Chris received new word processing software for her birthday. She also received a check, with which she intends to purchase a new computer. Chris’s college instructor assigned a paper due next week. Chris decided that she will prepare the paper on the new computer. She made a list of the activities she will need to do and their estimated times.
a. Arrange the activities into two logical sequences.
b. (1) Construct an AOA network diagram.
(2) Construct an AON diagram.
c. Determine the critical path and the expected duration time.
d. PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu. Printing is for personal, private use only. No part of this book may be reproduced or transmitted without publisher's prior permission. Violators will be prosecuted.
What are some possible reasons for the project to take longer than the expected duration?
Trending nowThis is a popular solution!
Chapter 17 Solutions
EBK OPERATIONS MANAGEMENT
- Four Squares Productions, a firm hired to coordinate the release of the movie Pirates of the Caribbean: On Stranger Tides (starring Johnny Depp), identified 16 activities to be completed before the release of the film. The appropriate data are shown in the following table: Time (weeks) Immediate Time (weeks) Immediate Activity a m b Predecessor(s) Activity a m b Predecessor(s) A 1.0 2.0 4.0 — I 10.5 13.0 14.0 C B 2.0 3.5 6.0 — J 2.0 4.0 6.0 C C 10.0 12.0 14.0 — K 2.0 4.0 6.0 D D 4.0 5.0 7.0 — L 3.0 5.0 7.0 E E 2.0 4.0…arrow_forwardPower Builders Inc. is planning for an upcoming job with a large client. They have listed the specific activities and steps to be performed, and estimated the time to complete each activity. The activities involved in the job are listed below: Activity Description of Activity Preceding Activity Estimated Time Required (in weeks) A B C D E F G H I J K Planning Meeting Obtain Permit Inspect Damage Begin Repair Work Order Additional Materials Apply for Waiver Obtain Waiver Complete Electrical Work Build Interior Partitions Onsite Testing Meet With Client -- A B A D E C, F D H G, I J 5 2 5 4 2 4 2 5 5 2 2 REQUIRED: Prepare a Gantt Chart from the facts in this time budget.arrow_forwardActivity on Arrows : Questions1. Organize the information above in an activity precedence table.2. Draw an Activity-On-Arrow (AOA) network diagram representing information shown onthe activity precedence table.3. Show all different paths and their durationsarrow_forward
- Activity time estimates for a production line design & implementation project at the CBA factory are as follows: Activity Time (in days) Immediate predecessors A 60 --- B 72 --- C 50 A D 60 B, C E 45 B, C F 77 D G 40 E, F Find early start, early finish, late start, and late finish times for every activity.arrow_forwarda) Prepare the Activity Node Diagram and identify the Critical Path b) Prepare Gantt ChartThanksarrow_forwardA toy manufacturing company is in the process of designing and subsequently launching a new toy. The process consists of seven activities with predecessor activity relationships and activity time estimates as follows: Activity Description Predecessor activity Duration (Weeks) A Design prototype - 2 B Build prototype A 3 C Order parts B 2 D Prepare for production B 4 E Prepare for marketing B 5 F Assembly and testing C, D 2 G Launch E, F 1 a. Draw the critical path diagram b. Determine the early start, early finish, late start, and late finish times c. Show critical path and determine its duration d. Determine the slack for each activityarrow_forward
- Humber Web Design Co. is organizing a new project to increase efficiency and improve relations with their clients. The project manager for this initiative has broken the project up into several parts as follows: Activity Activity Description Immediate Predecessor Activity time (days) A Identify Client Base ― 33 B Develop Client Prospectus ― 21 C Perform Design Analysis ― 35 D Program Back End A, B, C 47 E Program Front End A 13 F Project Consolidation D, E 11 (a) For the given project, fill in the nodes of the network diagram below. A E 33 13 Start B D F Finish Time 21 47 11 Time C 35 (b) Using the network diagram, fill in the table. Make sure that you put the values in the appropriate columns. Activity Earliest Start (ES) Latest…arrow_forwarda) What is the completion time of the project? b) Draw the resource loading graph. c) Try to level the resource loading as possible.arrow_forwardDraw the PDM network diagram for the following project, calculate the earliest and latest starting and finishing times for all activities, and hence calculate the total float, free float for each activity. Activity IPA Duration (WEEKS) WORKERS REQUIRED PER WEEK EQUIPMENT REQUIRED (hrs/WEEK) H ---- 10 5 8 I H 8 4 2 J H 6 8 6 K J 4 2 1 L J 2 6 2 M J 4 3 2 N I 4 2 0 O I 5 5 0 P I, J 5 6 6 Q L 5 2 0 R M 5 0 4 S N 3 0 4 T Q 3 0 0 U O, S 1 9 8 V K, R 5 14 8 W U 2 6 8 X V 3 6 8 Y P,W,X,T 8 14 8 Z Y 6 5 8 If there is a limit of 15 workers per week, smooth the workers loading using ES and LS histogram. Based on the proposed scheduling, plot the equipment loading histogram for the project. Independently of the above resource leveling, schedule the…arrow_forward
- The conditions and pert times for constructing a network diagram are given below.-Creation conditions:(0-1) It is the initial activity.(1-2) and (1-3) Activities begin together.It follows activity (2-4) (1-2), activity (3-4) (1-3), and ends together.( 4-5 ) It is the last activity. a-Create the network diagram.b-Calculate the critical path and show it on the diagram.c- If the expiry time is extended by 15 days, how much will the probability of expiry increase?arrow_forwardActivity Description of Activity Preceding Activity Estimated Time Required (in weeks) A B C D E F G H I J K Planning Meeting Obtain Permit Inspect Damage Begin Repair Work Order Additional Materials Apply for Waiver Obtain Waiver Complete Electrical Work Build Interior Partitions Onsite Testing Meet With Client -- A B A D E C, F D H G, I J 5 2 5 4 2 4 2 5 5 2 2 Use the time budget provided in the question to complete the following requirements. REQUIRED: a) Prepare a PERT network diagram to aid the coordination of the activities. Calculation of earliest and latest times for each activity is not required. Save the diagram as a pdf and attach it using the link below the answer box. b) Identify the critical path for completing the electrical job. c) Power Builders Inc. would like to finish the job one week earlier than indicated by the schedule, and as a result, they are considering several alternatives. One such…arrow_forward2.1. Construct an Activity-On-Node (AON) Network Diagram for the HR Departments’system upgrade project. 2.2. Calculate the duration of all possible paths on the network diagram.2.3. Identify the critical path and project duration2.4. Briefly explain the meaning of merge activities. From the network diagram identify themerge activities.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.