Textbook Question
Chapter 6, Problem 2P
A manager wants to assign tasks to workstations as efficiently as possible and achieve an hourly output of
a. In order of most following tasks Tiebreaker: greatest positional weight.
b. In order of greatest positional weight Tiebreaker: most following tasks.
c. What is the efficiency?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A manager wants to assign tasks to workstations as efficiently as possible and achieve an hourlyoutput of four units. The department uses a working time of 56 minutes per hour. Assign the tasksshown in the accompanying precedence diagram (times are in minutes) to workstations using thefollowing rules:a. In order of most following tasks. Tiebreaker: greatest positional weight.b. In order of greatest positional weight. Tiebreaker: most following tasks.c. What is the efficiency?
(a) What is the cycle time necessary to achieve the desired rate of production?(b) Using the longest element rule, create workstations to balance the line,attempting to get as close as possible to the theoretical minimum numberof workstations.(c) What is the efficiency and idle time of the line balance?(d) The company considers that if the lamps are successful with the publicit may need to increase production to 30,000 units. The company thinksthe simplest solution is to obtain two more production lines, thus havingtriple capacity. Another option is to re-balance the line. Considering thata single worker is assigned to a work station, determine which option(more production lines or re-balancing) yields the smallest labour size.
Use the information in the table below (image 1):
a. Construct the Precedence Diagram.
b.The productive operating time is 55 minutes per hour for an 8-hour work. Compute the cycle time, CT, needed to obtain 50 units per hour.
OT=_____
D= ________
CT= ____________
c. Determine the minimum number of workstation, Nmin.
d. Assign tasks to workstations using the longest task-time Use the table format below. (IMAGE 2)
e. Compute the Percentage Idle Time.
f. Compute the Efficiency of the line.
g. Draw the Balanced Line.
Chapter 6 Solutions
EBK OPERATIONS MANAGEMENT
Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.3 - FOXCONN SHIFTS ITS FOCUS TO AUTOMATION Foxconn...Ch. 6.3 - FOXCONN SHIFTS ITS FOCUS TO AUTOMATION Foxconn...Ch. 6.3 - Prob. 2.1RQCh. 6.3 - Prob. 2.2RQ
Ch. 6.3 - Prob. 3.1RQCh. 6.3 - Prob. 3.2RQCh. 6.5 - Prob. 1.1RQCh. 6.5 - Prob. 1.2RQCh. 6 - Explain the importance of process selection in...Ch. 6 - Briefly describe the five process types, and...Ch. 6 - Prob. 3DRQCh. 6 - Briefly describe computer-assisted approaches to...Ch. 6 - What is a flexible manufacturing system, and under...Ch. 6 - Prob. 6DRQCh. 6 - Why might the choice of equipment that provides...Ch. 6 - Prob. 8DRQCh. 6 - Prob. 9DRQCh. 6 - Briefly describe the two main layout types.Ch. 6 - Prob. 11DRQCh. 6 - Prob. 12DRQCh. 6 - What is the goal of Line balancing? What happens...Ch. 6 - Why are routing and scheduling continual problems...Ch. 6 - Prob. 15DRQCh. 6 - Prob. 16DRQCh. 6 - The City Transportation Planning Committee must...Ch. 6 - Identify the fixed-path and variable-path...Ch. 6 - Prob. 19DRQCh. 6 - Prob. 20DRQCh. 6 - Prob. 21DRQCh. 6 - Prob. 22DRQCh. 6 - What is cellular manufacturing? What are its main...Ch. 6 - Prob. 24DRQCh. 6 - Prob. 25DRQCh. 6 - Prob. 1TSCh. 6 - What trade-offs are involved when deciding how...Ch. 6 - Who needs to be involved in process selection?Ch. 6 - Prob. 4TSCh. 6 - Prob. 5TSCh. 6 - Prob. 1CTECh. 6 - Prob. 2CTECh. 6 - What are the risks of automating a production...Ch. 6 - Consider an assembly line such as the burrito...Ch. 6 - Prob. 1PCh. 6 - A manager wants to assign tasks to workstations as...Ch. 6 - A manager wants to assign tasks to workstations as...Ch. 6 - A producer of inkjet printer is planning to add a...Ch. 6 - As part of a major plant renovation project, the...Ch. 6 - Twelve tasks, with times and precedence...Ch. 6 - For the given set of tasks, do the following: a....Ch. 6 - A shop works a 400-minute day. The manager of the...Ch. 6 - Arrange six departments into a 2 3 grid so that...Ch. 6 - Using the information given in the preceding...Ch. 6 - Using the information in the following grid,...Ch. 6 - Arrange the eight departments shown in the...Ch. 6 - Arrange the departments so they satisfy the...Ch. 6 - a. Determine the placement of departments fix a...Ch. 6 - Prob. 15PCh. 6 - Develop a process layout that will minimize the...Ch. 6 - Prob. 17PCh. 6 - Rebalance the assembly line in Problem 7. This...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The following is a list of activities that must be completed in order to assemble a car. Draw the precedence diagram. Calculate the cycle time if there5 are 8 hours in a workday and 800 units desired per day. Balance the line using the longest operation time as a selection rule. Calculate the efficiency rating. How much overtime would be needed for an additional 20 units? Is this possible? Task Time Feasible TASK TIME PRECEDING Station Task Time Remaining Tasks TASK (Seconds) TASK A 16 ----- B 14 ----- C 22 ----- D…arrow_forwardGiven the following task, times, and sequence, develop a balanced line capable of operating with a I 0-minute cycle time at Dave Visser's company. a) Draw the precedence diagram.b) Assign tasks to the minimum feasible number of workstations according to the greatest time remaining (ranked positional weight) decision rule.c) What is the efficiency of the process?arrow_forwardA manager wants to assign tasks to workstations as efficiently as possible, and achieve an hourly output of 4 units. The department uses a working time of 56 minutes per hour. Assign the tasks shown in the accompanying precedence diagram (times are in minutes) to workstations using the following rules:arrow_forward
- What type of process—project, job shop, flow shop, and continuous flow—would most likely be used to produce the following? Explain your reasoning. Personal computers - Weddings- Paper-Continuous Paper Books- Tax preparation - What type of process – project, job shop, flow shop, and continuous flow – would most likely be used to produce the following? Gasoline- Air-conditioners - Specialized machine tools- Ships- Producing many flavors of ice cream-arrow_forwardThe Sail-Sea is a boat manufacturer. The assembly location is available for production of 60 boats for 240 minutes per day. Given the information in the table, a) Draw the precedence diagram b) Fins the minimum number of workstations needed to produce the required daily demand. c) What is the efficiency of the assembly line d) What is the idle time per boat produced e) Assign the tasks to workstations using the most follower method f) What is the maximum theoretical capacity this line can achieve in 240 minutesarrow_forwardA manager wants to assign tasks to workstations as efficiently as possible and achieve an hourly output of 331/3 units. Assume the shop works a 60-minute hour. Assign the tasks shown in the accompanying precedence diagram (times are in minutes) to workstations using the following rules: A. In order of most following tasks. Tiebreaker: greatest positional weight. Work Station Task I II III IV b. In order of greatest positional weight. Tiebreaker: most following tasks. Work Station Tasks I II III IV c. What is the efficiency? (Round your answer to 2 decimal places.) Efficiency _________%arrow_forward
- Gordon Miller's job shop has four work areas, A, B, C, and D. Distances in feet between centers of the work areas are: A B C D A − 4 10 8 B − − 5 9 C − − − 9 D − − − − Workpieces moved per week between work areas are: A B C D A − 900 700 600 B − − 400 300 C − − − 600 D − − − − It costs Gordon $3 to move 1 work piece 1 foot. The weekly total material handling cost of the layout =....... $nothing (enter your response as a whole number). The weekly total material handling cost of the layout =....... nothing dollars (enter your response as a whole number).arrow_forwardThe Sail-Sea is a boat manufacturer. The assembly location is available for production of 60 boats for240 minutes per day.Given the information in the table,c) What is the efficiency of the assembly lined) What is the idle time per boat producede) Assign the tasks to workstations using the most follower methodf) What is the maximum theoretical capacity this line can achieve in 240 minutes task performance time(min) task must follow task listed below a 1 - b 1 a c 2 a d 1 c e 3 c f 1 c g d, e, f h 2 b i 1 g, harrow_forwardA DIY product manufacturing company wishes to create a ‘product’ focused layout for the manufacture of their new cordless drill. There order book requires them to produce 480 drills per eight hour day. The assembly operations for the drill and the associated information are given in the table below. Therefore the key tasks are to: Management has decided to cut down 3 seconds from each operation (operation 1 - 8) to improve overall effectiveness. (a) calculate the maximum cycle time (b) calculate the minimum number of work stations (c) produce the precedence diagram (d) produce the line design which achieves the required cycle time (e) calculate balancing lossarrow_forward
- A Manager’s Woes Kyle Peschken has been a manager for the discount store Zelmart for the past two years. It’s time for his annual performance review, and Kyle would like to make a big impression on the corporate staff. Walking through the store, he makes a mental note of which departments need to be straightened, which ones need to be reorganized, and which employees he’d like to schedule during the week of his review. And then he sees it—blocking the aisles, creating commotion, and looking very unprofessional—the long line in the electronics department. It’s time to confront Chris, the sales clerk. “Chris, what’s the holdup here?” “I’mwaiting for a manager to approve this $120 check. And then I have to show this lady a digital camera from the display cabinet. She’s been waiting half an hour, and then . . . .” “Alright Chris . . . I can help out for a while . . .Two hours later, Kyle exited the electronics department disheartened. That’s no way for a store manager to spend his…arrow_forwardBalance the assembly line shown below for (a) a shift output of 60 pieces and (b) a shift output of 40 pieces. Assume an 8-hour shift, and use the rule: choose the assignable task with the longest processing time. Compute the line efficiency for each case. Fill in the table below for a shift output of 60 pieces. Break ties by choosing the lowest task number. If your answer is zero, enter "0". Round your answers to the nearest whole number. Workstation Tasks Total Time Idle Time 1 2 3 4 Total What is the assembly-line efficiency? Round your answer to one decimal place. % Fill in the table below for a shift output of 40 pieces. Break ties by choosing the lowest task number. If your answer is zero, enter "0". Round your answers to the nearest whole number. Workstation Tasks Total Time Idle Time 1 2 3 Total What is the assembly-line efficiency? Round your answer to one decimal place. %arrow_forwardThere is a canteen set up serving food (Breakfast, Lunch, Snacks-tea, and Dinner) to 500 students in a B school. It has a huge well-furnished dining hall and has a serving zone where students queue to pick up their eatables. The Institute director, during his regular Gemba walks in the canteen, has seen a lot of inefficiency in the related operational processes and needs a major improvement. (a)Provide one relatable and relevant example of five of the eight wastes under Lean systems which are likely to be witnessed in the canteen. (b)Recommend lean tools & techniques/system solutions to be employed for curbing each of those five wastes with a line on justification. (c) Suggest three key enablers and measures track the progress on lean in the canteen.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY