EBK OPERATIONS MANAGEMENT
EBK OPERATIONS MANAGEMENT
14th Edition
ISBN: 9781260718447
Author: Stevenson
Publisher: MCG COURSE
bartleby

Concept explainers

bartleby

Videos

Textbook Question
Book Icon
Chapter 6, Problem 6P

Twelve tasks, with times and precedence requirements as shown in the following table, are 10 be assigned to workstations using a cycle time of 1.5 minutes. Two heuristic rules will be tried: (1) greatest positional weight, and (2) most following tasks. In each case, the tiebreaker will be shortest processing time.

Chapter 6, Problem 6P, Twelve tasks, with times and precedence requirements as shown in the following table, are 10 be

a. Draw the precedence diagram for this line.

b. Assign tasks to stations under each of the two rules.

c. Compute the percentage of idle tune fox each rule.

Blurred answer
Students have asked these similar questions
The times required to complete each of eight jobs in a two-machine flow shop are shown in thetable that follows. Each job must follow the same sequence, beginning with machine A and moving to machine B.a. Determine a sequence that will minimize makespan time.b. Construct a chart of the resulting sequence, and find machine B’s idle time. c. For the sequence determined in part a, how much would machine B’s idle time be reduced bysplitting the last two jobs in half?TIME (hours)Job Machine A Machine Ba 16 5b 3 13c 9 6d 8 7e 2 14f 12 4g 18 14h 20 11
As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 250 units per 8-hour day. Task times and precedence relationships are as follows:   Task Duration(minutes) ImmediatePredecessor a 0.5 - b 0.4 a c 0.5 b d 0.3 - e 1.8 d f 1.9 c g 2 e, f       Do each of the following: a. Determine the number of followers for each task.    (Please answer number of tasks following task for A-G)
As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows:  Task Duration(minutes) ImmediatePredecessor a 0.2 - b 0.4 a c 0.2 b d 0.4 - e 1.2 d f 1.2 c g 1.0 e, f     Click here for the Excel Data File   Do each of the following: a. Determine the minimum cycle time, the maximum cycle time, and the calculated cycle time. (Round your answers to 1 decimal place.)        b. Determine the minimum number of stations needed. (Round your answer to the next whole number.)      c. Assign tasks to workstations on the basis of greatest number of following tasks. Use longest processing time as a tiebreaker. If ties still exist, assume indifference in choice.         d. Compute the percentage of idle time for the assignment in part d. Use the actual bottleneck cycle time in your calculation.…

Chapter 6 Solutions

EBK OPERATIONS MANAGEMENT

Ch. 6.3 - Prob. 3.1RQCh. 6.3 - Prob. 3.2RQCh. 6.5 - Prob. 1.1RQCh. 6.5 - Prob. 1.2RQCh. 6 - Explain the importance of process selection in...Ch. 6 - Briefly describe the five process types, and...Ch. 6 - Prob. 3DRQCh. 6 - Briefly describe computer-assisted approaches to...Ch. 6 - What is a flexible manufacturing system, and under...Ch. 6 - Prob. 6DRQCh. 6 - Why might the choice of equipment that provides...Ch. 6 - Prob. 8DRQCh. 6 - Prob. 9DRQCh. 6 - Briefly describe the two main layout types.Ch. 6 - Prob. 11DRQCh. 6 - Prob. 12DRQCh. 6 - What is the goal of Line balancing? What happens...Ch. 6 - Why are routing and scheduling continual problems...Ch. 6 - Prob. 15DRQCh. 6 - Prob. 16DRQCh. 6 - The City Transportation Planning Committee must...Ch. 6 - Identify the fixed-path and variable-path...Ch. 6 - Prob. 19DRQCh. 6 - Prob. 20DRQCh. 6 - Prob. 21DRQCh. 6 - Prob. 22DRQCh. 6 - What is cellular manufacturing? What are its main...Ch. 6 - Prob. 24DRQCh. 6 - Prob. 25DRQCh. 6 - Prob. 1TSCh. 6 - What trade-offs are involved when deciding how...Ch. 6 - Who needs to be involved in process selection?Ch. 6 - Prob. 4TSCh. 6 - Prob. 5TSCh. 6 - Prob. 1CTECh. 6 - Prob. 2CTECh. 6 - What are the risks of automating a production...Ch. 6 - Consider an assembly line such as the burrito...Ch. 6 - Prob. 1PCh. 6 - A manager wants to assign tasks to workstations as...Ch. 6 - A manager wants to assign tasks to workstations as...Ch. 6 - A producer of inkjet printer is planning to add a...Ch. 6 - As part of a major plant renovation project, the...Ch. 6 - Twelve tasks, with times and precedence...Ch. 6 - For the given set of tasks, do the following: a....Ch. 6 - A shop works a 400-minute day. The manager of the...Ch. 6 - Arrange six departments into a 2 3 grid so that...Ch. 6 - Using the information given in the preceding...Ch. 6 - Using the information in the following grid,...Ch. 6 - Arrange the eight departments shown in the...Ch. 6 - Arrange the departments so they satisfy the...Ch. 6 - a. Determine the placement of departments fix a...Ch. 6 - Prob. 15PCh. 6 - Develop a process layout that will minimize the...Ch. 6 - Prob. 17PCh. 6 - Rebalance the assembly line in Problem 7. This...
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY