EBK OPERATIONS MANAGEMENT
14th Edition
ISBN: 9781260718447
Author: Stevenson
Publisher: MCG COURSE
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 17, Problem 13P
Here is a list of activity times for a project as well as crashing costs for its activities. Determine which activities should be crashed and the total cost of crashing if the goal is to shorten the project by three weeks as cheaply as possible. First construct a network diagram. You can use either an AOA or an AON (see Solved Problem 5).
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
I need a detailed explanation and assistance to solve the this problem:
A company decides to plan a project, with activities, precedences and deterministic durations given in the following table:
Activity
i
Duration
(days)
Immediate
Predecessors
A
32
none
B
21
none
C
30
none
D
45
A
E
26
A, B
F
28
C
G
20
E, F
a) What method should be used? Using only one pseudo-activity, draw the project network, with arcs labeled by the activity name and duration.
b) Compute and display in a table the earliest and latest starting and finishing times, as well as slack, for each activity, and identify the critical path(s).
C) Draw a Gantt chart of the schedule, based on earliest starting times
d) Which activities must be completed by day 60 to ensure that the project is not delayed?
Office Automation, has developed a proposal for introducing a new computerized office system that will improve word processing and interoffice communications for a particular company. Contained in the proposal is a list of activities that must be ac- accomplished to complete the new office-system project. Information about the activities is shown below where times are in weeks and costs are in thousands of dollars.
NOTE: The crashing cost given in the last (seventh) column of the table below is the total cost to finish an activity by its minimum time given in the fifth column.
Draw the Network Diagram based off the table of dependencies
Draw the critical path using the following activity notation.
Identify the critical part and explain the project duration
Which activity or activities duration can be reduced to reduce the overall project duration?
Based on you answer of sub question (d) draw the new critical path.
What is the critical path and project duration? Explain your answer.
Chapter 17 Solutions
EBK OPERATIONS MANAGEMENT
Ch. 17.3 - Will the AI technology render project managers...Ch. 17.3 - Prob. 1.2RQCh. 17 - A project manager may need two skill setsthose of...Ch. 17 - Explain the term project champion and list some...Ch. 17 - List the steps in risk management.Ch. 17 - Give some examples of ethical issues that may...Ch. 17 - What are the key advantages of using project...Ch. 17 - What is a work breakdown structure, and how is it...Ch. 17 - Identify the term being described for each of the...Ch. 17 - List the main advantages of PERT. List the main...
Ch. 17 - Why might a probabilistic estimate of a projects...Ch. 17 - Define each of these terms, and indicate how each...Ch. 17 - Why might a person wish to be involved with a...Ch. 17 - Prob. 12DRQCh. 17 - What are some aspects of the project managers job...Ch. 17 - What is the main benefit of a project organization...Ch. 17 - What trade-offs are associated with time and cost...Ch. 17 - Who needs to be involved in assessing the cost of...Ch. 17 - Prob. 3TSCh. 17 - Project management techniques have been used...Ch. 17 - Give three examples of unethical conduct involving...Ch. 17 - For each of the following network diagrams,...Ch. 17 - Chris received new word processing software for...Ch. 17 - Prepare a Gantt chart for each of the following in...Ch. 17 - a. Develop a list of activities and their...Ch. 17 - For each of the problems listed, determine the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Three recent college graduates have formed a...Ch. 17 - The new director of special events at a large...Ch. 17 - Prob. 9PCh. 17 - The project described in the following table is...Ch. 17 - The following precedence diagram reflects three...Ch. 17 - A project manager has compiled a list of major...Ch. 17 - Here is a list of activity times for a project as...Ch. 17 - The project manager of a task force planning the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Chucks Custom Boats (CCB) builds luxury yachts to...Ch. 17 - Prob. 17PCh. 17 - Create a risk matrix in the style of Figure 17.13...Ch. 17 - Create a risk matrix for this project: Explain...Ch. 17 - B. Smitty Smith is a project manager for a large...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- You may need to use the appropriate technology to answer this question. Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 43-week completion date requested by the owner. The Mueller project manager prepared the following project network. A project network with 10 activities and 14 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B, to activity C, and to activity D. Activity B is connected to activity F. Activity C is connected to activity E and to activity F. Activity D is connected to activity E. Activity E is connected to activity G and to activity Finish. Activity F is connected to activity G and to activity H. Activity G is connected to activity H. Activity H is connected to activity Finish. Activity Finish has no arcs directed to other activities. Estimates of the optimistic, most…arrow_forwardYou may need to use the appropriate technology to answer this question. Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 43-week completion date requested by the owner. The Mueller project manager prepared the following project network. A project network with 10 activities and 14 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B, to activity C, and to activity D. Activity B is connected to activity F. Activity C is connected to activity E and to activity F. Activity D is connected to activity E. Activity E is connected to activity G and to activity Finish. Activity F is connected to activity G and to activity H. Activity G is connected to activity H. Activity H is connected to activity Finish. Activity Finish has no arcs directed to other activities. Estimates of the optimistic, most…arrow_forwardThere are four critical paths in a network. A-B-C-D-E, A-F-G-E, A-H-J-K-L-E and A-S-T-E. Each activity in this network can be crashed by 100 hours. The maximum possible reduction in the project duration will be: a. Insufficient information b. 1300 hours c. 500 hours d. 400 hours e. 600 hourarrow_forward
- In the space provided below create the network diagram that shows the relationship (logic) of project activities shown below and then number each event. 1. In a given project activities "A, B and C are initial activities that may begin at the same time 2. -----"D" cannot begin until "A" is complete. 3. ----- "B" must be complete before E can begin. 4. ----- "F" cannot start until "C" is finished. 5. ----- "G" cannot begin until "B" is finished. 6. ----- "G" and "D" must be done before "H" can begin. 7. ----- "I" cannot begin until "B" is finished. 8. ----- "J" can begin only after "F" and "I" are complete. 9. ----- Once "E" is complete, "K" can begin. 10. ---- The project will be finished when "H" "J" and "K" are complete.arrow_forwardThe required data for a small project consisting of different activities are given below: a) Draw the network diagram for the project and find the normal and minimum project lengthb) If the project is to be completed in 21 days with minimum crash cost which activities should be crashed to how many days? Please explain how you made the project network.arrow_forwardIdentify at least four (4) critical issues that the project management team faced in executing, monitoring, and controlling project work while constructing a bridge and discuss the strategies used to effectively manage these issues. issues could be for example schedule delay, cost issue, insufficient resources , cost overhead etc Please give detail imformation in response this is a project management coursearrow_forward
- You may need to use the appropriate technology to answer this question. Use the following network with activities and times estimated in days to answer the questions. A project network with 13 activities and 17 directed arcs is shown. Activity Start is connected to activity A, to activity B, and to activity C. Activity A is connected to activity D, to activity E, and to activity F. Activity B is connected to activity F. Activity C is connected to activity G and to activity H. Activity D is connected to activity K. Activity E is connected to activity I. Activity F is connected to activity I. Activity G is connected to activity I. Activity H is connected to activity J. Activity I is connected to activity K. Activity J is connected to activity K. Activity K is connected to activity Finish. Activity Finish has no arcs directed to other activities. Activity Optimistic Most Probable Pessimistic A 2 5 6 B 1 3 7 C 5 6 9 D 5 12 14 E 3 4 5 F 9 10 13 G 4 6 8 H 3 6 8 I 5 7 12 J 11 12 13 K 1 3 4…arrow_forwardUse the Program Evaluation and Review Technique to represent the project in an activity network. In conjunction with the Critical Path Method, use the activity network to find the shortest time possible to complete the project, to identify the critical jobs in the project, and to determine the earliest and latest that each activity can start and finish without making the project completion longer.a=1, b=1, c=6, d=5, e=2, f=5; andab=1x1=1, bc=1x6=6, cd=6x5=30, de=5x2=10, ef=2x5=10, af=1x5=5.arrow_forwardwhat is the critical path in project management. Please write to critacal path for this diagram.arrow_forward
- The activities necessary for the completion of a project are listed in the table below (Time in weeks). You are asked to complete the project 1 week ahead of time. You should crash Activity ________. This will incur an additional cost of $_________ .arrow_forwardConsider the following activities for a project. Answer the questions below. a. Assume the durations given are high confidence, create a network chart (don’t considerresources yet), and identify the critical path. What is the duration of the project? b. You aren’t quite ready to apply the critical chain project management yet, but you do want toeliminate multi-tasking. Eliminate any resource contention in your network. Identify the criticalpath now? What is the duration of the project? c. Apply the critical chain project management approach to this project. Create a new view ofyour project network, include a project buffer and any needed feeding buffers. What is the criticalchain? What is the duration of the project now?arrow_forwardGiven the following project: Activity Predecessor Normal Time (day) Normal Cost ($) Crash Time (day) Crash Cost ($) A - 4 800 2 1300 B - 10 1200 7 2400 C A 6 1100 4 1700 D A,B 7 1000 4 1600 E C 10 2000 8 3000 F C,D 5 900 - - (a) Draw the network and find the critical path duration of the project, total cost of project using normal times. (b) Calculate the maximum time reduction and crash cost-per-day (all activities may be partially crashed) for each activity. Then fill the table below. (Note: Activity “F” cannot be crashed) Activity Maximum Time Reduction (day) Cost to Crash per Period ($/day) A B C D E F (c) Find the optimal way of getting a 20-day delivery time. What is the project cost? (d) Find the optimal way of getting a 18-day delivery time. What is the project cost?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY