Question
Chapter 4, Problem 51P
To determine
Calculate the difference in capitalized cost.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The capital investment cost for a switchgrass-fueled ethanol plant with a capacity of 250,000 gallons per year is $6 million. The cost-capacity factor for this particular plant technology is 0.59 for capacities ranging from 200,000 gallons per year to 500,000 gallons per year. What is the estimated capitalinvestment for a similar ethanol plant with a capacity of 450,000 gallons per year?
If alternative A has i * A = 10% and alternative B has i * B = 18% per year, what is known about the rate of return on the increment between A and B if the investment required in B is (a) larger than that required for A, and (b) smaller than that required for A?
Define the term capitalized cost and give a realworld example of something that might be analyzed using a capitalized cost evaluation technique.
Chapter 4 Solutions
Basics Of Engineering Economy
Ch. 4 - State two conditions under which the do-nothing...Ch. 4 - Prob. 2PCh. 4 - Prob. 3PCh. 4 - Prob. 4PCh. 4 - Prob. 5PCh. 4 - Prob. 6PCh. 4 - Prob. 7PCh. 4 - Prob. 8PCh. 4 - Prob. 9PCh. 4 - The costs associated with manufacturing a...
Ch. 4 - Prob. 11PCh. 4 - Prob. 12PCh. 4 - Prob. 13PCh. 4 - Prob. 14PCh. 4 - Prob. 15PCh. 4 - Prob. 16PCh. 4 - Prob. 17PCh. 4 - Prob. 18PCh. 4 - Prob. 19PCh. 4 - Prob. 20PCh. 4 - Prob. 21PCh. 4 - Prob. 22PCh. 4 - Prob. 23PCh. 4 - Prob. 24PCh. 4 - Prob. 25PCh. 4 - Prob. 26PCh. 4 - Prob. 27PCh. 4 - Prob. 28PCh. 4 - Prob. 29PCh. 4 - Prob. 30PCh. 4 - Prob. 31PCh. 4 - Two mutually exclusive projects have the estimated...Ch. 4 - Prob. 33PCh. 4 - Prob. 34PCh. 4 - Prob. 35PCh. 4 - Prob. 36PCh. 4 - Prob. 37PCh. 4 - The manager of engineering at the 900-megawatt...Ch. 4 - Prob. 39PCh. 4 - Prob. 40PCh. 4 - Prob. 41PCh. 4 - Three different plans were presented to the GAO by...Ch. 4 - The U.S. Army received two proposals for a turnkey...Ch. 4 - Prob. 44PCh. 4 - Prob. 45PCh. 4 - Prob. 46PCh. 4 - Prob. 47PCh. 4 - Prob. 48PCh. 4 - Prob. 49PCh. 4 - Prob. 50PCh. 4 - Prob. 51PCh. 4 - Prob. 52PCh. 4 - Prob. 53PCh. 4 - Prob. 54PCh. 4 - Prob. 55PCh. 4 - Prob. 56PCh. 4 - Prob. 57PCh. 4 - Prob. 58PCh. 4 - Prob. 59PCh. 4 - Prob. 60PCh. 4 - Prob. 61PCh. 4 - Prob. 62PCh. 4 - Prob. 63APQCh. 4 - Prob. 64APQCh. 4 - Prob. 65APQCh. 4 - Prob. 66APQCh. 4 - Prob. 67APQCh. 4 - Prob. 68APQCh. 4 - Prob. 69APQCh. 4 - Prob. 70APQCh. 4 - Prob. 71APQ
Knowledge Booster
Similar questions
- An engineer must decide between two ways to pump concrete to the top of a seven-story building. Plan 1 requires the leasing of equipment for $60,000 initially and will cost between $0.40 and $0.95 per metric ton to operate, with a most likely cost of $0.50 per metric ton. The pumper can pump 100 metric tons per 8-hour day. If leased, the asset will have a contract period of 5 years. Plan 2 is a rental option that will cost $17,000 per year. In addition, an extra $13.5 per hour labor cost will be incurred for operating the rented equipment per 8-hour day. Which plan should the engineer recommend if the equipment will be needed for 90 days per year? The MARR is 12% per year.arrow_forwardAn engineer must decide between two ways to pump concrete to the top of a seven-story building. Plan 1 requires the leasing of equipment for $60,000 initially and will cost between $0.40 and $0.95 per metric ton to operate, with a most likely cost of $0.50 per metric ton. The pumper can pump 100 metric tons per 8-hour day. If leased, the asset will have a contract period of 5 years. Plan 2 is a rental option that will cost $12,000 per year. In addition, an extra $17.5 per hour labor cost will be incurred for operating the rented equipment per 8-hour day. Which plan should the engineer recommend if the equipment will be needed for 55 days per year? The MARR is 11% per year. The annual worth of plan 1 lease optimistic is $ . The annual worth of plan 1 most likely is $_____ . The annual worth of plan 1 pessimistic is $___________ . The annual worth of plan 2 rental is $_________ .arrow_forwardPolymer Molding, Inc. is considering two processes for manufacturing storm drains. Plan A involves conventional injection molding that will require making a steel mold at a cost of $2 million. The cost for inspecting, maintaining, and cleaning the molds is expected to be $60,000 per year. Since the cost of materials for this plan is expected to be the same as for the other plan, this cost is not included in the comparison. The salvage value for plan A is expected to be 10% of the first cost. Plan B involves using an innovative process known as virtual engineered composites wherein a floating mold uses an operating system that constantly adjusts the water pressure around the mold and the chemicals entering the process. The first cost to tool the floating mold is only $795,000, but because of the newness of the process, personnel and product-reject costs are expected to be higher than for a conventional process. The company expects the operating costs to be $85,000 for the first year and…arrow_forward
- Because of international competition, a company that manufactures high-speed submersible rotary indexing spindles must upgrade its production equipment to reduce costs over a 6-year planning horizon. The company can invest $80,000 one year from now, 2 years from now, or 3 years from now. Depending on when the investment is made, the savings will vary. That is, the savings will be $20,000, 25,000, or $38,000 per year if the investment is made 1, 2, or 3 years from now, respectively. Will the timing of the investment affect the request to make at least 20% per year return? Use future worth analysis and solve using factors. Please provide excel formula.arrow_forwardBecause of international competition, a company that manufactures high-speed submersible rotary indexing spindles must upgrade its production equipment to reduce costs over a 6-year planning horizon. The company can invest $80,000 one year from now, 2 years from now, or 3 years from now. Depending on when the investment is made, the savings will vary. That is, the savings will be $29,000, 34,000, or $38,000 per year if the investment is made 1, 2, or 3 years from now, respectively. Will the timing of the investment affect the request to make at least 20% per year return? Use future worth analysis and solve using factors. (Click to select) No Yes , the timing of the investment (Click to select) will not will affect the request to make at least 20% per year return. The investment must be made in (Click to select) 3 2 1 years.arrow_forwardIn capital budgeting, when the present worth over the respective life of each project is used to select independent projects, all positive net cash flows are assumed to be: (a) Reinvested at the MARR through the end of the shortest-lived project (b) Reinvested at the internal rate of return of the project through the end of the longest-lived project (c) Reinvested at the MARR through the least common multiple of years of all of the projects (d) Reinvested at the MARR through the end of the longest-lived projectarrow_forward
- Six projects have been identified for possible implementation by a company that makes dry ice blasters, machines that propel tiny dry ice pellets at supersonic speeds so they flash freeze and then lift grime, paint, rust, mold, asphalt, and other contaminants off of in-place machines and a wide range of surfaces. The present worth of each project has been determined. Identify all acceptable mutually exclusive bundles if the budget limitation is $31,000. Project PW Project at 15%, $ L 29,000 M 11,000 N 41,000 O 35,000 P 6,000 Q 2,000arrow_forwardCopper and nickel electroless plating processes are under consideration for printed circuit boards. The copper process has fixed costs of $110,000 per year with a variable cost of $66 per batch. The nickel process has a fixed cost of $89,500 per year and a variable cost of $90 per batch. Determine the number of batches that must be produced each year in order for the processes to break even. The number of batches that must be produced each year in order for the processes to break even is batches.arrow_forwardSix projects have been identified for possible implementation by a company that makes dry ice blasters, machines that propel tiny dry ice pellets at supersonic speeds so they flash freeze and then lift grime, paint, rust, mold, asphalt, and other contaminants off in-place machines and a wide range of surfaces. The present worth of each project has been determined. Identify all acceptable mutually exclusive bundles if the budget limitation is $32,000. Arrange the acceptable bundles in such a way that the total PW values are in ascending order. Project Project PW at 15%, $ L 29,000 M 11,000 N 41,000 O 35,000 P 6,000 Q 2,000arrow_forward
- NPVs and IRRs for Mutually Exclusive Projects Davis Industries must choose between a gas-powered and an electric-powered forklift truck for moving materials in its factory. Because both forklifts perform the same function, the firm will choose only one. (They are mutually exclusive investments.) The electric-powered truck will cost more, but it will be less expensive to operate; it will cost $21,500, whereas the gas-powered truck will cost $17,960. The cost of capital that applies to both investments is 13%. The life for both types of truck is estimated to be 6 years, during which time the net cash flows for the electric-powered truck will be $6,860 per year, and those for the gas-powered truck will be $4,600 per year. Annual net cash flows include depreciation expenses. Calculate the NPV and IRR for each type of truck, and decide which to recommend. Do not round intermediate calculations. Round the monetary values to the nearest dollar and percentage values to two decimal places.…arrow_forwardThe AW values of three cost alternatives are $−23,000 for alternative A, $−21,600 for B, and $−27,300 for C. On the basis of these results, the decision is to: (a) select alternative A (b) select alternative B (c) select alternative C (d) select the Do Nothing alternativearrow_forwardAn engineer must decide between two ways to pump concrete to the top of a seven-story building. Plan 1 requires the leasing of equipment for $60,000 initially and will cost between $0.40 and $0.95 per metric ton to operate, with a most likely cost of $0.50 per metric ton. The pumper is able to deliver 100 metric tons per 8-hour day. If leased, the asset will have a contract period of 5 years. Plan 2 is rental option that will cost $15,000 per year. In addition, an extra $15 per hour labor cost will be incurred for operating the rented equipment per 8-hour day. Which plan should the engineer recommend if the equipment will be needed for 50 days per year? The MARR is 12% per year.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Principles of Economics (12th Edition)EconomicsISBN:9780134078779Author:Karl E. Case, Ray C. Fair, Sharon E. OsterPublisher:PEARSONEngineering Economy (17th Edition)EconomicsISBN:9780134870069Author:William G. Sullivan, Elin M. Wicks, C. Patrick KoellingPublisher:PEARSON
- Principles of Economics (MindTap Course List)EconomicsISBN:9781305585126Author:N. Gregory MankiwPublisher:Cengage LearningManagerial Economics: A Problem Solving ApproachEconomicsISBN:9781337106665Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike ShorPublisher:Cengage LearningManagerial Economics & Business Strategy (Mcgraw-...EconomicsISBN:9781259290619Author:Michael Baye, Jeff PrincePublisher:McGraw-Hill Education
Principles of Economics (12th Edition)
Economics
ISBN:9780134078779
Author:Karl E. Case, Ray C. Fair, Sharon E. Oster
Publisher:PEARSON
Engineering Economy (17th Edition)
Economics
ISBN:9780134870069
Author:William G. Sullivan, Elin M. Wicks, C. Patrick Koelling
Publisher:PEARSON
Principles of Economics (MindTap Course List)
Economics
ISBN:9781305585126
Author:N. Gregory Mankiw
Publisher:Cengage Learning
Managerial Economics: A Problem Solving Approach
Economics
ISBN:9781337106665
Author:Luke M. Froeb, Brian T. McCann, Michael R. Ward, Mike Shor
Publisher:Cengage Learning
Managerial Economics & Business Strategy (Mcgraw-...
Economics
ISBN:9781259290619
Author:Michael Baye, Jeff Prince
Publisher:McGraw-Hill Education