Samuel Smith's company wants to establish an assembly line to manufacture its new product, the iStar phone. Samuel’s goal is to produce 60 iStars per hour. Tasks, task times, and immediate predecessors are as follows:
- a. What is the theoretical minimum for the number of workstations that Samuel can achieve in this assembly line?
- b. Use the most following tasks heuristic to balance an assembly line for the iStar phone.
- c. How many workstations are in your answer to (b)?
- d. What is the efficiency of your answer to (b)?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Sue Helms Appliances wants to establish an assembly line to manufacture its new product, the Micro Popcorn Popper. The goal is to produce five poppers per hour. The tasks, task times, and immediate predecessors for producing one Micro Popcorn Popper are as follows: a) What is the theoretical minimum for the smallest number of workstations that Helms can achieve in this assembly line?b) Graph the assembly line, and assign workers to workstations. Can you assign them with the theoretical minimum?c) What is the efficiency of your assignment?
About the product v process layouts, which statement(s) is correct?1. Process layout is more flexible, and therefore, it is only applicable to a service context.
2. Compared to a product layout, a process layout is located closer to "Project" in a product-process matrix.
3. Product layout is more efficient, and therefore, it is only applicable to a manufacturing context.
4. Compared to a process layout, a product layout is closer to a fixed-position layout in a product-process matrix.
5. None of the statements are correct
Note: You need to provide which statements are correct. It can be more than one.
Sue Helms Appliances wants to establish an assembly line to manufacture its new product, the Micro Popcorn Popper. The goal is to produce
five
poppers per hour. The tasks, task times, and immediate predecessors for producing one Micro Popcorn Popper are as follows:
Task
Performance Time (mins)
Task Must Follow Task Listed Below
A
8
−
B
11
A
C
10
A, B
D
9
B, C
E
8
C
F
4
D, E
A
C
F
B
E
D
In the diagram, there are 6 circles labeled using the letters from A to F. There are 8 of arrows, and each arrow connects one circle to another circle. The arrows are situated in the following manner: A to B, A to C, B to C, C to D, B to D, C to E, D to F, and E to F.
Part 2
a) The theoretical minimum number of
workstations=55
(round your response up to the…
Chapter 9 Solutions
OPERATIONS MGMT.(EBOOK)W/MYOMLAB>IC<
Ch. 9 - Prob. 1DQCh. 9 - Prob. 2DQCh. 9 - Prob. 3DQCh. 9 - Prob. 4DQCh. 9 - Prob. 5DQCh. 9 - Prob. 6DQCh. 9 - Prob. 7DQCh. 9 - Prob. 8DQCh. 9 - What are the requirements for a focused work...Ch. 9 - Prob. 10DQ
Ch. 9 - Prob. 11DQCh. 9 - Prob. 12DQCh. 9 - Prob. 13DQCh. 9 - Prob. 14DQCh. 9 - Prob. 15DQCh. 9 - Prob. 16DQCh. 9 - Explain the concept of cross-docking.Ch. 9 - What is a heuristic? Name several that can be used...Ch. 9 - Prob. 1PCh. 9 - Prob. 2PCh. 9 - Three departmentsmilling (M), drilling (D), and...Ch. 9 - Roy Creasey Enterprises, a machine shop, is...Ch. 9 - Prob. 5PCh. 9 - Prob. 6PCh. 9 - Prob. 7PCh. 9 - Prob. 8PCh. 9 - Six processes are to be laid out in six areas...Ch. 9 - After an extensive product analysis using group...Ch. 9 - Stanford Rosenberg Computing wants to establish an...Ch. 9 - Illinois Furniture, Inc., produces all types of...Ch. 9 - Sue Helms Appliances wants to establish an...Ch. 9 - The Action Toy Company has decided to manufacture...Ch. 9 - The following table details the tasks required for...Ch. 9 - Tailwind, Inc., produces high-quality but...Ch. 9 - Prob. 17PCh. 9 - Because of the expected high demand for Mach 10,...Ch. 9 - Prob. 19PCh. 9 - Suppose production requirements in Solved Problem...Ch. 9 - The preinduction physical examination given by the...Ch. 9 - Samuel Smith's company wants to establish an...Ch. 9 - As the Cottrell Bicycle Co. of St. Louis completes...Ch. 9 - Prob. 1CSCh. 9 - Prob. 2CSCh. 9 - Prob. 3CSCh. 9 - Prob. 4CSCh. 9 - Prob. 1.1VCCh. 9 - Prob. 1.2VCCh. 9 - Prob. 1.3VCCh. 9 - Prob. 1.4VCCh. 9 - Prob. 1.5VCCh. 9 - Prob. 2.1VCCh. 9 - Prob. 2.2VCCh. 9 - Prob. 2.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Discuss the advantages and disadvantages of using computer programs todevelop layouts.arrow_forwardFor the given set of tasks, do the following:a. Develop the precedence diagram.b. Determine the minimum cycle time and then calculate the cycle time for a desired output of 500 units in a seven-hour day. Why might a manager use a cycle time of 50 seconds?c. Determine the minimum number of workstations for output of 500 units per day. Balance the line using the greatest positional weight heuristic. Break ties with the most following tasks heuristic. Use a cycle time of 50 seconds.e. Calculate the percentage idle time for the line.TaskTask Time(seconds)ImmediatePredecessorA 45 —B 11 AC 9 BD 50 —E 26 DF 11 EG 12 CH 10 CI 9 F, G, HJ 10 I193arrow_forwardStanford Rosenberg Computing wants to establish anassembly line for producing a new product, the Personal DigitalAssistant (PDA). The tasks, task times, and immediate predecessorsfor the tasks are as follows: Rosenberg's goal is to produce 180 PDAs per hour.a) What is the cycle time?b) What is the theoretical minimum for the number of workstations that Rosenberg can achieve in this assembly line?c) Can the theoretical minimum actually be reached when workstations are assigned?arrow_forward
- As part of a major plant renovation project, the industrial engineering department has been askedto balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Tasktimes and precedence relationships are as follows: [ please refer the attachment for addl details ] Do each of the following:a. Draw the precedence diagram.b. Determine the minimum cycle time, the maximum cycle time, and the calculated cycle time.c. Determine the minimum number of stations needed.d. Assign tasks to workstations on the basis of most following tasks. Use shortest processing timeas a tiebreaker. If ties still exist, assume indifference in choice.e. Compute the percentage of idle time for the assignment in part d.arrow_forwardSmart Manufacturing's production engineers are reviewing the layout of their assembly line for their leading product. The line will operate eight hours a day with a desired output of 240 units per day. The following table contains information about this product's task times and precedence relationships: TASK Task Time (seconds) Immediate Precedent A 60 -- B 80 A C 20 A D 50 A E 90 B,C F 30 C,D G 30 E, F H 60 G Determine: a) Network of activities (precedence diagram) b) Cycle time c) The required number of workstations d) Evaluate the solution by the appropriate line balance heuristicarrow_forwardAn assembly line is to operate eight hours per day with a desired output of 240 units perday. The following table contains information on this product’s task times and precedencerelationships: Task Task Time (Seconds) Immediate Predecessor A 60 — B 80 A C 20 A D 50 A E 90…arrow_forward
- A company needs to rebalance a product layout for producing new plastic license plates. They plan to use the assembly line six hours in order to meet projected demand of 2,160 license plates each day. The following table describes the tasks involved in the production of this product: Without regard to projected demand, what is the maximum possible cycle time for this assembly line? Task Time (secs) Immediate Predecessor a 3 none b 4 none c 5 a,b d 7 none e 9 c,darrow_forward10. The following precedence network is used for assembling a product. You have been asked to achieve an output of 240 units per eight-hour day. All times in this network are in minutes. Balance the line using the following rule: assign tasks to workstations on the basis of most following tasks (Rule 1). Use greatest positional weight (Rule 2) as a tiebreaker. What is the first activity assigned to workstation 3? b c d f e aarrow_forwardUse the longest work element rule to balance the assembly line described in the following table and Figure so that it will produce 40 units per hour.a. What is the cycle time?b. What is the theoretical minimum number of workstations?c. Which work elements are assigned to each workstation?d. What are the resulting efficiency and balance delay percentages?e. Use the shortest work element rule to balance the assembly line. Do you note any changes in solution? Work Element Time (Sec) Immediate Predecessor(s) A B C D E F G H I J K 40 80 30 25 20 15 60 45 10 75 15 None A A B C B B D E,G F H,I,Jarrow_forward
- The process used for patient registration, consultation, blood test, X ray and other tests in a general hospital uses: Option- a. A continuous process layout b. A workcenter layout c. An assembly line layout d. A project layoutarrow_forwardWhat are the key factors that firms consider while designing a facility layout? List five major factors. What kind of layout is best suited for a Pharmaceuticals manufacturing firm?arrow_forwardThe desired daily output for an assembly line is 360 units. This assembly line will operate 450 minutes per day. The following table contains information on this product’s task times and precedence relationships: TASK TASK TIME (SECONDS) IMMEDIATE PREDECESSOR A 30 — B 35 A C 30 A D 35 B E 15 C F 65 C G 40 E, F H 25 D, G What is the required workstation cycle time to meet the desired output rate? Balance this line using the largest number of following tasks. Use the longest task time as a secondary criterion. Note: Leave no cells blank - be certain to enter "0" wherever required.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY