What is the definition of the latest completion time (LCT) of a project activity?
- a. LCT(Ai) = Max{LST(Aj) for which Aj is a successor of Ai}
- b. LCT(Ai) = Min{LST(Aj) for which Aj is a successor of Ai}
- c. LCT(Ai) = Max{LST(Aj) for which Aj is a predecessor of Ai}
- d. LCT(Ai) = Min{LST(Aj) for which Aj is a predecessor of Ai}
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
What happens as you increase the number of people working on a project from three to six?a. The project will get done twice as quickly.b. The communication requirements for the project double.c. The project might or might not be accelerated.d. The communication requirements for the project increase by far more than 2x.e. The project will get done twice as quickly and the communication requirements for theproject double.f. The project might or might not be accelerated and the communication requirementsfor the project increase by far more than 2x.
Management Firm is a consulting company that specializes in the development of decision support systems.
Time (Weeks)
Activity
Description
ImmediatePredecessor
Optimistic
Most Probable
Pessimistic
A
Report generation
2
8
12
B
Web scraping
4
9
11
C
Testing
A, B
1
1
1
(A)
Based solely on the critical path, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.)
(b)
Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.)
Which of the following statements is correct with respect to slack time?a. The slack time of an activity is the latest completion time of the activity minus theearliest completion time.b. The slack time of an activity is the latest start time of the activity minus the earliest start time.c. The slack time of an activity determines how long an activity can be delayed withoutimpacting the overall completion of the project.d. All of these statements are correct.
Chapter 19 Solutions
OPERATIONS MANAGEMENT (LL)-W/ACCESS
Ch. 19 - A project has four activities that take 4, 3, 6,...Ch. 19 - Consider the simple dependency matrix shown in...Ch. 19 - Consider a project with two activities that are...Ch. 19 - Prob. 4CQCh. 19 - Prob. 5CQCh. 19 - Prob. 6CQCh. 19 - Prob. 7CQCh. 19 - Prob. 8CQCh. 19 - Prob. 9CQCh. 19 - Prob. 10CQ
Ch. 19 - Consider two projects that have the same...Ch. 19 - Prob. 12CQCh. 19 - Prob. 13CQCh. 19 - Prob. 14CQCh. 19 - The key objectives of a project are given by a....Ch. 19 - Which of the following descriptions best captures...Ch. 19 - Prob. 1PACh. 19 - Prob. 2PACh. 19 - Prob. 3PACh. 19 - Prob. 4PACh. 19 - A project activity has an earliest completion time...Ch. 19 - What is the definition of the latest completion...Ch. 19 - Which of the following statements is correct with...Ch. 19 - A project consists of three tasks: A, B, and C....Ch. 19 - Prob. 9PACh. 19 - Prob. 10PACh. 19 - You manage a project with 10 activities....Ch. 19 - Which of the following activities is not part of...Ch. 19 - You have been asked by the CEO of your company to...Ch. 19 - BUILDING A HOUSE IN THREE HOURS Habitat for...Ch. 19 - BUILDING A HOUSE IN THREE HOURS Habitat for...
Additional Business Textbook Solutions
Find more solutions based on key concepts
What is precedent, and how does it affect common law?
Business in Action (8th Edition)
2. In what circumstances might a market-pull approach or a technology-push approach to new-product design be th...
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
2. Identify four people who have contributed to the theory and techniques of operations management.
Operations Management: Sustainability and Supply Chain Management (12th Edition)
There is a huge demand in the United States and elsewhere for affordable women’s clothing. Low-cost clothing re...
Loose-leaf for Operations Management (The Mcgraw-hill Series in Operations and Decision Sciences)
Mary Williams, owner of Williams Products, is evaluating whether to introduce a new product line. After thinkin...
Operations Management: Processes and Supply Chains (11th Edition)
The flowchart for the process at the local car wash. Introduction: Flowchart: A flowchart is a visualrepresenta...
Principles Of Operations Management
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings? (b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time? Activity Normal Duration (hours) Normal Cost ($) Crash Duration (hours) Crash Cost (S) Immediate Predecessors A 2 10 2 0 None B 3 15 2 23 A C 5 25 4 30 B D 3 20 1 24 C E 6 30 4 45 C F 1 5 1 0 E G 7 35 6 50 F H 10 50 7 80 D, Garrow_forward2.To obtain reasonable assurance about the completion of the project within the timeline, the best method is which of the following? Group of answer choices To compare the estimated end date and estimated time for completion of the project To obtain confirmation from the project manager about the project completion date To obtain confirmation from the project manager about the project completion date To extrapolate the end date on the basis of completed work and resource availability 15.From among the following activities, which is the best example of a project? Group of answer choices Writing a term paper Completing a college degree Producing automobiles Processing insurance claimsarrow_forwardTo obtain reasonable assurance about the completion of the project within the timeline, the best method is which of the following? To obtain affirmation from the project manager about the project completion date To extrapolate the end date based on completed work and resource availability To compare the estimated end date and estimated time for completion of the project To interpolate the end date based on completed work and resource availabilityarrow_forward
- Mangement Project management is the discipline of planning, organizing, motivating, and controlling resources to achieve specific goals and objectives within a specified time frame. It involves identifying project requirements, defining scope, establishing timelines, allocating resources, and managing risks. Project managers oversee the execution of projects, ensuring that they are completed on time, within budget, and according to quality standards. Effective project management requires strong leadership, communication, and problem-solving skills, as well as the ability to adapt to changing circumstances and stakeholders' needs. It is crucial for achieving project success and delivering value to stakeholders. Question: How does project management contribute to organizational efficiency and effectiveness?arrow_forwardYou are the project manager of the BTU AVIC project in Bolgatanga. As a result of the ongoing pandemic, you are responsible to ensure the project does not overly delay among other objectives. Required:a. Discuss five strategies for reducing the critical path of the BTU AVIC project.b. Explain five ways you can resolve the problem of resource allocation on the project. c. Using the Four-Stage Process of risk management discuss how risks could be managed on the ongoing BTU AVIC project. Identify three potential categories of team conflicts and how you will resolve such conflictsarrow_forwardThe client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing. (a) What is the crash cost for 8 hours of time-savings?(b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time?arrow_forward
- An IT company must complete a project with the following tasks listed A to G. ACTIVITY NORMAL DURATION (DAYS) CRASHED DURATION (DAYS) NORMAL COST ($) CRASHED COST ($) A 7 5 500 900 B 4 2 400 600 C 5 5 500 500 D 6 4 800 1000 E 7 4 700 1000 F 5 2 800 1400 G 6 4 800 1600 The following are all the paths in the project from start to end and the durations of each: A-B-E-G : 24 days A-C-E-G : 25 days A-C-F-G : 23 days A-D-F-G : 24 days Develop a crashing schedule to show which activities should be crashed to crash the project by 4 days and the lowest cost of doing so.arrow_forwardTo obtain reasonable assurance about the completion of the project within the timeline, the best method is which of the following? A. To interpolate the end date based on completed work and resource availability B. To obtain affirmation from the project manager about the project completion date C. To compare the estimated end date and estimated time for completion of the project D. To extrapolate the end date based on completed work and resource availability.arrow_forwardThis exercise tests your ability to come up with a detailed and elaborate Business Case for a project. One of the main responsibilities of an IT Project Manager is writing and defending Project Proposals, that is, justifying the need for the project. You need to explain the organization’s need(s), the current situation, and why your proposed solution will workAssume that you wish to import a 14-seater Public Service Vehicle (PSV) to ply route 14 (Town-Nairobi West-Madaraka) of Nairobi City. You need to compute the Total Cost of Ownership (TCO), that is, the cost of purchasing and maintaining the vehicle including the regulatory requirements. You are expected to take a loan at the prevailing rates and spread it as you wish (based on your assumptions-show the calculations). You then calculate projected income expected from the “Project” (again based on some assumptions which you need to state) and give a realistic position about the viability of getting into this “project”. You earn…arrow_forward
- Managing a project may be challenging, particularly when many departments must collaborate. When each department works on a project, they'll almost certainly employ a technique that they're most familiar with to get the outcomes they desire. Due to variations in approach and technique, this might make project cooperation across departments challenging. When working on a bigger project with multiple moving elements that must finally coordinate, project problems might arise. The project will slow down, become less productive, and potentially grind to a standstill if these pieces are not properly aligned. Project integration management is used to bring together the many departments and aspects of a project. Project integration management is a technique for coordinating many activities. It takes the many processes utilised in a project and ensures that they are coordinated. Making trade-offs is how project integration management does this. That implies you won't be able to have it all if…arrow_forwardFor this assignment, you will design a risk management plan for a project titled “prolonged waiting times for patients in a large outpatient hospital” that will include the following elements: Risk Register/Matrix (list of at least 5 (five) risks along with the associated impact and probability scores along with risk score) Contingency plan (list of any risks you will plan for in advance along with what triggers the contingency). Be sure to include any information useful to stakeholders on the rationale for the creation of these elements as well as any outside references supporting the risk management plan.arrow_forwardSubject : IT project management A project requires the conducting or performing of the following three tasks / activities to achieve the project objective: a) Requirements analysis b) Program design c) Program code using the project above , explain the difference between the two activity sequencing techniques (below) using fully labeled diagrams: 1) Activities performed serially 2) Laddering Required : Draw the diagrams - only use letters A, B and C instead of using full task names in labeling the diagram - Ensure that your diagrams use correct arrows to show the sequence of the activities.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY