Textbook Question
Chapter 19, Problem 5PA
A project activity has an earliest completion time of 5, an activity time of 3, and a latest completion time of 6. What is the slack time for the activity?
- a. 1
- b. 2
- c. 3
- d. 4
- e. 5
- f. 6
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Project 1-3: Creating a Project Schedule for Hiring a New EmployeeIn this project, you will create a project schedule for the process of hiring a new employee for your department.
GET READY. OPEN a new blank project schedule.
Set the project start date to be October 21, 2019.Enter the following tasks and durations:Task DurationWrite job description 2dNotify departmental recruiter 1dPost job internally 5dPost job externally 5dCollect résumés 10dReview résumés 5dSet up interviews 3dConduct interviews 8dSelect candidate 1dMake offer milestoneAssign a finish-to-start relationship to all the tasks.Change the relationship between tasks 3 and 4 to a start-to-start relationship.Auto-fit all the columns and rows.Change all tasks to the Automatically Scheduled mode.Use the statistics button on the Project Information dialog box to determine the current project duration.SAVE the project schedule in the solutions folder for this lesson as Hiring Employee xxd where…
a) Draw a schedule showing the work package critical path and duration. b) Assume the wor kpackage has to be completed within 44 weeks.Calculate the most costeffective way of completing the work package within this time, giving the costincrease associated with this crash sequence. c) Discuss the main factors likely to be considered by the project manager whenconsidering time– cost trade-offs and time–quality trade-offs as ways of reducingthe overall time required to complete a project or work package.
A project activity has an earliest completion time of 5, an activity time of 3, and a latestcompletion time of 6. What is the slack time for the activity?a. 1b. 2c. 3d. 4e. 5f. 6
Chapter 19 Solutions
OPERATIONS MANAGEMENT (LL)-W/ACCESS
Ch. 19 - A project has four activities that take 4, 3, 6,...Ch. 19 - Consider the simple dependency matrix shown in...Ch. 19 - Consider a project with two activities that are...Ch. 19 - Prob. 4CQCh. 19 - Prob. 5CQCh. 19 - Prob. 6CQCh. 19 - Prob. 7CQCh. 19 - Prob. 8CQCh. 19 - Prob. 9CQCh. 19 - Prob. 10CQ
Ch. 19 - Consider two projects that have the same...Ch. 19 - Prob. 12CQCh. 19 - Prob. 13CQCh. 19 - Prob. 14CQCh. 19 - The key objectives of a project are given by a....Ch. 19 - Which of the following descriptions best captures...Ch. 19 - Prob. 1PACh. 19 - Prob. 2PACh. 19 - Prob. 3PACh. 19 - Prob. 4PACh. 19 - A project activity has an earliest completion time...Ch. 19 - What is the definition of the latest completion...Ch. 19 - Which of the following statements is correct with...Ch. 19 - A project consists of three tasks: A, B, and C....Ch. 19 - Prob. 9PACh. 19 - Prob. 10PACh. 19 - You manage a project with 10 activities....Ch. 19 - Which of the following activities is not part of...Ch. 19 - You have been asked by the CEO of your company to...Ch. 19 - BUILDING A HOUSE IN THREE HOURS Habitat for...Ch. 19 - BUILDING A HOUSE IN THREE HOURS Habitat for...
Additional Business Textbook Solutions
Find more solutions based on key concepts
Mary Williams, owner of Williams Products, is evaluating whether to introduce a new product line. After thinkin...
Operations Management: Processes and Supply Chains (11th Edition)
2. Identify four people who have contributed to the theory and techniques of operations management.
Operations Management: Sustainability and Supply Chain Management (12th Edition)
2. In what circumstances might a market-pull approach or a technology-push approach to new-product design be th...
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Many companies including Company OM tried to implement dynamic pricing in their ticketing system. The dynamic p...
Principles of Operations Management: Sustainability and Supply Chain Management (10th Edition)
What is precedent, and how does it affect common law?
Business in Action (8th Edition)
What are the three major business functions, and how are they related to one another? Give specific examples.
Operations Management, Binder Ready Version: An Integrated Approach
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- a.How would you explain Project? One time activity to solve a problemb. Describe what happens after scope creep on a typical industrial project? increase inproject costarrow_forward114. Duration Task Estimates A ABCDE F 2 5 1 2 3 12 Click here for the Excel Data File Req B1 b-1. Identify the critical path. b-2. Identify the earliest start and finish. Task b-3. Identify the slack for each task. c. Which of these activities should the project manager track most closely? OUM TI Complete this question by entering your answers in the tabs below. D days days day F E F E F C days days days B A Immediate Predecessors None Identify the slack for each task. Note: Leave no cells blank - be certain to enter "0" wherever required. None A B A B and D E and C C, E B, D Immediate Successors Req B2 Req B3 Req C Latest Completion Latest Start (LS) Slackarrow_forwardProject scope (Per Chapter 4, this should be more detailed than the proposal scope)a. Project Objectivesb. Customer Requirementsc. Project Statement of Work (Tasks)d. Project Deliverablese. Project Acceptance/Success Criteria2. Provide Estimated Number of Workers Needed to Complete Project and their responsibilitiesa. Develop fictional people with professions needed to complete the project3. Provide a Task List/Work Breakdown Structure to divide the project into piecesa. Use graphical structure from pages 114-115 in text 4. Provide a Network Diagram for your project with estimated activity durations for each step. 5. Using a Project Schedule similar to page 161 in the text, provide a schedule for the project if wewere to start on June 1st, i.e. estimated time to completion and time to complete various tasksa. Need Earliest Start/Finish and Latest Start/Finish Calculations, and Slackb. Identify the Critical Path in your project6. Provide any risks that your team believes the…arrow_forward
- Often circumstances dictate the need to accelerate a project schedule. Describe howcrashing and fast tracking can be used to compress a project schedule. What limitationsdo you see with using each of these methodsarrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 7 − E 5 B B 8 − F 6 B C 4 A G 11 C, E D 3 A H 7 D , F Part 2 Dave's earliest start (ES) and earliest finish (EF) are: Part 3 Part 4 Part 5 Part 6 Part 7 Part 8 Part 9 Part 10 Dave's latest start (LS) and latest finish (LF) are:…arrow_forward2. A small software development project at Krishna Dhir's firm has five major activities. The times (in days) are estimated and provided in the table below: Activity Immediate Predecessor a m b A − 2 5 8 B − 3 6 9 C A 4 7 10 D B 2 5 14 E C 3 3 3 Part 2 d) The probability that it will take more than 17 days to complete this projectbe is __ (keep two decimal places). e) The due date that yields a 98% chance of completion is ____ days (keep two decimal places).arrow_forward
- Ans c. The earliest starting time for activity H is 15 days Ans d. The latest start time for activity J is 25 days. Ans e. The critical path is A-B-H-I-L-M with the minimum duration of the project as 28 days This is a follow up question please do f and garrow_forwardI need a detailed explanation and assistance to solve this problem: A company decides to plan a project, with activities, precedences and random duration statistics given in the following table: Activity Immediate Predecessors Duration Minimum (weeks) Duration Mode (weeks) Duration Maximum (weeks) A none 2 5 9 B A 1 6 8 C A 3 5 12 D B 2 4 12 E B, C 4 6 8 F B 6 7 8 G D, E 1 2 6 H F, G 4 6 16 * What method should be used? Compute the mean and variances for each activity and add them to the table above * Draw the project network and label the arcs with the activity name. * Assuming that the critical path is AàBàP1àEàGàH, compute the probability that this path duration is between 28 weeks and 32 weeks. * Assuming that the critical path is AàBàP1àEàGàH, compute the number of weeks within which the project will be completed with probability 0.95.arrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s) A 7 − E 4 B B 6 − F 5 B C 4 A G 10 C, E D 2 A H 8 D , F Part 2 Dave's earliest start (ES) and earliest finish (EF) are: Part 3 Part 4 Part 5 Part 6 Part 7 Part 8 Part 9 Part 10 Dave's latest start (LS) and latest finish (LF) are:…arrow_forward
- Don't use AI PERT and CPM are NOT used in which phase of project management? A Controlling B. Planning C. Scheduling D. PERT and CPM are used in all three phases GIVE CORRECT ANSWER WITH FULL EXPLANATIONarrow_forwardPlease help in deatils to find the correct answers Mueller & Associates is a urban planning firm that is designing a new public park in an Omaha suburb. Coordination of the architect and subcontractors will require a major effort to meet the 43-week completion date requested by the owner. The Mueller project manager prepared the following project network. A project network with 10 activities and 14 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B, to activity C, and to activity D. Activity B is connected to activity F. Activity C is connected to activity E and to activity F. Activity D is connected to activity E. Activity E is connected to activity G and to activity Finish. Activity F is connected to activity G and to activity H. Activity G is connected to activity H. Activity H is connected to activity Finish. Activity Finish has no arcs directed to other activities. Estimates of the optimistic, most probable, and…arrow_forwardExplain SEVEN (7) steps for Project Time Management Processes. What is Work Breakdown Structure (WBS) and state 3 advantages of WBS.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY