Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
12th Edition
ISBN: 9780134741062
Author: Lee J. Krajewski, Manoj K. Malhotra, Larry P. Ritzman
Publisher: PEARSON
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 5, Problem 18P
To meet holiday demand, Penny’s Pie Shop requires a production line that is capable of producing 50 pecan pies per week, while operating only 40 hours per week. There are only four steps required to produce a single pecan pie with respective processing times of 5 minutes, 5 minutes, 45 minutes, and 15 minutes.
- What should be the line’s cycle time?
- What is the smallest number of workstations Penny could hope for in designing the line considering this cycle time?
- Suppose that Penny finds a solution that requires only four stations. What would be the efficiency of this line?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
To meet holiday demand, Penny’s Pie Shop requires a pro-duction line that is capable of producing 50 pecan pies perweek, while operating only 40 hours per week. There areonly four steps required to produce a single pecan pie withrespective processing times of 5 minutes, 5 minutes, 45 min-utes, and 15 minutes.a. What should be the line’s cycle time?b. What is the smallest number of workstations Penny couldhope for in designing the line considering this cycletime?c. Suppose that Penny finds a solution that requires onlyfour stations. What would be the efficiency of this line?
Explain why doubling the capacity of a bottleneck may not double the system capacity?
Use a diagram to explain the concept of Throughput time and Bottleneck.
Mr. K’s is a very popular hair salon. It offers high-quality hair styling and physical relaxation services at a reasonable price, so it always has unlimited demand. The service process includes five activities that are conducted in the sequence described below. (The time required for each activity is shown in parenthesis):
Activity 1: Welcome a guest and offer homemade herb tea. (10 minutes)
Activity 2: Wash and condition hair. (10 minutes)
Activity 3: Neck, shoulder, and back stress release massage. (10 minutes)
Activity 4: Design the hairstyle and do the hair. (25 minutes)
Activity 5: Check out the guest. (5 minutes)
Three servers (S1, S2, and S3) offer the services in a worker-paced line. The assignment of tasks to servers is the following:
S1 does Activity 1.
S2 does Activities 2 and Activity 3.
S3 does Activities 4 and Activity 5.
a) Which server is the bottleneck of the process ?
b) What is the utilization of server 2 ?
c) What is the…
Chapter 5 Solutions
Operations Management: Processes and Supply Chains (12th Edition) (What's New in Operations Management)
Ch. 5 - Take a process that you encounter on a daily...Ch. 5 - Prob. 2DQCh. 5 - How could the efficiency of the redesigned process...Ch. 5 - Bill’s Barbershop has two barbers available to...Ch. 5 - Melissa’s Photo Studio offers both individual...Ch. 5 - Figure 5.11 details the process flow for two types...Ch. 5 - Prob. 4PCh. 5 - Super Fun Industries manufactures four top-selling...Ch. 5 - Prob. 6PCh. 5 - Yost-Perry Industries (YPI) manufactures a mix of...
Ch. 5 - Prob. 8PCh. 5 - Prob. 9PCh. 5 - A.J.’s Wildlife Emporium manufactures two unique...Ch. 5 - Cooper River Glass Works (RGW) produces four...Ch. 5 - Quick Stop Pharmacy is a small family-owned,...Ch. 5 - Use the longest work element rule to balance the...Ch. 5 - Johnson Cogs wants to set up a line to serve 60...Ch. 5 - Refer back to Problem 16. Suppose that in addition...Ch. 5 - To meet holiday demand, Penny’s Pie Shop...Ch. 5 - A paced assembly line has been devised to...Ch. 5 - Prob. 20PCh. 5 - Greg Davis, a business major at the University of...Ch. 5 - Prob. 1VCCh. 5 - Which boarding scenario among the different ones...Ch. 5 - How should Southwest evaluate the gate boarding...Ch. 5 - How will Southwest know that the bottleneck had...
Additional Business Textbook Solutions
Find more solutions based on key concepts
What is precedent, and how does it affect common law?
Business in Action (8th Edition)
What is precedent, and how does it affect common law?
Business in Action
2. Identify four people who have contributed to the theory and techniques of operations management.
Operations Management
The flowchart for the process at the local car wash. Introduction: Flowchart: A flowchart is a visualrepresenta...
Principles Of Operations Management
What are the three major business functions, and how are they related to one another? Give specific examples.
Operations Management, Binder Ready Version: An Integrated Approach
2. Identify four people who have contributed to the theory and techniques of operations management.
Operations Management: Sustainability and Supply Chain Management (12th Edition)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Positively Rivet Inc. is a small machine shop that produces sheet metal products. It had one line dedicated to the manufacture of light-duty vent hood shells, but because of strong demand it recently added a second line. The new line makes use of higher-capacity automated equipment but consists of the same basic four processes as the old line. In addition, the new line makes use of one machine per workstation, while the old line has parallel machines at the workstations. The processes, along with their machine rates, number of machines per station, and average times for a lone job to go through a station (i.e., not including queue time), are given for each line in the following table: Process Old Line New Line Rate per Machine (parts/hour) # Machines per Station Time (minute) Rate per Machine (parts/hour) # Machines per Station Time (minute) Punching 15 4 4.0 120 1 0.50 Braking 12 4 5.0 120 1 0.50 Assembly 20 2 3.0 125…arrow_forwardMr. Aris Benn manages an assembly line that produces a piece of equipment that is used to clean floors. The process to produce this piece of equipment consists of 10 steps. 1. Determine what other information is needed in order to balance this assembly line. 2. set up a numerical example of the line balancing problem at hand. Using this example, demonstrate how to balance the line and how to calculate its efficiency.arrow_forwardWAI is evaluating a new machine that reduces the machinetime needed for the standard corkscrew to 0.08 hour, but increasesthe machine time for the deluxe corkscrew to 0.40 hour.(a) Calculate the machine capacity needed for each period ifWAI uses the new machine.(b) Will the new machine prove benefi cial to WAI?arrow_forward
- a. what is the bottleneck of this process? b. what is the hourly capacity of the process?arrow_forwardA work cell at Chris Ellis Commercial Laundry hasa workstation with two machines, and each unit produced at thestation needs to be processed by both of the machines. (The sameunit cannot be worked on by both machines simultaneously.)Each machine has a production capacity of 4 un its per hour.What is the throughput time of the work cell?arrow_forwardIn a job shop, effective capacity is only 43 percent of design capacity, and actual output is 71 percent of effective output. What design capacity would be needed to achieve an actual output of 11 jobs per week? What is its effective capacity?a. The Design Capacity needed to achieve the required actual job outputs = (round to whole number)b. The Effective Capacity needed to achieve the required actual job outputs = (round to whole number)arrow_forward
- 1. A process is accomplished in 4 sequential steps- S1, S2, S3 and S4. The lead times (in minutes) and the number of resources for every step are indicated in the table below. Sub - Process Time (min) No of resources S1 12 1 S2 8 1 S3 16 1 S4 10 1 a.) Assuming infinite demand, what is the utilization of process S2? (answer in decimals) b.) If customers arrive at a constant rate of 3 customers per hour, what is the utilization of S3? (answer in decimals)arrow_forwardA production process at Kenneth Day Manufacturing is shown in Figure S7.9. The drilling operation occurs separately from, and simultaneously with, sawing and sanding, which are independent and sequential operations. A product needs to go through only one of the three assembly operations (the operations are in parallel).a) Which operation is the bottleneck?b) What is the bottleneck time?c) What is the throughput time of the overall system?d) If the firm operates 8 hours per day, 20 days per month, whatis the monthly capacity of the manufacturing process?arrow_forwardThree departments- milling (M), drilling (D), andsawing (S)- are assigned to three work areas in Victor Berardis'smachine shop in Kent, Ohio. The number of workpieces movedper day and the distances between the centers of the work areas,in feet, follow. Pieces Moved between Work Areas Each Day lt costs $2 to move I workpiece I foot.What is the cost?arrow_forward
- given information: which step is in bottleneck=30 min for tan leather 60/30=2 briefcases per hr are processed at the bottleneck workstation per hour throughput time of the overall process Throughput = 75 minutes PLEASE answer the following 3 questions: If the manufacturing facility operates 8 hours per day, 250 days a year, what is the annual capacity of this manufacturing process. Assume the company decides to hire additional workers in order to duplicate the bottleneck step identified in part a so that there are 3 of these workstations instead of 1. Redraw the diagram showing the flow of the revised process. Answer parts a through d again based on the new process created in part e?arrow_forwardExplain the techniques to deal with bottleneck operations and some of those techniques that does not decrease throughput time ?arrow_forwardAn output of 720 units per shift (7.40 hours) is desired for a new processing system. The system requires product to pass through four stations where the work content at each station is 26 seconds. What is the required cycle time for such a system? How efficient is your system with the cycle time calculated? Station 3 changes and now requires 50 seconds to complete. What will need to be done to meet demand (assume only 7.40 hours are available)? What is the efficiency of the new system?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY