Production and Operations Analysis, Seventh Edition
7th Edition
ISBN: 9781478623069
Author: Steven Nahmias, Tava Lennon Olsen
Publisher: Waveland Press, Inc.
expand_more
expand_more
format_list_bulleted
Question
Chapter 11.6, Problem 13P
Summary Introduction
Interpretation: The predicted cost obtained from the first iteration is to be verified.
Concept Introduction:
Computerized Relative Allocation of Facilities Techniques (CRAFT) refers to the computerized tools used to improve the existing layout of the facilities.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
(a) What is the cycle time necessary to achieve the desired rate of production?(b) Using the longest element rule, create workstations to balance the line,attempting to get as close as possible to the theoretical minimum numberof workstations.(c) What is the efficiency and idle time of the line balance?(d) The company considers that if the lamps are successful with the publicit may need to increase production to 30,000 units. The company thinksthe simplest solution is to obtain two more production lines, thus havingtriple capacity. Another option is to re-balance the line. Considering thata single worker is assigned to a work station, determine which option(more production lines or re-balancing) yields the smallest labour size.
Use the longest work element rule to balance the assembly line described in the following table and Figure so that it will produce 40 units per hour.a. What is the cycle time?b. What is the theoretical minimum number of workstations?c. Which work elements are assigned to each workstation?d. What are the resulting efficiency and balance delay percentages?e. Use the shortest work element rule to balance the assembly line. Do you note any changes in solution?
Work Element
Time (Sec)
Immediate Predecessor(s)
A
B
C
D
E
F
G
H
I
J
K
40
80
30
25
20
15
60
45
10
75
15
None
A
A
B
C
B
B
D
E,G
F
H,I,J
The Build-Em-Fast Company has agreed to supply its best customer with three widgets during each of the next 3 weeks, even though producing them will require some overtime work. The relevant production data are as follows:
Week
Maximum Production,
Regular Time
Maximum Production,
Overtime
Production Cost per Unit,
Regular Time
1
2
2
$300
2
3
2
$500
3
1
2
$400
The cost per unit produced with overtime for each week is $100 more than for regular time. The cost of storage is $50 per unit for each week it is stored. There is already an inventory of two widgets on hand currently, but the company does not want to retain any widgets in inventory after the 3 weeks.
Management wants to know how many units should be produced in each week to minimize the total cost of meeting the delivery schedule.
Formulate this problem as a transportation problem by constructing the appropriate parameter table.
Chapter 11 Solutions
Production and Operations Analysis, Seventh Edition
Ch. 11.3 - Prob. 1PCh. 11.3 - Prob. 2PCh. 11.3 - Prob. 3PCh. 11.3 - Prob. 4PCh. 11.3 - Prob. 5PCh. 11.3 - Prob. 6PCh. 11.4 - Prob. 7PCh. 11.4 - Prob. 8PCh. 11.5 - Prob. 10PCh. 11.6 - Prob. 11P
Ch. 11.6 - Prob. 12PCh. 11.6 - Prob. 13PCh. 11.6 - Prob. 14PCh. 11.6 - Prob. 15PCh. 11.6 - Prob. 16PCh. 11.6 - Prob. 17PCh. 11.6 - Prob. 18PCh. 11.6 - Prob. 19PCh. 11.7 - Prob. 20PCh. 11.7 - Prob. 21PCh. 11.7 - Prob. 22PCh. 11.7 - Prob. 23PCh. 11.8 - Prob. 24PCh. 11.8 - Prob. 25PCh. 11.8 - Prob. 26PCh. 11.8 - Prob. 27PCh. 11.9 - Prob. 28PCh. 11.9 - Prob. 29PCh. 11.9 - Prob. 30PCh. 11.9 - Prob. 31PCh. 11.9 - Prob. 32PCh. 11.9 - Prob. 33PCh. 11.9 - Prob. 34PCh. 11.9 - Prob. 35PCh. 11.9 - Prob. 36PCh. 11.9 - Prob. 37PCh. 11.9 - Prob. 38PCh. 11.10 - Prob. 39PCh. 11.10 - Prob. 40PCh. 11.10 - Prob. 41PCh. 11.11 - Prob. 42PCh. 11.11 - Prob. 43PCh. 11.11 - Prob. 45PCh. 11 - Prob. 46APCh. 11 - Prob. 47APCh. 11 - Prob. 48APCh. 11 - Prob. 49APCh. 11 - Prob. 50APCh. 11 - Prob. 51APCh. 11 - Prob. 52APCh. 11 - Prob. 53APCh. 11 - Prob. 54APCh. 11 - Prob. 55APCh. 11 - Prob. 56APCh. 11 - Prob. 58AP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Job Costing Johnson Inc. is a job-order manufacturing company that uses a predetermined overhead ratebased on direct labor hours to apply overhead to individual jobs. For the current year, estimated direct laborhours are 95,000 and estimated factory overhead is $617,500. The following information is for Septemberof the current year. Job A was completed during September, and Job B was started but not finished.[LO 4-3, 4-4, 4-5]September 1, InventoriesMaterials Inventory $ 7,500Work-in-Process Inventory (All Job A) 31,200Finished Goods Inventory 67,000Material purchases 104,000Direct materials requisitionedJob A 65,000Job B 33,500Direct labor hoursJob A 4,200Job B 3,500Labor costs incurredDirect labor ($8.50/hour) 65,450Indirect labor 13,500Supervisory salaries 6,000Rental costsFactory 7,000Administrative offices 1,800Total equipment depreciation costsFactory 7,500Administrative offices 1,600Indirect materials used 12,000Required1. What is the total cost of Job A?2. What is the total…arrow_forwardSue Helms Appliances wants to establish an assem-bly line to manufacture its new product, the Micro Popcorn Popper. The goal is to produce five poppers per hour. The tasks,task times, and immediate predecessors for producing one MicroPopcorn Popper are as follows:TASK TIME (min) IMMEDIATEPREDECESSORSA 10 —B 12 AC 8 A, BD 6 B, CE 6 CF 6 D, Ea) What is the theoretical minimum for the smallest number ofworkstations that Helms can achieve in this assembly line?b) Graph the assembly line, and assign workers to workstations.Can you assign them with the theoretical minimum?c) What is the efficiency of your assignment?arrow_forwardThe design capacity for car workshop in a company is 110 cars per week. The effective capacity is 95 cars per week and the actual output for this week was 88 cars. If the utilization for next week is expected to be 70%, then the expected output is (...................) cars per week. Answer:arrow_forward
- Alocal toy manufacturer is using a production line that runs 8 hours per day and produces a toy that requires a total of 7 tasks to be performed. The daily demand is 100 toys. Times of the tasks are 2.73, 2.01 201 2.13, 2.0, 2.61, 2.71 , and 2.95 minutes for A,B,C,D,E,F, and respectively. However, due to the nature of the product there are precedence rules that must be observed. Such that Task Adoes not need any predecessorsB requires task A to completed. To start task C and task Deach require task B to be completed. Task C must be completed prior to stating task E. Task F needs both task D and task Eto be completed. Finally, task G can start only once task Fis completed.Given we apply the most remaining tasks rule for balancing the assembly line with ties broken according to longest task time firstthe tasks that will be assigned to the SECOND workstation arearrow_forwardPrint Item Equivalent Units of Production Data for the two departments of Kimble & Pierce Company for June of the current fiscal year are as follows: Drawing Department Winding Department Work in process, June 1 10,000 units, 38% completed 4,000 units, 35% completed Completed and transferred to next processing department during June 60,000 units 60,500 units Work in process, June 30 11,500 units, 70% completed 3,500 units, 60% completed Production begins in the Drawing Department and finishes in the Winding Department. a. If all direct materials are placed in process at the beginning of production, determine the direct materials and conversion equivalent units of production for June for the Drawing Department. If an amount is zero, enter in "0". Drawing Department Direct Materials and Conversion Equivalent Units of Production For June Whole Units Direct MaterialsEquivalent Units ConversionEquivalent Units Inventory in process, June 1 fill…arrow_forwardExplain the five step proceses that serves as the foundation of the theory of constraints ?arrow_forward
- WAI uses two resources for each product that it builds: directlabor and machine time. From historical records, WAI calculatesthe following planning factors:Direct labor for standard corkscrew is 0.20 hour.Direct labor for deluxe corkscrew is 0.50 hour.Machine time for standard corkscrew is 0.10 hour.Machine time for deluxe corkscrew is 0.30 hour.Calculate the capacity needed for the MPS developed in Problem 4arrow_forwardFrancis Johnson’s plant needs to design an efficient assembly line to make a new product. The assembly line needs to produce 15 units per hour, and there is room for only four workstations. The tasks and the order in which they must be performed are shown in the following table. Tasks cannot be split, and it would be too expensive to duplicate any task. TASK TASK TIME (MINUTES) IMMEDIATE PREDECESSOR A 1 — B 2 — C 3 — D 1 A, B, C E 3 C F 2 E G 3 E What is the workstation cycle time required to produce 15 units per hour? Note: Round your answer to 1 decimal place. Balance the line to use the fewest possible workstations to meet the cycle time found in part (b). Use whatever method you feel is appropriate. What is the efficiency of your line balance, assuming the line operates at the cycle time from part (b)? Note: Round your answer to 1 decimal place.arrow_forwardplease solve D only (a) What is the cycle time necessary to achieve the desired rate of production? =12min(b) Using the longest element rule, create workstations to balance the line,attempting to get as close as possible to the theoretical minimum numberof workstations.(c) What is the efficiency and idle time of the line balance? =72.22%(d) The company considers that if the lamps are successful with the publicit may need to increase production to 30,000 units. The company thinksthe simplest solution is to obtain two more production lines, thus havingtriple capacity. Another option is to re-balance the line. Considering thata single worker is assigned to a work station, determine which option(more production lines or re-balancing) yields the smallest labour size.arrow_forward
- Describe the five step proceses that serves as the foundation of the theory of constraints ?arrow_forwardThe effective capacity and efficiency for the next quarter at MMU Mfg. in Waco, Texas, for each of three departments are shown: Compute the expected production for next quarter for each department.arrow_forwardAs the Operations Manager of Shane Manufacturing Ltd., you are given the task to balance the assembly line that is used to produce a special type of toy. b. Draw the precedence diagram for the problem that you set up in part “a” above. c. Use the example that you set up to demonstrate how you will balance the line. d. Calculate the efficiency of the line.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Process selection and facility layout; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=wjxS79880MM;License: Standard YouTube License, CC-BY