Consider an assembly line such as the burrito assembly line a Chipotle Mexican Grill. During slow times of the day, one server can handle assembly, but during very busy times, having many servers would be prudent. Explain why either approach wouldn’t work all the time, and the benefit of matching the number of servers to the pace of customer arrivals.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Consider an assembly line such as the burrito assembly line at Chipotle Mexican Grill. During slow times of the day, one server can handle assembly, but during very busy times, having many servers would be prudent. Explain why either approach wouldn’t work all the time, and the benefit ofmatching the number of servers to the pace of customer arrivals.
Positively Rivet Inc. is a small machine shop that produces sheet metal products. It had one line dedicated to the manufacture of light-duty vent hood shells, but because of strong demand it recently added a second line. The new line makes use of higher-capacity automated equipment but consists of the same basic four processes as the old line. In addition, the new line makes use of one machine per workstation, while the old line has parallel machines at the workstations. The processes, along with their machine rates, number of machines per station, and average times for a lone job to go through a station (i.e., not including queue time), are given for each line in the following table:
Process
Old Line
New Line
Rate per Machine
(parts/hour)
# Machines per Station
Time
(minute)
Rate per Machine
(parts/hour)
# Machines per Station
Time
(minute)
Punching
15
4
4.0
120
1
0.50
Braking
12
4
5.0
120
1
0.50
Assembly
20
2
3.0
125…
Use excel to show formulas
1. A company is designing a product layout for a new product. They plan to use this production line 16 hours a day in order to meet forecasted demand of 1200 units per day. For output to equal forecasted demand, what should be the actual cycle time for this production?
Chapter 6 Solutions
EBK OPERATIONS MANAGEMENT
Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.2 - MORTON SALT Introduction Morton Salt is a...Ch. 6.3 - FOXCONN SHIFTS ITS FOCUS TO AUTOMATION Foxconn...Ch. 6.3 - FOXCONN SHIFTS ITS FOCUS TO AUTOMATION Foxconn...Ch. 6.3 - Prob. 2.1RQCh. 6.3 - Prob. 2.2RQ
Ch. 6.3 - Prob. 3.1RQCh. 6.3 - Prob. 3.2RQCh. 6.5 - Prob. 1.1RQCh. 6.5 - Prob. 1.2RQCh. 6 - Explain the importance of process selection in...Ch. 6 - Briefly describe the five process types, and...Ch. 6 - Prob. 3DRQCh. 6 - Briefly describe computer-assisted approaches to...Ch. 6 - What is a flexible manufacturing system, and under...Ch. 6 - Prob. 6DRQCh. 6 - Why might the choice of equipment that provides...Ch. 6 - Prob. 8DRQCh. 6 - Prob. 9DRQCh. 6 - Briefly describe the two main layout types.Ch. 6 - Prob. 11DRQCh. 6 - Prob. 12DRQCh. 6 - What is the goal of Line balancing? What happens...Ch. 6 - Why are routing and scheduling continual problems...Ch. 6 - Prob. 15DRQCh. 6 - Prob. 16DRQCh. 6 - The City Transportation Planning Committee must...Ch. 6 - Identify the fixed-path and variable-path...Ch. 6 - Prob. 19DRQCh. 6 - Prob. 20DRQCh. 6 - Prob. 21DRQCh. 6 - Prob. 22DRQCh. 6 - What is cellular manufacturing? What are its main...Ch. 6 - Prob. 24DRQCh. 6 - Prob. 25DRQCh. 6 - Prob. 1TSCh. 6 - What trade-offs are involved when deciding how...Ch. 6 - Who needs to be involved in process selection?Ch. 6 - Prob. 4TSCh. 6 - Prob. 5TSCh. 6 - Prob. 1CTECh. 6 - Prob. 2CTECh. 6 - What are the risks of automating a production...Ch. 6 - Consider an assembly line such as the burrito...Ch. 6 - Prob. 1PCh. 6 - A manager wants to assign tasks to workstations as...Ch. 6 - A manager wants to assign tasks to workstations as...Ch. 6 - A producer of inkjet printer is planning to add a...Ch. 6 - As part of a major plant renovation project, the...Ch. 6 - Twelve tasks, with times and precedence...Ch. 6 - For the given set of tasks, do the following: a....Ch. 6 - A shop works a 400-minute day. The manager of the...Ch. 6 - Arrange six departments into a 2 3 grid so that...Ch. 6 - Using the information given in the preceding...Ch. 6 - Using the information in the following grid,...Ch. 6 - Arrange the eight departments shown in the...Ch. 6 - Arrange the departments so they satisfy the...Ch. 6 - a. Determine the placement of departments fix a...Ch. 6 - Prob. 15PCh. 6 - Develop a process layout that will minimize the...Ch. 6 - Prob. 17PCh. 6 - Rebalance the assembly line in Problem 7. This...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Mr. Aris Benn manages an assembly line that produces a piece of equipment that is used to clean floors. The process to produce this piece of equipment consists of 10 steps. Determine what other information is needed in order to balance this assembly line. Also, set up a numerical example of the line balancing problem at hand. Using this example, demonstrate how to balance the line and how to calculate its efficiency.arrow_forwardThe Morris Machine Company just received an order to refurbish five motors for materials handling equipment that were damaged in a fire. The motors have been delivered and are available for processing. The motors will be repaired at two workstations in the following manner. Workstation 1: Dismantle the motor and clean the parts. Workstation 2: Replace the parts as necessary, test the motor, and make adjustments. The customer’s shop will be inoperable until all the motors have been repaired, so the plant manager is interested in developing a schedule that minimizes the makespan and has authorized around-the-clock operations until the motors have been repaired. The estimated time to repair each motor is shown in the following table: TIME (HR) Motor Workstation 1 Workstation 2 M1 M2 M3 M4 M5 12 4 5 15 10 22 5 3 16 8arrow_forwardA small firm intends to increase the capacity of a bottleneck operation by adding a new machine.Two alternatives, A and B, have been identified, and the associated costs and revenues have beenestimated. Annual fixed costs would be $40,000 for A and $30,000 for B; variable costs per unitwould be $10 for A and $11 for B; and revenue per unit would be $15.b. At what volume of output would the two alternatives yield the same profit?arrow_forward
- Kiko Teddy Bear is a manufacturer of stuffed teddy bears. Kiko would like to be able to produce 40 teddy bears per hour on its assembly line. The following information will assist in answering the questions that follow: Task Information for Kiko Teddy Bear What is the maximum possible output of the line? What is the theoretical minimum number of workstations using the cycle time computed in” b “above Assign tasks to workstations using the cycle time in “b” above.arrow_forwardThere is a canteen set up serving food (Breakfast, Lunch, Snacks-tea, and Dinner) to 500 students in a B school. It has a huge well-furnished dining hall and has a serving zone where students queue to pick up their eatables. The Institute director, during his regular Gemba walks in the canteen, has seen a lot of inefficiency in the related operational processes and needs a major improvement. (a)Provide one relatable and relevant example of five of the eight wastes under Lean systems which are likely to be witnessed in the canteen. (b)Recommend lean tools & techniques/system solutions to be employed for curbing each of those five wastes with a line on justification. (c) Suggest three key enablers and measures track the progress on lean in the canteen.arrow_forwardThree departments- milling (M), drilling (D), andsawing (S)- are assigned to three work areas in Victor Berardis'smachine shop in Kent, Ohio. The number of workpieces movedper day and the distances between the centers of the work areas,in feet, follow. Pieces Moved between Work Areas Each Day lt costs $2 to move I workpiece I foot.What is the cost?arrow_forward
- The three-station work cell illustrated in the figure below has a product that must go through one of the two machines at station 1 (they are parallel) before proceeding to station 2. a) The bottleneck time of the system isminutes per unit (enter your response as a whole number). b) is the bottleneck station. c) The throughput time isminutes (enter your response as a whole number). d) If the firm operates 9 hours per day, 5 days per week, the weekly capacity of this work cell is units (enter your response as a whole number).arrow_forwardThe three-station work cell at Pullman Mfg., Inc. is illustrated in the figure below. It has two machines at station 1 in parallel (i.e., the product needs to go through only one of the two machines before proceeding to station 2). a) The throughput time isminutes (enter your response as a whole number). b) The bottleneck time of this work cell isminutes per unit (enter your response as a whole number) c) is the bottleneck station. If the firm operates 11 hours per day, 6 days per week, the weekly capacity of this work cell isunits (enter your response as a whole number).arrow_forwardA production line at V. J. Sugumaran’s machineshop has three stations. The first station can process a unit in10 minutes. The second station has two identical machines,each of which can process a unit in 12 minutes. (Each unitonly needs to be processed on one of the two machines.) Thethird station can process a unit in 8 minutes. Which station isthe bottleneck station?arrow_forward
- An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the totaltime for all tasks is 18 minutes. The line will operate for 450 minutes per day.a. What are the minimum and maximum cycle times?arrow_forwardMr. Aris Benn manages an assembly line that produces a piece of equipment that is used to clean floors. The process to produce this piece of equipment consists of 10 steps. 1. Determine what other information is needed in order to balance this assembly line. 2. set up a numerical example of the line balancing problem at hand. Using this example, demonstrate how to balance the line and how to calculate its efficiency.arrow_forwardIn a job shop, effective capacity is only 88 percent of design capacity, and actual output is 69 percent of effective output. What design capacity would be needed to achieve an actual output of 11 jobs per week? What is its effective capacity?a. The Design Capacity needed to achieve the required actual job outputs =( ) (round to whole number)b. The Effective Capacity needed to achieve the required actual job outputs =( ) (round to whole number)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY