8QCCh. 3 - Prob. 9QCCh. 3 - Prob. 10QC
Ch. 3 - Identify product costs, period costs, and product...Ch. 3 - Decide on product costing system (Learning...Ch. 3 - Determine the flow of costs between inventory...Ch. 3 - Understanding key document terms in a job cost...Ch. 3 - Compute a professional billing rate (Learning...Ch. 3 - Prob. 3.6SECh. 3 - Continuation of S3-6: compute total allocated...Ch. 3 - Continuation of S3-7: determine over- or under...Ch. 3 - Prob. 3.9SECh. 3 - Calculate job cost and billing at appliance repair...Ch. 3 - Calculating overallocated or underallocated...Ch. 3 - Prob. 3.12SECh. 3 - Record manufacturing labor costs (Learning...Ch. 3 - Prob. 3.14SECh. 3 - Prob. 3.15SECh. 3 - Understanding key terms (Learning Objectives 1, 2,...Ch. 3 - Identify type of costing system (Learning...Ch. 3 - Prob. 3.18AECh. 3 - Determine the cost of a job and use it for pricing...Ch. 3 - Compute a predetermined overhead rate and...Ch. 3 - Prob. 3.21AECh. 3 - Prob. 3.22AECh. 3 - Determine the cost of a job (Learning Objectives...Ch. 3 - Compare bid prices under two different allocation...Ch. 3 - Analyze manufacturing overhead (Learning...Ch. 3 - Record manufacturing overhead (Learning Objectives...Ch. 3 - Record journal entries (Learning Objectives 2, 3,...Ch. 3 - Analyze T-accounts (Learning Objectives 2, 3, 5, ...Ch. 3 - Job cost and bid price at a consulting firm...Ch. 3 - Record journal entries (Learning Objectives 2, 3,...Ch. 3 - Identify type of costing system (Learning...Ch. 3 - Understand the flow of costs in a job cost shop...Ch. 3 - Prob. 3.33BECh. 3 - Prob. 3.34BECh. 3 - Prob. 3.35BECh. 3 - Sustainability and job costing (Learning...Ch. 3 - Determine the cost of a job (Learning Objectives...Ch. 3 - Compare bid prices under two different allocation...Ch. 3 - Analyze manufacturing overhead (Learning...Ch. 3 - Record manufacturing overhead (Learning Objectives...Ch. 3 - Record journal entries (Learning Objectives 2, 3,...Ch. 3 - Analyze T-accounts (Learning Objectives 2, 3, 5, ...Ch. 3 - Prob. 3.43BECh. 3 - Record journal entries (Learning Objectives 2, 3,...Ch. 3 - Analyze Manufacturing Overhead (Learning...Ch. 3 - Use job costing at an advertising agency (Learning...Ch. 3 - Use job costing at a consulting firm (Learning...Ch. 3 - Prepare job cost record (Learning Objectives 2, 3,...Ch. 3 - Determine and record job costs (Learning...Ch. 3 - Determine flow of costs through accounts (Learning...Ch. 3 - Analyze Manufacturing Overhead (Learning...Ch. 3 - Use job costing at an advertising agency (Learning...Ch. 3 - Use job costing at a consulting firm (Learning...Ch. 3 - Prepare job cost record (Learning Objectives 2, 3,...Ch. 3 - Determine and record job costs (Learning...Ch. 3 - Determine flow of costs through accounts (Learning...Ch. 3 - Job costing or process costing for wedding...Ch. 3 - Discussion Questions 1. Why would it be...Ch. 3 - Unwrapped or How Its Made Go to www.YouTube.com...Ch. 3 - Ethics involved with choice of cost driver...Ch. 3 - Prob. 3.61ACTCh. 3 - Issues with cost of job (Learning Objectives 2, 3,...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Bordner Company manufactures HVAC (heating, ventilation, and air conditioning) systems for commercial buildings. For each new design, Bordner faces a 90 percent learning rate. On average, the first unit of a new design takes 600 hours. Direct labor is paid 25 per hour. Required: 1. Set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, and cumulative total time in hours. Show results by row for total production of one unit, two units, four units, eight units, and sixteen units. (Round hour answers to two significant digits.) 2. What is the total labor cost if Bordner makes the following number of units: one, four, sixteen? What is the average cost per system for the following number of systems: one, four, or sixteen? (Round your answers to the nearest dollar.) 3. Using the logarithmic function, set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, cumulative total time in hours, and the time for the last unit. Show results by row for each of units one through eight. (Round answers to two significant digits.)arrow_forwardYour company has received an order for 20 units of aproduct. Th e labor cost to produce the item is $9.50 per hour. Th esetup cost for the item is $60 and material costs are $25 per unit. Th e item is sold for $92. Th e learning rate is 80 percent. Overheadis assessed at a rate of 55 percent of unit labor cost.(a) Determine the average unit cost for the 20 units if the fi rstunit takes four hours.(b) Determine the minimum number of units that need to bemade before the selling price meets or exceeds the averageunit cost.arrow_forwardFNG Paint (Pty) Ltd produces finger paint and sells them to pre‐schools. The following information relates to a set of finger paint. A set of finger paint is considered to be one unit. Direct labour needed for the first set of paint 4 hoursDirect labour costs per unit R30 per hourDirect material costs per unit R25Total Fixed costs R2 000Learning curve 80% Using the learning curve theory and information provided above, calculate the expected average cost for one set of paint should four and sixteen sets be produced, respectively. Round off to two decimal places.arrow_forward
- A professional division at a business school provides several development programs that have been tailored to the specific training needs of both the public and private sectors. The program director is planning to offer a one-full-day course in risk management to be sold at $2,250 plus orientation fee (5%) per participant. The division incurs a cost of $45,000 for promotion, classroom space, staff and instructor’s salary, as well as a cost of $240 per participant for refreshments, lunch, course material, a gift package, and a framed certificate of completion. How many participants need to register in the course for it to be worthwhile to offer it? Round to two decimal places. Group of answer choices 21.20 26.86 36.72arrow_forwardYou wish to take an Excel course. You may enroll at one within your school or you may take a community class at the local library. You've gathered the following information to aid in your decision-making process: Costs/Benefits College Course Community Course Cost $4,300 $1,190 Distance to course 0.20 miles (walking distance) 18 miles (driving distance) Timing of course Weekday Weekend Number of meetings 16 8 Qualitative considerations Convenience, quality of instruction Flexibility, brief duration Pretend transportation (gas, mileage, and parking) cost $220 per class session at the library. If you consider solely the cost - including transportation - of each alternative, which would you choose? Multiple Choice College course Community course Both alternatives Neither alternativearrow_forwardTo complete the first setup on a new machine took an employee 100 minutes. Using an 80% incremental unit-time learning model indicates that the second setup on the new machine is expected to take ________. Select one: a. 70 minutes b. 80 minutes c. 120 minutes d. 60 minutesarrow_forward
- Profit Planning and Control This case is a manufacturer and could make specialty bikes, ski or outdoor equipment, computers, food like chocolates, saltwater taffy, cookies, or donuts, etc. Create the balance sheet, income statement, and statement of the cash flow from the following information. Use the following information for the learning experiences Sales volume units = 11,000 Sales price/unit = $100 Variable manufacturing costs/unit = $60 Fixed manufacturing costs = $210,000 Fixed sales & administration costs = $190,000 Business income tax rate = 25% Current assets = $250,000 (Cash $50,000, Accounts Receivables $100,000, Inventory $100,000) Fixed assets = $750,000 Current liabilities = $200,000 (Accounts Payable $100,000, Short Term Debt $100,000) Long Term Debt = $300,000 Owners' Equity = $500,000arrow_forwardLearning curve, cumulative average-time learning model. Northern Defense manufactures radar systems. It has just completed the manufacture of its first newly designed system, RS-32. Manufacturing data for the RS-32 follow: Calculate the total variable costs of producing 2, 4, and 8 units.arrow_forwardTriad Children's Center (TCC), a non-profit organization, uses relevant cost analysis to determine whether new services are desirable. TCC is looking at adding a new educational program for grade school children who are having difficulty with their reading and math skills. The following relevant costs are expected if the program is accepted: Costs (per year) Program Director salary $ 39,000 Part-time Assistants $ 28,000 Variable cost per child $ 900 TCC estimates that a maximum of 40 children will participate in this program in the first year. If TCC decides to implement this program, funding will be received from the City Chamber of Commerce ($50,000) and a local Private University Endowment Fund ($35,000). Calculate the expected surplus or deficit from operations given the above information.arrow_forward
- P10-53B Determine transfer price at a manufacturer under various scenarios (Learning Objective 4) Assume the Small Components Division of Lang Manufacturing produces a video card used in the assembly of a variety of electronic products. The division's manufacturing costs, and variable selling expenses related to the video card are as follows: Cost per unit Direct materials $ 14.00 Direct labor $ 4.00 Variable manufacturing overhead $ 8.00 Fixed manufacturing overhead (at current production level) $ 9.00 Variable selling expenses $ 10.00 The Computer Division of Lang Manufacturing can use the video card produced by the Small Components Division and is interested in purchasing the video card in-house rather than buying it from an outside supplier. The Small Components Division has sufficient excess capacity with which to make the extra video cards. Because of competition, the market price for this video card is $30 regardless of whether the…arrow_forwardLearnCo manufactures and sells one product, an abacus for classroom use, with two models, the Basic model and the Deluxe model. The company began operations on January 1, 20Y1, and is planning for 20Y2, its second year of operations, by preparing budgets from its master budget. The company is trying to decide how many units to manufacture, how much it might spend on direct materials and direct labor, and what their factory overhead expenses might be. In addition, the company is interested in budgeting for selling and administrative costs, and in creating a budgeted income statement showing a prediction of net income for 20Y2. You have been asked to assist the controller of LearnCo in preparing the 20Y2 budgets. The sales budget often uses the prior year’s sales as a starting point, and then sales quantities are revised for various factors such as planned advertising and promotion, projected pricing changes, and expected industry and general economic conditions. LearnCo has…arrow_forwardNUBD Company is planning to introduce a new product with an 80 percent learning rate for production for batches of 1,000 units. The variable labor costs are P30 per unit for the first 1,000-unit batch. Each batch requires 100 hours. There are P10,000 in fixed costs not subject to learning. What is the cumulative total time (labor hours) to produce 16,000 units based on the cumulative average-time learning curve? A. 655.36 hours B. 256 hours C. 160 hours D. 409.6 hoursarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningManagerial Accounting: The Cornerstone of Busines...AccountingISBN:9781337115773Author:Maryanne M. Mowen, Don R. Hansen, Dan L. HeitgerPublisher:Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Managerial Accounting: The Cornerstone of Busines...
Accounting
ISBN:9781337115773
Author:Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:Cengage Learning
Inspection and Quality control in Manufacturing. What is quality inspection?; Author: Educationleaves;https://www.youtube.com/watch?v=Ey4MqC7Kp7g;License: Standard youtube license