As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows:
Do each of the following:
a. Draw the precedence diagram.
b. Determine the minimum cycle time, the maximum cycle time, and the calculated cycle time.
c. Determine the minimum number of stations needed.
d. Assign tasks to workstations on the basis of most following tasks. Use shortest processing time as a tiebreaker. If ties still exist, assume indifference in choice.
e. Compute the percentage of idle time for the assignment in part d.
Trending nowThis is a popular solution!
Chapter 6 Solutions
EBK OPERATIONS MANAGEMENT
- A manufacturing company is designing an assembly lineto produce its main product. Th e line should be able to produce60 units per hour. Th e following data in Table 10-16 give thenecessary information. (a) Which task is the bottleneck?(b) Draw a precedence diagram for the above information.(c) Compute the cycle time with a desired output of 60 unitsper hourarrow_forwardA manager wants to assign tasks to workstations as efficiently as possible and achieve an hourlyoutput of four units. The department uses a working time of 56 minutes per hour. Assign the tasksshown in the accompanying precedence diagram (times are in minutes) to workstations using thefollowing rules:a. In order of most following tasks. Tiebreaker: greatest positional weight.b. In order of greatest positional weight. Tiebreaker: most following tasks.c. What is the efficiency?arrow_forwardAs part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 250 units per 8-hour day. Task times and precedence relationships are as follows: Task Duration(minutes) ImmediatePredecessor a 0.5 - b 0.4 a c 0.5 b d 0.3 - e 1.8 d f 1.9 c g 2 e, f Do each of the following: a. Determine the number of followers for each task. (Please answer number of tasks following task for A-G)arrow_forward
- The City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: Code Description Time (hrs) Immediate Predecessor(s) A Find location; determine resource requirements 20 None B Requisition of lumber and sand 55 A C Dig and grade 100 A D Saw lumber into appropriate sizes 35 B E Position lumber in correct locations 25 D, C F Nail lumber together 5 E G Put sand in and under the equipment 20 F H Put dirt around the equipment 10 F I Put grass all over the garden, landscape, paint 35 G, H Refer to the legend LOADING... for the activity that corresponds to each code. Part 2 Using the line drawing tool, draw a…arrow_forwardAn assembly line is to operate eight hours per day with a desired output of 240 units perday. The following table contains information on this product’s task times and precedencerelationships: Task Task Time (Seconds) Immediate Predecessor A 60 — B 80 A C 20 A D 50 A E 90…arrow_forwardManagement wants to design an assembly line that will turn out 800 videotapes per day. There will be eight working hours in each day. The industrial engineering staff has assembled the information below: Task a Time (min. .2 .2 .4 .1 .3 .2 .1 .2 Immediate Predecessor none a none none c, d be none £ g (A) Determine the maximum and minimum cycle time. (B) Determine the optimum cycle time. (C) What is the minimum number of stations needed? (D) Draw the precedence diagram. (E) Assign tasks to stations in order of most following tasks first.arrow_forward
- For the given set of tasks, do the following:a. Develop the precedence diagram.b. Determine the minimum cycle time and then calculate the cycle time for a desired output of 500 units in a seven-hour day. Why might a manager use a cycle time of 50 seconds?c. Determine the minimum number of workstations for output of 500 units per day. Balance the line using the greatest positional weight heuristic. Break ties with the most following tasks heuristic. Use a cycle time of 50 seconds.e. Calculate the percentage idle time for the line.TaskTask Time(seconds)ImmediatePredecessorA 45 —B 11 AC 9 BD 50 —E 26 DF 11 EG 12 CH 10 CI 9 F, G, HJ 10 I193arrow_forwardThe City Commission of Nashville has decided to build a botanical garden and picnic area in the heart of the city for the recreation of its citizens. The precedence table for all the activities required to construct this area successfully is as follows: Code Description Time (hrs) Immediate Predecessor(s) A Find location; determine resource requirements 15 None B Requisition of lumber and sand 60 A C Dig and grade 100 A D Saw lumber into appropriate sizes 30 B E Position lumber in correct locations 20 D, C F Nail lumber together 5 E G Put sand in and under the equipment 25 F H Put dirt around the equipment 10 F I Put grass all over the garden, landscape, paint 35 G, H Refer to the legend Code Activity A Planning B Purchasing C Excavation D Sawing E…arrow_forwardAs part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows: Task Duration(minutes) ImmediatePredecessor a 0.2 - b 0.4 a c 0.2 b d 0.4 - e 1.2 d f 1.2 c g 1.0 e, f Click here for the Excel Data File Do each of the following: a. Determine the minimum cycle time, the maximum cycle time, and the calculated cycle time. (Round your answers to 1 decimal place.) b. Determine the minimum number of stations needed. (Round your answer to the next whole number.) c. Assign tasks to workstations on the basis of greatest number of following tasks. Use longest processing time as a tiebreaker. If ties still exist, assume indifference in choice. d. Compute the percentage of idle time for the assignment in part d. Use the actual bottleneck cycle time in your calculation.…arrow_forward
- A dress-making operation is being designed as an assemblyline. Table 10-22 shows the tasks that need to be performed, theirtask times, and preceding tasks. If the goal is to produce 30 dressesper hour, answer the questions that follow the table. (a) Compute the cycle time.(b) Which task is the bottleneck?(c) What is the maximum output for this line?(d) Compute the theoretical minimum number of stations.(e) Assign work elements to stations, using the longest tasktime rule.(f) Compute the effi ciency and balance delay of yourassignment.arrow_forwardThe desired daily output for an assembly line is 540 units. This assembly line will operate 720 minutes per day. The following table contains information on this product's task times and precedence relationships: TASK TASK TIME(SECONDS) IMMEDIATEPREDECESSOR A 35 — B 25 A C 35 A D 55 B E 5 B F 15 C G 30 E-D H 5 F-G b. What is the workstation cycle time? c. Balance this line using the largest number of following tasks. Use the longest task time as a secondary criterion. (Leave no cells blank - be certain to enter "0" wherever required.)arrow_forwardFrancis Johnson’s plant needs to design an efficient assembly line to make a new product. The assembly line needs to produce 15 units per hour, and there is room for only four workstations. The tasks and the order in which they must be performed are shown in the following table. Tasks cannot be split, and it would be too expensive to duplicate any task. TASK TASK TIME (MINUTES) IMMEDIATE PREDECESSOR A 1 — B 2 — C 3 — D 1 A, B, C E 3 C F 2 E G 3 E What is the workstation cycle time required to produce 15 units per hour? Note: Round your answer to 1 decimal place. Balance the line to use the fewest possible workstations to meet the cycle time found in part (b). Use whatever method you feel is appropriate. What is the efficiency of your line balance, assuming the line operates at the cycle time from part (b)? Note: Round your answer to 1 decimal place.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.