Textbook Question
Chapter 17, Problem 16P
Chuck’s Custom Boats (CCB) builds luxury yachts to customer order. CCB has landed a contract with a mysterious New York lawyer (Mr. T). Relevant data are shown on the next page. The complication is that Mr. T wants delivery in 32 weeks or he will impose a penalty of $375 for each week his yacht is late. Note: No activity can be crashed more than two weeks.
Develop a crashing
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The project manager of a task force planning the construction of a domed stadium had hopedto be able to complete construction prior to the start of the next college football season. Afterreviewing construction time estimates, it now appears that a certain amount of crashing will beneeded to ensure project completion before the season opener. Given the following time and costestimates, determine a minimum-cost crashing schedule that will shave five weeks off the projectlength. Note: No activity can be crashed more than two weeks.CRASHING COSTS ($000)Activity Immediate Predecessor Normal Time (weeks) First Week Second WeekA — 12 $15 $20B A 14 10 10C — 10 5 5D C 17 20 21E C 18 16 18F C 12 12 15G D 15 24 24H E 8 — —I F 7 30 —J I 12 25 25K B 9 10 10M G 3 — —N H 11 40 —P H, J 8 20 20End K, M, N, P
The Peabody Coal Corporation recently completed the final feasibility report for a new general ledger accounting system. It has hired a consulting firm to program and install the new system. The consulting firm is charging $350,000 for the remaining tasks to be performed. These tasks are to be performed over the next 10 months as detailed in the Gantt chart in the diagram. The consulting firm is extremely concerned with the project staying on schedule because it is receiving a flat fee. The release of the final payment is contingent upon the system performing as stated in the contract and upon Peabody receiving appropriate documentation of the system.Requireda. Prepare a PERT diagram and indicate the critical path.b. What happens to the time frame of the implementation of the project if the manufacturer is 4 weeks late shipping the hardware?c. What happens if the data conversion does not go smoothly and takes an additional 3 weeks? d. Who should conduct the postimplementation review?…
A competitor of Kozar International, Inc. has begun marketing a new instant-developing film project. Kozar has had a similar product under study in its R&D department but has not yet been able to begin production. Because of the competitor's action, top managers have asked for a speedup of R&D activities so that Kozar can produce and market instant film at the earliest possible date. The predecessor information and activity time estimates in months are shown in the following columns.
Immediate
Optimistic
Most Probable
Pessimistic
Activity
Predecessor(s)
Time
Time
Time
A
—
3.5
5
6.5
B
A
1.5
3
4.5
C
A
2
4
6
D
B, C
3.5
4.5
8.5
E
B
1
3
5
F
C, D
7.5
8.5
12.5
G
E, F
6
8
10
Compute expected times and variances for each activity. Round your answers for the expected times to nearest whole number and for the variances to two decimal places.
Activity
Mean
Variance
A
B
C
D
E
F
G…
Chapter 17 Solutions
EBK OPERATIONS MANAGEMENT
Ch. 17.3 - Will the AI technology render project managers...Ch. 17.3 - Prob. 1.2RQCh. 17 - A project manager may need two skill setsthose of...Ch. 17 - Explain the term project champion and list some...Ch. 17 - List the steps in risk management.Ch. 17 - Give some examples of ethical issues that may...Ch. 17 - What are the key advantages of using project...Ch. 17 - What is a work breakdown structure, and how is it...Ch. 17 - Identify the term being described for each of the...Ch. 17 - List the main advantages of PERT. List the main...
Ch. 17 - Why might a probabilistic estimate of a projects...Ch. 17 - Define each of these terms, and indicate how each...Ch. 17 - Why might a person wish to be involved with a...Ch. 17 - Prob. 12DRQCh. 17 - What are some aspects of the project managers job...Ch. 17 - What is the main benefit of a project organization...Ch. 17 - What trade-offs are associated with time and cost...Ch. 17 - Who needs to be involved in assessing the cost of...Ch. 17 - Prob. 3TSCh. 17 - Project management techniques have been used...Ch. 17 - Give three examples of unethical conduct involving...Ch. 17 - For each of the following network diagrams,...Ch. 17 - Chris received new word processing software for...Ch. 17 - Prepare a Gantt chart for each of the following in...Ch. 17 - a. Develop a list of activities and their...Ch. 17 - For each of the problems listed, determine the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Three recent college graduates have formed a...Ch. 17 - The new director of special events at a large...Ch. 17 - Prob. 9PCh. 17 - The project described in the following table is...Ch. 17 - The following precedence diagram reflects three...Ch. 17 - A project manager has compiled a list of major...Ch. 17 - Here is a list of activity times for a project as...Ch. 17 - The project manager of a task force planning the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Chucks Custom Boats (CCB) builds luxury yachts to...Ch. 17 - Prob. 17PCh. 17 - Create a risk matrix in the style of Figure 17.13...Ch. 17 - Create a risk matrix for this project: Explain...Ch. 17 - B. Smitty Smith is a project manager for a large...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Image of Diagram included Using the diagram, find: The critical path. How long it will take to complete the project? How does simulation determine the probabilities of various project completion times? What is "slack" and why is it important? Why is activity-on-arrow (AOA) or activity-on-node (AON) of significant value to the project manager? How is the uncertainty in project scheduling dealt with? Should the critical path activities be managed differently from noncritical path activities? Explain.arrow_forwardDave is the project manager for a construction project that is building agazebo. When the project first started, he met with the stakeholders to definethe scope. The sponsors mentioned that the gazebo is a really important partof their daughter’s wedding ceremony that was planned for 7 months fromthen. In fact, they said that if the gazebo couldn’t be completed in 7 months, itwouldn’t be worth it for them to even start the project. Dave wrote down the7-month deadline to put in his Project Scope Statement. In which section ofthe document did the deadline appear?”A. Project ConstraintsB. Project DeliverablesC. Project ObjectivesD. Project Assumptions Which of the following is a “hygiene factor” under Herzberg’s Motivation-Hygiene Theory?A. Recognition for excellent workB. Self-actualizationC. Clean clothingD. Good relations with coworkers and managersarrow_forwardHi, I need help answering the last question. Rob Smith is managing a small project at Boston University. He is under pressure to shorten the overall duration of the project by 4 weeks and he wants to do so at the lowest cost possible. In order to meet this objective a number of activities must be crashed. Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s) A 5 3 $800 $1,200 - B 6 5 $300 $450 - C 6 5 $550 $775 - D 3 2 $750 $950 A E 6 3 $1,350 $2,250 C F 5 3 $675 $875 B What is the total cost of crashing the project 4 weeks (just the additional cost, not total project cost)? (Display your answer to two decimal places.)arrow_forward
- Explain how finding the customer requirements relates to the business goals in the project charter.arrow_forwardYou are the project manager of the software installationproject in Table 7.12. You would like to find the minimum-costschedule for your project. There is a $1,000-per-week penaltyfor each week the project is delayed beyond week 25. In addi-tion, your project team determined that indirect project costsare $2,500 per week.a. What would be your target completion week?b. How much would you save in total project costs with yourschedule?arrow_forwardSwimming Pool Installation: You are the project manager working for Mack's Pool Co. Your project consists of installing a new swimming pool at the local country club before Memorial Day weekend (pool opening weekend). You would like to find the minimum cost schedule for your project. There is a $9,000 per week penalty for each week the project is delayed beyond week 9. In addition, your project team determined that indirect costs are $15,000 per week. ACTIVITY Immediate Predecessor (s) NORMAL TIME (NT) CRASH TIME (CT) Normal Cost (NC) Crash Cost (CC) A -- 2 1 7,000 10,000 B -- 2 2 3,000 3,000 C A 3 1 12,000 40,000 D B 3 2 12,000 28,000 E C 1 1 8,000 8,000 F D, E 5 3 5,000 15,000 G E 3 2 9,000 18,000 Before crashing, the project duration is _________ week(s). The total cost of the project if we do nothing is $ __________ (round to the nearest dollar). The minimum cost…arrow_forward
- Table contains information about an environmental cleanup project in the township of Hiles. Shorten the project three weeks by finding the minimum-cost schedule. Assume that project indirect costs and penalty costs are negligible. Identify activities to crash while minimizing the additional crash costs.arrow_forwardCompany A has a project that will scheduled on March 15, 2021, so the Operation department prepared all the materials needed in the project and they found out that some of the materials and equipment are not in the storage room, so they contacted the supplier (BC Company) to purchase the missing materials needed to conduct the project. So they issue the purchase order to BC and agreed that they will provide and deliver the materials needed on same day March 15, 2021. But on that day, BC company didn’t comply to deliver the materials and equipment. So what is your Approach if you were the Company A?arrow_forwardFarihah is a project manager for a systems development project involving a new database application for her organization’s human resources department. Despite Farihah’s best efforts at estimating the time requirements for the project, the team has missed the deadline for completing the Analysis Phase and producing the System Proposal. Farihah had estimated during her 6-week Planning Phase that Analysis would require 2 months, but the team finished the System Proposal 2 weeks behind their planned target date. Based on her discussions with the team members, Farihah believes that the system is more complex than she originally thought. Should Farihah adjust her timeline, or can she try to make up for the lost two weeks? Farihah needs your advice.arrow_forward
- Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a). Develop a project network. (b) Develop an activity schedule. Activity EarliestStart LatestStart EarliestFinish LatestFinish Slack A B C D E F (c) What are the critical activities? (Enter your answers as…arrow_forwardOffice Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop an activity schedule. What are the critical activities? (Enter your answers as a comma-separated list.) Assume that the company wants to complete the project in six months or 26 weeks. What is the amount of crash time (in weeks) for each activity that minimizes…arrow_forwardOffice Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop a project network. A project network with 8 activities and 8 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B and to activity C. Activity B is connected to activity D. Activity C is connected to activity E. Activity D is…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY