Interpretation:The sequence for the production of the ice-cream flavors for the minimization of the mean flow time for all flavors is to be determined.
Concept Introduction:
Shortest processing time rule is used for the minimization of mean time flow of the project and hence it is used to minimize the time of mean flow of a process.
Tardiness is used to calculate the difference between the actual completion time and the required due date of the job. Any tardy jobs get completed after the due date of the job.
(b)
Interpretation:The optimal sequence for the production of the ice-cream flavors for the minimization of the number of flavors late is to be determined.
Concept Introduction:
Shortest processing time rule is used for the minimization of mean time flow of the project and hence it is used to minimize the time of mean flow of a process.
Tardiness is used to calculate the difference between the actual completion time and the required due date of the job. Any tardy jobs get completed after the due date of the job.
Want to see the full answer?
Check out a sample textbook solutionChapter 9 Solutions
Production and Operations Analysis, Seventh Edition
- Four automobiles have entered Bubba’s Repair Shop for various types of work, ranging from a transmis-sion overhaul to a brake job. The experience level of the mechanics is quite varied, and Bubba would liketo minimize the time required to complete all of thejobs. He has estimated the time in minutes for eachmechanic to complete each job. Billy can completejob 1 in 400 minutes, job 2 in 90 minutes, job 3 in60 minutes, and job 4 in 120 minutes. Taylor willfinish job 1 in 650 minutes, job 2 in 120 minutes, job3 in 90 minutes, and job 4 in 180 minutes. Mark willfinish job 1 in 480 minutes, job 2 in 120 minutes, job3 in 80 minutes, and job 4 in 180 minutes. John willcomplete job 1 in 500 minutes, job 2 in 110 minutes,job 3 in 90 minutes, and job 4 in 150 minutes. Eachmechanic should be assigned to just one of these jobs.What is the minimum total time required to finish thefour jobs? Who should be assigned to each job?arrow_forwardChris has three different workstations: one for drip coffee, one for espresso drinks, and one to prepare food. During the morning rush, Chris has 5 people working: one person at the drip coffee station, two at the espresso station, and two at the food prep station. These employees are not cross-trained, and thus must stay at their station. On average, it takes the person at the drip coffee station 1 minute to make the coffee. On average, it takes one person working at the espresso station 3 minutes to make one espresso drink. On average, it takes one person working at the food station 4.5 minutes to prepare the food for one customer. The customer mix is as follows. 10% order just a drip coffee, 30% order a drip coffee and food, 35% order just an espresso drink, and 25% order an espresso drink plus food. A total of 40 customers/ hour frequent Chris'. What is the implied utilization at the espresso station? Provide your answer in decimal form, and round to 4 decimal places. (So, if your…arrow_forwardDan is a member of a four person sales team in a gourmet kitchen shop. All of the sales team members have been cross trained in the daily assignments that must be completed. Their first task each day is to restock shelves, clean and prepare the store for opening. Dan is often late to work, arriving just a few minutes before opening time. He is an excellent salesperson and loves to work with customers on the floor. He will often trade his cashiering shirt with another team member so that he can work with customers. His excellent sales record helps to ensure that his team always meets their sales goal. However, some of the team members are complaining that is not a good team player. How would you feel about working with Dan? b. What would you do it you were the store manager? Why?arrow_forward
- Baking dog treats in her kitchen has been a simple process for Emma to manage. She has two ovens, one sink, a refrigerator, and enough room for two people to work at the same time. However, when Emma moves her business out of her home, she will have a commercial kitchen that can accommodate as many as six people working simultaneously. She had never thought of her business as “production” until the real estate agent who showed her the space asked how many production workers she needs to accommodate. At that point, Emma realized she would be running a production system. Even worse, she realized that she had never even visited a manufacturing facility or set foot on a real production floor. How will she ever manage this process?arrow_forwardMorgan Manufacturing operates in an industry in which frequent changes in market conditions results in a hectic and volatile IT environment within the company. To keep abreast, Morgan’s system development team are engaged in a considerable level of new program development and application change activities. To efficiently manage the workload, the director of IT has combined the functions of systems development and program change into a single department. This allows programmers of new applications to also maintain those applications. To achieve cross training, programmers also maintain applications originally programmed by other IT personnel. This has resulted in an “open” library policy that allows programmers to access all programs stored in the SPL and download them to personal computers for maintenance. The immediate effect of this policy has been an increase in the work flow by reducing the startup time needed by programmers to become familiar with the systems being modified. It…arrow_forwardPosh Nails Katie Posh runs an upscale nail salon. The service process includes five activities that are conducted in the sequence described below. (The time required for each activity is shown in parentheses): Activity 1: Welcome a guest. (1 minute)Activity 2: Clip and file nails. (3 minutes)Activity 3: Paint. (5 minutes)Activity 4: Dry. (10 minutes)Activity 5: Check out the customer. (4 minutes)Three servers (S1, S2, and S3) offer the services in a worker-paced line. The assignment of tasks to servers is the following: S1 does Activity 1. S2 does Activities 2 and 3. S3 does Activities 4 and 5. The drying process does not require server 3’s constant attention; she/he needs to only escort the customer to the salon’s drying chair (equipped with fans for drying). The time to do this is negligible. There exists only one drying chair in the salon. Assume a wage rate of $12 per hour. What are the direct labor costs for one customer (in dollars)?arrow_forward
- Posh Nails Katie Posh runs an upscale nail salon. The service process includes five activities that are conducted in the sequence described below. (The time required for each activity is shown in parentheses): Activity 1: Welcome a guest. (1 minute)Activity 2: Clip and file nails. (3 minutes)Activity 3: Paint. (5 minutes)Activity 4: Dry. (10 minutes)Activity 5: Check out the customer. (4 minutes)Three servers (S1, S2, and S3) offer the services in a worker-paced line. The assignment of tasks to servers is the following: S1 does Activity 1. S2 does Activities 2 and 3. S3 does Activities 4 and 5. The drying process does not require server 3’s constant attention; she/he needs to only escort the customer to the salon’s drying chair (equipped with fans for drying). The time to do this is negligible. There exists only one drying chair in the salon. What is the average labor utilization of the servers (in decimal form)? Assume that there is unlimited demand and that the process only admits…arrow_forwardA garment manufacturing has already finishedgarments to iron/press in order to prepare for selling them in the market. There aretwo kinds of garments, namely: poloshirt and t-shirts. Poloshirt is to be sold atP200 per piece while t-shirt at P50 each. Ironing/pressing one piece of polotshirttakes 30 minutes while t-shirt takes 12 minutes. The owner of the garment factoryhas a total of 7 finishing workers, who each works 8 hours per day. Four (4) ofwhich are assigned as pressers and three (3) as packagers. For one day, theowner would like to maximize his profit.Using linear programming, determine how many pieces of poloshirts and howmany pieces of t-shirts should be sold in the market in day in order to maximizethe profit. In line with your answer on the number of pieces of poloshirts andnumber of pieces of t-shirts to be sold in the market, compute for the profit.Select the best answer from the choices enumerated below.You may use linear equations and/or inequalities to arrive at the…arrow_forwardJoe’s commercial laundry has contracts to wash bedsheets for hotels. Joe intakes each batch of sheets, which takes 1 minute, and then the sheets are washed, taking 20 minutes,and dried, taking 30 minutes. The batch of sheets is ironed, taking 10 minutes for one employee to complete each batch, and there are two employees ironing sheets. Finally, Joe packages the sheets and bills the customer, taking 2 minutes. Joe has five washing machines and seven dryers that can process one batch of sheets each. a. What is the capacity of the laundry system, and what is the bottleneck? b. What is the average throughput time of a batch of sheets? c. If the flow rate is 10 batches per hour, what is the average number of batches of sheets in the system (inventory)?arrow_forward
- Part A is processed on a MILLING machine; Part B is processed on a LATHE machine. Two parts (A and B) are then assembled on an ASSEMBLY machine. Standard times, scrap rates, efficiency, and availability of each machine and the assembly are given in the table below. Determine the number of milling (M), the lathe (L) and the assembly (A) machines needed to produce 100 good parts from this production system during and 8-hour (480 minutes) shift. (Note: Round up the number of parts processed on each station and then round up the number of machines needed).arrow_forwardThe Prime Manufacturing Company is a garment factory that employs about 1250 employees of varied skills. About 75 percent are women who are mostly in the production department. Men employees are assigned in the maintenance department and as operators of machines used in garment production. Women are mostly in the sewing department, packaging, and quality control. Mr. Duztin Fernando was hired to head the HR department. Prior to his assignment at Prime Manufacturing Company, Rod was in a construction firm, a medium-sized organization. His main concern was preparing the payroll and handling employees’ records. The Human Resource Department is composed of 5 employees, a payroll clerk, a personnel assistant, two supervisors, and Mr. Duztin Fernando as Manager. The record of Duztin Fernando in his academic achievements is quite satisfactory. His Bachelor’s degree is in the field of Engineering. Performance in the previous employment is quite satisfactory. The…arrow_forwardShow your step-by-step process using the SPECIAL PURPOSE LINEAR PROGRAMMING: ASSIGNMENT METHOD to solve this problem. Four Engineers are to work on 4 projects of Dora Company. The problem is to decide which engineer should be assigned to which project. Each engineer charges different fees on each project, due to distances of the projects and the complexity of the work. The cost of assigning particular engineers to particular projects are as stated below. The objective is to find the lease cost of assignment. Engineer 1 to Projects A, B, C, D = $11k, $8k, $10k, $7k respectively.Engineer 2 to Projects A, B, C, D = $6k, $5k, $3k, $8k respectively.Engineer 3 to Projects A, B, C, D = $4k, $8k, $10k, $9k respectively.Engineer 4 to Projects A, B, C, D = $11k, $10k, $5k, $7k respectively.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,