Textbook Question
Chapter 17, Problem 11P
The following precedence diagram reflects three time estimates in weeks for each activity. Determine:
a. The expected completion time for each path and its variance.
b. The probability that the project will require more than 49 weeks.
c. The probability that the project can be completed in 46 weeks or less.
Expert Solution & Answer
Trending nowThis is a popular solution!
Students have asked these similar questions
The following precedence diagram reflects three time estimates in weeks for each activity.Determine:a. The expected completion time for each path and its variance.b. The probability that the project will require more than 49 weeks.c. The probability that the project can be completed in 46 weeks or less.
Doug Casey is in charge of planning and coordinating next spring’s sales management training program for his company. Doug listed the following activity information for this project:
A. Draw a project network.
B. What are the critical activities and what is the expected project completion time?
C. If Doug wants a 0.99 probability of completing the project on time, how far ahead of the scheduled meeting date should he begin working on the project?
Draw a network representation of the project (nodes = activities, arrows = precedence constraints). Provide early start/early finish as well as late start/late finish times for all activities.
What is the duration of the project, and which tasks are on the critical path?
Task
Description
Duration
Predecessors
A
Project Planning
16 days
-
B
Evaluation Existing Apps
20 days
-
C
Define Value Proposition
12 days
B
D
Define User Interface
18 days
B
E
Define Technology Requirements
22 days
C and D
F
Document Requirements
14 days
E
G
Develop Architecture
35 days
A and F
H
Creation Code Design
18 days
G
I
Roadmap Feature Development
12 days
G
J
User Interface Development
74 days
H and I
K
Code Development
92 days
H and I
L
Release Testing
32 days
J and K
M
Get User Feedback
22 days
L
N
Bug Fixing
28 days
L
O
Marketing Plan
54 days
E
P
Release Product
5 days
M, N and O
Chapter 17 Solutions
EBK OPERATIONS MANAGEMENT
Ch. 17.3 - Will the AI technology render project managers...Ch. 17.3 - Prob. 1.2RQCh. 17 - A project manager may need two skill setsthose of...Ch. 17 - Explain the term project champion and list some...Ch. 17 - List the steps in risk management.Ch. 17 - Give some examples of ethical issues that may...Ch. 17 - What are the key advantages of using project...Ch. 17 - What is a work breakdown structure, and how is it...Ch. 17 - Identify the term being described for each of the...Ch. 17 - List the main advantages of PERT. List the main...
Ch. 17 - Why might a probabilistic estimate of a projects...Ch. 17 - Define each of these terms, and indicate how each...Ch. 17 - Why might a person wish to be involved with a...Ch. 17 - Prob. 12DRQCh. 17 - What are some aspects of the project managers job...Ch. 17 - What is the main benefit of a project organization...Ch. 17 - What trade-offs are associated with time and cost...Ch. 17 - Who needs to be involved in assessing the cost of...Ch. 17 - Prob. 3TSCh. 17 - Project management techniques have been used...Ch. 17 - Give three examples of unethical conduct involving...Ch. 17 - For each of the following network diagrams,...Ch. 17 - Chris received new word processing software for...Ch. 17 - Prepare a Gantt chart for each of the following in...Ch. 17 - a. Develop a list of activities and their...Ch. 17 - For each of the problems listed, determine the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Three recent college graduates have formed a...Ch. 17 - The new director of special events at a large...Ch. 17 - Prob. 9PCh. 17 - The project described in the following table is...Ch. 17 - The following precedence diagram reflects three...Ch. 17 - A project manager has compiled a list of major...Ch. 17 - Here is a list of activity times for a project as...Ch. 17 - The project manager of a task force planning the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Chucks Custom Boats (CCB) builds luxury yachts to...Ch. 17 - Prob. 17PCh. 17 - Create a risk matrix in the style of Figure 17.13...Ch. 17 - Create a risk matrix for this project: Explain...Ch. 17 - B. Smitty Smith is a project manager for a large...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The estimated times and immediate predecessorsfor the activities in a project at George Kyparis’s retinal scan-ning company are given in the following table. Assume thatthe activity times are independent. a) Calculate the expected time and variance for each activity.b) What is the expected completion time of the critical path?What is the expected completion time of the other path inthe network?c) What is the variance of the critical path? What is the vari-ance of the other path in the network?d) If the time to complete path A–C is normally distributed,what is the probability that this path will be finished in22 weeks or less?e) If the time to complete path B–D is normally distributed,what is the probability that this path will be finished in22 weeks or less?f) Explain why the probability that the critical path will befinished in 22 weeks or less is not necessarily the probabil-ity that the project will be finished in 22 weeks or less.arrow_forwardGiven the following table, construct a network diagram, either AOA or AON. Times are in days.a. Determine the expected duration of the project.b. Compute the probability that the project will take at least 18 days.Path Activity Time EstimatesA 4-5-6Top B 7-8-10C 3-5-9D 7-8-11Bottom E 2-3-4F 1-4-6arrow_forwardThe estimated times and immediate predecessors for the activities in a project a t George Kyparis's retinal scanning company are given in the following table. Assume that the activitytimes are independent. a) Calculate the expected time and variance for each activity.b) What is the expected completion time of the critical path?What is the expected completion time of the other path in the network?c) What is the variance of the critical path? Wha t is the variance of the other path in the network?d) If the time to complete path A-C is normally distributed, what is the probability that this path will be fini shed in 22 weeks or less?e) If the time to complete path B- D is normally distributed, what is the probability that this path will be finished in 22 weeks or less?f) Explain why the probability that the critical path will be finished in 22 weeks or…arrow_forward
- #3) Consider the following project, all durations are in days. Construct a precedence diagram, find the critical path and which tasks have slack and how much each has. Which tasks would you recommend crashing to reduce the project duration by six days assuming that it costs the same to crash each task and no task by be crashed to more than half its original duration and tasks A and N cannot be crashed at all? Task Predecessors Most Likely Duration A - 8 B A 12 C A 6 D A 12 E B 10 F E 7 G C 18 H C 13 I G 10 J H 13 K D 10 L K 11 M L 7 N F, I, J, M 4 Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forwardConsider the simple dependency matrix shown in Table 19.12.Which of the following statements is correct? a. The two activities are independent of each other and the project can carry out both of them immediately. b. A1 is a predecessor activity to A2. c. A2 is a predecessor activity to A1. d. None of these statements is correctarrow_forwardWhich project management approach follows a deterministic approach and assumes the activity duration is a known certainty? a) PERT b) CPM c) Network Diagram d) JIT e) ABCarrow_forward
- Key: A is optimist time, M is the most likely time and B is the pessimistic time. i). Calculate the expected time for each activity ii. Draw a Gantt Chart from the same information above iii. State the critical path and the maximum number of weeks the project will take to be completed. iv. Discuss the pros and cons of using the Gantt chart as a planning and scheduling tool?arrow_forwardDraw CPM network of activities tabulated below: 1. Calculate the expected duration and the standard deviation for the critical path. 2. Compute the followings: (a) The probability that the project will finish by the end of day 50 (b) The probability that the project will finish at day 52 (c) The probability that the project will finish before the start of day 49. (d) The completion date with at least a 95% confidence levelarrow_forwardThe Laurenster Corporation needs to set up an as-sembly line to produce a new product. The fol-lowing table describes the relationships among the activities that need to be completed for this productto be manufactured. (a) Develop a project network for this problem.(b) Determine the expected duration and variancefor each activity.arrow_forward
- The project manager must make trade-offs between project progress and process. Conceptually, this involves trade-offs between the __________ functions. a. schedule and cost b. technical and managerial c. cost and performance d. performance and schedulearrow_forwardYou may need to use the appropriate technology to answer this question. Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 43-week completion date requested by the owner. The Mueller project manager prepared the following project network. A project network with 10 activities and 14 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B, to activity C, and to activity D. Activity B is connected to activity F. Activity C is connected to activity E and to activity F. Activity D is connected to activity E. Activity E is connected to activity G and to activity Finish. Activity F is connected to activity G and to activity H. Activity G is connected to activity H. Activity H is connected to activity Finish. Activity Finish has no arcs directed to other activities. Estimates of the optimistic, most…arrow_forwardYou may need to use the appropriate technology to answer this question. Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 43-week completion date requested by the owner. The Mueller project manager prepared the following project network. A project network with 10 activities and 14 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B, to activity C, and to activity D. Activity B is connected to activity F. Activity C is connected to activity E and to activity F. Activity D is connected to activity E. Activity E is connected to activity G and to activity Finish. Activity F is connected to activity G and to activity H. Activity G is connected to activity H. Activity H is connected to activity Finish. Activity Finish has no arcs directed to other activities. Estimates of the optimistic, most…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY