Johnson Cogs wants to set up a line to serve 60 customers per hour. The work elements and their precedence relationships are shown in the following table.
- What is the theoretical minimum number of stations?
- How many stations are required using the longest work element decision rule?
- Suppose that a solution requiring five stations is obtained. What is its efficiency?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Johnson Cogs wants to set up a line to serve 60 customers perhour. The work elements and their precedence relationshipsare shown in the following table.a. What is the theoretical minimum number of stations?b. How many stations are required using the longest workelement decision rule?c. Suppose that a solution requiring five stations is obtained.What is its efficiency?
The Gardner Theater, a community playhouse, needs to determine the lowest-cost production budget for an upcoming show. Specifically, they have to determine which set pieces to construct and which, if any, set pieces to rent from another local theater at a predetermined fee. However, the organization has only two weeks to fully construct the set before the play goes into technical rehearsals. The theater has two part-time carpenters who work up to 12 hours a week, each at $10 an hour. Additionally, the theater has a part-time scenic artist who can work 15 hours per week to paint the set and props as needed at a rate of $15 per hour. The set design requires 20 flats (walls), two hanging drops with painted scenery, and three large wooden tables (props). The number of hours required for each piece for carpentry and painting is shown below:
Gardner Theater
Hours Required/Piece
Carpentry
Painting
Flats
0.5
2.0
Hanging Drops
2.0
12.0
Props
3.0
4.0
Hours Available
48.0…
Assign the 4 departments in Table X to locations A, B, C, and D, which are separated by the distances shown in Table y, in such a way that transportation cost is minimized. Use this heuristic: assign departments with the greatest interdepartmental workflow first. (See attached table)
Illustrate the configuration of the 4 departments in each of the 4 locations. Show the distances between departments and total interdepartmental workflows of department pairs.
Chapter 5 Solutions
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Ch. 5 - Take a process that you encounter on a daily...Ch. 5 - Prob. 2DQCh. 5 - How could the efficiency of the redesigned process...Ch. 5 - Bill’s Barbershop has two barbers available to...Ch. 5 - Melissa’s Photo Studio offers both individual...Ch. 5 - Figure 5.11 details the process flow for two types...Ch. 5 - Prob. 4PCh. 5 - Super Fun Industries manufactures four top-selling...Ch. 5 - Prob. 6PCh. 5 - Yost-Perry Industries (YPI) manufactures a mix of...
Ch. 5 - Prob. 8PCh. 5 - Prob. 9PCh. 5 - A.J.’s Wildlife Emporium manufactures two unique...Ch. 5 - Cooper River Glass Works (RGW) produces four...Ch. 5 - Quick Stop Pharmacy is a small family-owned,...Ch. 5 - Use the longest work element rule to balance the...Ch. 5 - Johnson Cogs wants to set up a line to serve 60...Ch. 5 - Refer back to Problem 16. Suppose that in addition...Ch. 5 - To meet holiday demand, Penny’s Pie Shop...Ch. 5 - A paced assembly line has been devised to...Ch. 5 - Prob. 20PCh. 5 - Greg Davis, a business major at the University of...Ch. 5 - Prob. 1VCCh. 5 - Which boarding scenario among the different ones...Ch. 5 - How should Southwest evaluate the gate boarding...Ch. 5 - How will Southwest know that the bottleneck had...
Additional Business Textbook Solutions
Find more solutions based on key concepts
Feeding America Each year, the Feeding America network helps provide food to more than 46 million people facing...
Operations and Supply Chain Management 9th edition
2. Identify four people who have contributed to the theory and techniques of operations management.
Operations Management: Sustainability and Supply Chain Management (12th Edition)
2. Identify four people who have contributed to the theory and techniques of operations management.
Operations Management
What is precedent, and how does it affect common law?
Business in Action
What are the three major business functions, and how are they related to one another? Give specific examples.
Operations Management, Binder Ready Version: An Integrated Approach
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A college provides free tutoring services for its students 7 days a week, and the daily requirements for tutors are: Day M T W Th F S Su Requirements 5 4 7 3 6 3 4 Find the minimum number of tutors required if each tutor works 4 days a week and has 3 consecutive days off. Give preference to Saturday and Sunday off in case of a tie. (Hint: Look for group of 3 days with the lowest requirements). Specify the work schedule for each tutor. How much slack does your schedule generate for each day?arrow_forward1. What’s the cycle time for this production line?2. What’s the theoretical minimum number of workstations that should be set up?3. List the paths for this problem.4. Draw the precedence diagram for this problem.5. How many workstations should be set up in this production line?6. Which tasks should be performed in each workstation?7. Draw the diagram of the production line.8. Calculate the efficiency of the production line.arrow_forwardThe Doan Modianos Manufacturing Company isputting out seven new electronic components. Each ofModianos'eight plants has the capacity to add one more product to its currentline of electronic parts. The unit manufacturing costs forproducing the different parts at the eight plants are shown in theaccompanying table. How should Modianos assign the new productsto the plants in order to minimize manufacturing costs?arrow_forward
- Show your step-by-step process using the SPECIAL PURPOSE LINEAR PROGRAMMING: ASSIGNMENT METHOD to solve this problem. Four Engineers are to work on 4 projects of Dora Company. The problem is to decide which engineer should be assigned to which project. Each engineer charges different fees on each project, due to distances of the projects and the complexity of the work. The cost of assigning particular engineers to particular projects are as stated below. The objective is to find the lease cost of assignment. Engineer 1 to Projects A, B, C, D = $11k, $8k, $10k, $7k respectively.Engineer 2 to Projects A, B, C, D = $6k, $5k, $3k, $8k respectively.Engineer 3 to Projects A, B, C, D = $4k, $8k, $10k, $9k respectively.Engineer 4 to Projects A, B, C, D = $11k, $10k, $5k, $7k respectively.arrow_forwardBaking dog treats in her kitchen has been a simple process for Emma to manage. She has two ovens, one sink, a refrigerator, and enough room for two people to work at the same time. However, when Emma moves her business out of her home, she will have a commercial kitchen that can accommodate as many as six people working simultaneously. She had never thought of her business as “production” until the real estate agent who showed her the space asked how many production workers she needs to accommodate. At that point, Emma realized she would be running a production system. Even worse, she realized that she had never even visited a manufacturing facility or set foot on a real production floor. How will she ever manage this process?arrow_forwardAs part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 250 units per 8-hour day. Task times and precedence relationships are as follows: Task Duration(minutes) ImmediatePredecessor a 0.5 - b 0.4 a c 0.5 b d 0.3 - e 1.8 d f 1.9 c g 2 e, f Do each of the following: a. Determine the number of followers for each task. (Please answer number of tasks following task for A-G)arrow_forward
- A group of six jobs is to be processed through a two-machine flow shop. The first operation involves cleaning and the second involves painting. Determine a sequence that willminimize the total completion time for this group of jobs. Processing times are as follows:PROCESSING TIME (hours)Job Work Center 1 Work Center 2A 5 5B 4 3C 8 9D 2 7E 6 8F 12 15 To employ Johnson’s rule, create a “blank” sequence first, such as:mhhe.com/stevenson13eEXAMPLE 41st 2nd 3rd 4th 5th 6tharrow_forwardA manufacturing system is used to produce a product.Each unit of product must be processed sequentially through workstations.V -----> W -----> X -----> Y The capacity of each workstation are as follows:Workstation V, 16 units per hour,Workstation W, 22 units per hour, Workstation X, 13 units per hour,Workstation Y, 18 units per hour. The raw material is always available in the front of workstation V. The manufacturing system has a cycle time of __________ minutes per unit. Use at least 4 decimals.You must show your calculation steps and brief explanation on your Excel spreadsheets.arrow_forwardHren Electronics is in process of setting a new office building. The following tables show the number of expected communications among the four departments and two possible layouts for considerations (tables 2 and 3 show the distance among the departments in the given layout). Calculate a total cost (or total distance traveled) for each layout and provide a recommendation that would minimize the total costs. Table 1. Number of transactions A B C D A 0 75 20 0 B 5 0 300 100 C 10 0 0 0 D 0 20 0 0 Table 2. Layout 1 (Walking distance in meters) A B C D A 0 10 20 30 B 10 0 10 20 C 20 10 0 10 D 30 20 10 0 Table 3 Layout 2 (Walking distance in meters) A B C D A 0 5 30 40 B 5 0 5 20 C 30 5 0 20 D 40 20 20 0arrow_forward
- Assign the 4 departments in Table X to locations A, B, C, and D, which are separated by the distances shown in Table y, in such a way that transportation cost is minimized. Use this heuristic: assign departments with the greatest interdepartmental workflow first. See attached table. a.Fill up the table attached. b. Compute the total transportation cost if the cost to move one workload 1 meter apart is P5.00.arrow_forwardMany business schools are increasing their offerings of internship and study abroad programs. In fact, some schools are requiring an internship and/or international study program as part of business degree requirements. They believe that on-the-job experience and global studies increase students’ knowledge base and employability. Consider the following variables for completing (1) an internship and (2) a study abroad program: costs (e.g., tuition, program fees, travel, lodging, food, and so on), timing (when these experiences are available and can be fit into your college years), options offered by your business school, and outcomes (how your preferences support your personal and professional growth). Construct a chart and then summarize the best plan for you to complete these experiencesarrow_forwardJeff Sowing Shop Jeff Sowing Shop was established in 2002 in downtown Kingston. The company currently employs one thousand five hundred (1,500) employees. In order to meet the Christmas demand, the company is considering employing an additional five hundred and fifty (550) workers and establishing a shift system. The first shift will work from 8 a.m. to 3 p.m. and the second shift from 3. p.m. to 11 p.m. Management took a decision not to pay a shift premium but told the workers in a meeting that they will be given a bonus at the end of the year providing the set targets are achieved. The workers were unhappy with the outcome of the meeting and decided to discuss the matter with their trade union. A delegation from the union met with management and the meeting ended in a stalemate. A second meeting was set to resolve the conflict. Prior to that meeting, management met and agreed that their position is right and they are not going to change. At the second meeting, both teams held their…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY