Textbook Question
Chapter 17, Problem 12P
A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships.
a. Construct a network diagram. You can use either AOA or AON (see Example 5).
b. If the project is finished within 26 weeks of its start, the project manager will receive a bonus of $1,000; and if the project is finished within 27 weeks of its start, the bonus will be $500. Find the probability of each bonus.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
3.1 Draw an Activity-On-Arrow (AOA) network diagram representing the project. Put the nodenumbers in circles and draw arrows from node to node, labelling each arrow with theactivity letter and estimated duration. 3.2 Identify all the paths on the network diagram and note how long they are. 3.3 What is the critical path for this project and how long is it? 3.4 What is the shortest possible time needed to complete the project?
Please help in deatils to find the correct answers
Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 43-week completion date requested by the owner. The Mueller project manager prepared the following project network.
A project network with 10 activities and 14 directed arcs is shown.
Activity Start is connected to activity A.
Activity A is connected to activity B, to activity C, and to activity D.
Activity B is connected to activity F.
Activity C is connected to activity E and to activity F.
Activity D is connected to activity E.
Activity E is connected to activity G and to activity Finish.
Activity F is connected to activity G and to activity H.
Activity G is connected to activity H.
Activity H is connected to activity Finish.
Activity Finish has no arcs directed to other activities.
Estimates of the optimistic, most probable, and…
A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activitiesand precedence relationships.ActivityImmediatePredecessorEstimatedTimes (weeks)A — 2-4-6D A 6-8-10E D 7-9-12H E 2-3-5F A 3-4-8G F 5-7-9ActivityImmediatePredecessorEstimatedTimes (weeks)B — 2-2-3I B 2-3-6J I 3-4-5K J 4-5-8C — 5-8-12M C 1-1-1N M 6-7-11O N 8-9-13End H, G, K, Oa. Construct a network diagram. You can use either AOA or AON (see Example 5).b. If the project is finished within 26 weeks of its start, the project manager will receive a bonusof $1,000; and if the project is finished within 27 weeks of its start, the bonus will be $500.Find the probability of each bonus.
Chapter 17 Solutions
EBK OPERATIONS MANAGEMENT
Ch. 17.3 - Will the AI technology render project managers...Ch. 17.3 - Prob. 1.2RQCh. 17 - A project manager may need two skill setsthose of...Ch. 17 - Explain the term project champion and list some...Ch. 17 - List the steps in risk management.Ch. 17 - Give some examples of ethical issues that may...Ch. 17 - What are the key advantages of using project...Ch. 17 - What is a work breakdown structure, and how is it...Ch. 17 - Identify the term being described for each of the...Ch. 17 - List the main advantages of PERT. List the main...
Ch. 17 - Why might a probabilistic estimate of a projects...Ch. 17 - Define each of these terms, and indicate how each...Ch. 17 - Why might a person wish to be involved with a...Ch. 17 - Prob. 12DRQCh. 17 - What are some aspects of the project managers job...Ch. 17 - What is the main benefit of a project organization...Ch. 17 - What trade-offs are associated with time and cost...Ch. 17 - Who needs to be involved in assessing the cost of...Ch. 17 - Prob. 3TSCh. 17 - Project management techniques have been used...Ch. 17 - Give three examples of unethical conduct involving...Ch. 17 - For each of the following network diagrams,...Ch. 17 - Chris received new word processing software for...Ch. 17 - Prepare a Gantt chart for each of the following in...Ch. 17 - a. Develop a list of activities and their...Ch. 17 - For each of the problems listed, determine the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Three recent college graduates have formed a...Ch. 17 - The new director of special events at a large...Ch. 17 - Prob. 9PCh. 17 - The project described in the following table is...Ch. 17 - The following precedence diagram reflects three...Ch. 17 - A project manager has compiled a list of major...Ch. 17 - Here is a list of activity times for a project as...Ch. 17 - The project manager of a task force planning the...Ch. 17 - PRINTED BY: 92248ddb24ccbc6@placeholder.10274.edu....Ch. 17 - Chucks Custom Boats (CCB) builds luxury yachts to...Ch. 17 - Prob. 17PCh. 17 - Create a risk matrix in the style of Figure 17.13...Ch. 17 - Create a risk matrix for this project: Explain...Ch. 17 - B. Smitty Smith is a project manager for a large...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A plumber has decided to use the techniques of project management in order to plan a job. He knew all the different activities of the job, their precedence and their average durations. They are shown on the table below. Activity Duration (days) Preceding activities A 3 None B 3 None C 4 A D 8 A E 2 B and C Required: 1. Draw a network diagram representing the sequence of activities and the dependence between them. 2. Determine how long it will take to complete the job by conducting the forward pass 3. By conducting the backward pass, identify the critical path and the non-critical path(s). Note: The work for this task should be produced using Word drawing facilities. The forward and backward passes should be clearly shown on the diagram. The calculations should be shown next to the network diagram.arrow_forwarda. Draw a project network. b. What is the critical path? c. What is the normal project cost? d. What is the total cost of the project if you need to crash it by 1 week?arrow_forward#3) Consider the following project, all durations are in days. Construct a precedence diagram, find the critical path and which tasks have slack and how much each has. Which tasks would you recommend crashing to reduce the project duration by six days assuming that it costs the same to crash each task and no task by be crashed to more than half its original duration and tasks A and N cannot be crashed at all? Task Predecessors Most Likely Duration A - 8 B A 12 C A 6 D A 12 E B 10 F E 7 G C 18 H C 13 I G 10 J H 13 K D 10 L K 11 M L 7 N F, I, J, M 4 Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.arrow_forward
- a) Draw an AON diagram of the project, including activity durations. b) Define the critical path, listing all critical activities in chronological order. c) What is the project duration (in weeks)? d) What is the slack (in weeks) associated with any and all noncritical paths through the project?arrow_forwardA plumber has decided to use the techniques of project management in order to plan a job. He knew all the different activities of the job, their precedence and their average durations. They are shown on the table below.ActivityDuration (days)Preceding activitiesA3NoneB3NoneC4AD9AE4B and CRequired:1. Draw a network diagram representing the sequence of activities and the dependence between them.2. Determine how long it will take to complete the job by conducting the forward pass3. By conducting the backward pass, identify the critical path and the non-critical path(s).Note:The work for this task should be produced using Word drawing facilities. The forward and backward passes should be clearly shown on the diagram. The calculations should be shown next to the network diagram.arrow_forwardTo be able to meet delivery dates, a project consultant intimates that a project should be analyzed with activities as follows: ACTIVITY IMMEDIATE PREDECESSOR EXPECT DURATION (WEEKS) A. Initial discussion none 3 B. product design none 5 C. Market survey B 3 D. market evaluation A,C 4 E. product costing D 8 F. sales plan C 2 G. product pricing F 4 H. prototype F 2 I. master inform B 5 J.prototype testing HEG 3 (i) Draw a network to represent the various activities of the project.(ii) Draw up a table showing for each activity, the earliest and latest start and finish times and total float/slack.(iii) Determine the critical path and project duration.(iv) As a management science student, advise the management about the effect on the project completion time If the start time of activity A is delayed by 3weeks, activity G is delayed by 8 weeksarrow_forward
- DO THE FOLLOWING:1. Draw a network diagram representing the project. Put the node numbers in circles and draw arrowsfrom node to node, labelling each arrow with the activity letter and estimated time.2. Identify all the paths on the network diagram and note how long they are.3. What is the critical path for this project and how long is it?4. What is the shortest possible time needed to complete this project?arrow_forwardA project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships.Use Table B1 and Table B2. Activity ImmediatePredecessor Estimated Times(weeks) A — 2-4-6 D A 6-8-10 E D 7-9-12 H E 2-3-5 F A 3-4-8 G F 5-7-9 B — 2-2-3 I B 2-3-6 J I 3-4-5 K J 4-5-8 C — 5-8-12 M C 1-1-1 N M 6-7-11 O N 8-9-13 End H, G, K, O If the project is finished within 26 weeks of its start, the project manager will receive a bonus of $1,000; and if the project is finished within 27 weeks of its start, the bonus will be $500. Find the probability of each bonus. (Round Mean, Standard Deviation to 2 decimal places and Probability to 4 decimal places.) Path Mean Std. Dev. a-d-e-h 24.33 Numeric Response1. Edit Unavailable.24.33correct. 1.35 Numeric Response2. Edit Unavailable.1.35correct. a-f-g 15.50 Numeric…arrow_forwardA project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships.Use Table B1 and Table B2. Activity ImmediatePredecessor Estimated Times(weeks) A — 2-4-6 D A 6-8-10 E D 7-9-12 H E 2-3-5 F A 3-4-8 G F 5-7-9 B — 2-2-3 I B 2-3-6 J I 3-4-5 K J 4-5-8 C — 5-8-12 M C 1-1-1 N M 6-7-11 O N 8-9-13 End H, G, K, O If the project is finished within 26 weeks of its start, the project manager will receive a bonus of $1,000; and if the project is finished within 27 weeks of its start, the bonus will be $500. Find the probability of each bonus. (Round Mean, Standard Deviation, z-value to 2 decimal places and Probability to 4 decimal places.) Path Mean Std. Dev. a-d-e-h a-f-g b-i-j-k c-m-n-o Probability ($1,000) ______________________________ Probability…arrow_forward
- You may need to use the appropriate technology to answer this question. Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 43-week completion date requested by the owner. The Mueller project manager prepared the following project network. A project network with 10 activities and 14 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B, to activity C, and to activity D. Activity B is connected to activity F. Activity C is connected to activity E and to activity F. Activity D is connected to activity E. Activity E is connected to activity G and to activity Finish. Activity F is connected to activity G and to activity H. Activity G is connected to activity H. Activity H is connected to activity Finish. Activity Finish has no arcs directed to other activities. Estimates of the optimistic, most…arrow_forwardYou may need to use the appropriate technology to answer this question. Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 43-week completion date requested by the owner. The Mueller project manager prepared the following project network. A project network with 10 activities and 14 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B, to activity C, and to activity D. Activity B is connected to activity F. Activity C is connected to activity E and to activity F. Activity D is connected to activity E. Activity E is connected to activity G and to activity Finish. Activity F is connected to activity G and to activity H. Activity G is connected to activity H. Activity H is connected to activity Finish. Activity Finish has no arcs directed to other activities. Estimates of the optimistic, most…arrow_forward1. A project has been defined to contain the following list of activities along with their required times for completion. What would happen if activity 6 were revised to take 6 weeks instead of 1 week? 2. Construct a Gantt chart for the project defined in Problem 1.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY